Prevault sump water rerouted to Main Ring OTR installation in AP1. (Another OTR will go into AP2 later) A30 bakeout; reconnect (stacktail tank) D:EKIK pulsing by Tue eve (modules modified; motorized stand) Safety system tests Wed Power supplies on since Wed eve (D:IB Thu day)
E N D
Prevault sump water rerouted to Main Ring OTR installation in AP1. (Another OTR will go into AP2 later) A30 bakeout; reconnect (stacktail tank) D:EKIK pulsing by Tue eve (modules modified; motorized stand) Safety system tests Wed Power supplies on since Wed eve (D:IB Thu day) Mock RR transfers Thu (exercise Linux sequencer) First 8 GeV proton beam Thu (yesterday) eve?? Target vault is ready for 120 GeV beam Limit to 2.0E12 ppp or less until further notice!! Brief accesses to rings Wed; prevault Thu DRF1-4 PA tube, D6Q9 amp; OTR & sump follow-up Antiproton source startup reportBill Ashmanskas 2006-05-26
Measure stacktail proto #1 Aim to remove proto #2 next Fri Establish reverse protons all the way to Debuncher Check efficiencies, orbits, tunes, acceptances Establish stacking beam At most 2E12 ppp initially! 1-2 shifts tuning at low intensity Check accumulator cooling with antiprotons After proto tanks removed from Debuncher, optimize Debuncher acceptances and tune up stacking Rough plan Priorities • Fri: Accumulator reverse protons • Sat: Protons to Debuncher; work with MI to get beam to target? • Sun: Measure ST proto #1 • tbd: Accumulator running wave, AP2 trims, beamline BPMs & optics • Tue: ST proto tank swap; pump down • Wed: Measure proto tank #2 • Thu: Try to stack at a few mA/hr • Fri: ST proto out of Debuncher; study 120 GeV optics? • 3 shifts 2 people initially; • may drop owls after first week