Cryo Capture Cavity II Progress. Mike McGee April 6, 2005. DESY will Provide. 1.3 GHz cavity. Helium vessel. Magnet shielding (short). 2 VAT valves. Input coupler assembly. Status at Fermilab. Finalizing US AND DS warm-to-cold transition and VAT valve to cavity spool design.
E N D
Cryo Capture Cavity II Progress Mike McGee April 6, 2005
DESY will Provide • 1.3 GHz cavity • Helium vessel • Magnet shielding (short) • 2 VAT valves • Input coupler assembly
Status at Fermilab • Finalizing US AND DS warm-to-cold transition and VAT valve to cavity spool design • 316 L bellows specified and ordered (to arrive 4/24) • 316 LN material and tube ready to order • Designing VAT valve supports, shipping/installation fixture (to be made of 316 L)
Fermilab will Provide • To be send to DESY • Cleaned US and DS warm-to-cold transitions (w/isolation flanges on ends and slight positive Ar pressure) • Cleaned spool between cavity and VAT valve (also capped on ends) • Cleaned helium vessel support clamps • Cleaned VAT valve supports • Shipping/installation fixture • Drawing and procedure for assembly with fixture to be shipped
Fermilab will Provide • Currently at Fermilab • Vacuum vessel and instrumentation • 80 K shielding • 5 K manifold • Tuner • 2 Spare VAT valves
Send to DESY (May 2005) Process • Cleaned US and DS warm-to-cold transitions and spool • Under argon positive pressure valve w/filter blank flange
Process cont… • 2 helium vessel support clamps
Process cont… • VAT valve supports
Process cont… • Shipping/installation fixture with temporary supports for bellows with crate
Work at DESY (May-June 2005) Process cont… • Clean US and DS warm-to-cold transitions • Assemble • Cavity and helium vessel • Spool between VAT valve and cavity • VAT valves with supports • Warm-to-cold transition • Magnet shielding
Process cont… • Send to Fermilab (July 2005) • Assembled cavity with VAT valves, shielding, spool and transitions
Process cont… • Work at Fermilab (July-August 2005) • Pressure test helium vessel • Modify helium return • Install cavity assembly into vacuum vessel • Make up cryogenic connections • Test fit feedcan and leak check circuits
Process cont… • Install cavity assembly into vacuum vessel
Process cont… • Make up cryogenic connections • Test fit feedcan and leak check circuits • Commission Cryo Capture Cavity II
Questions and Requests Need DESY cleaning procedure Need to confirm critical measurements