1 / 32

WS Infrastructure Programme Quarterly Workshop EASTERN CAPE (MPEKWENI BEACH RESORT)

WS Infrastructure Programme Quarterly Workshop EASTERN CAPE (MPEKWENI BEACH RESORT) Limpopo Region Date: 31 October 2013. Contents. A: Expenditure Status 2013/14 RBIG MWIG ACIP NTP B: Key Challenges C: Projects to be “Fast Tracked” D: Projects to be Launched.

sanjiv
Download Presentation

WS Infrastructure Programme Quarterly Workshop EASTERN CAPE (MPEKWENI BEACH RESORT)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WS Infrastructure Programme Quarterly Workshop EASTERN CAPE (MPEKWENI BEACH RESORT) Limpopo Region Date: 31 October 2013

  2. Contents A: Expenditure Status 2013/14 • RBIG • MWIG • ACIP • NTP B: Key Challenges C: Projects to be “Fast Tracked” D: Projects to be Launched LIMPOPO

  3. A1. RBIG : Expenditure 2013/14

  4. A1. RBIG : Re-allocation & Progress

  5. A1. RBIG : Re-allocation & Progress

  6. A1. IRS : Expenditure & Progress

  7. MWIG PROJECTS

  8. MWIG MTEF ALLOCATIONS

  9. MWIG TRANSFER SCHEDULE

  10. STATUS IN MOPANI DM Implementation not yet started Term contracts expired in August & extended for a period of 3 months New term contract appointments to be finalised in October 2013 A tender for a consultant who will assist with the BOQ advertised and is at evaluation stage. Notice to withhold funds issued

  11. STATUS IN VHEMBE DM Implementation started Two consultants appointed for verification of scope of work & monitoring performance DM experienced labour unrest & this affects verification of scope of work

  12. STATUS IN SEKHUKHUNE DM Implementation started Appointed 7 term contractors

  13. STATUS IN CAPRICORN DM Implementation started Have an intention of utilising DWA term contractors

  14. CONCLUSION & ACTION PLAN Bi lateral meetings are held with DMs to track progress, discuss challenges & to map a way-forward To request a special transfer date for Mopani & Vhembe

  15. ACIP PROJECTS

  16. A1. ACIP : Expenditure 2013/14

  17. B: Key Challenges • MWIG • non-reporting by District Municipalities • slow implementation caused by the delay in the appointment of term contractors.

  18. B: Key Challenges (RBIG & ACIP) • Discovery of hard-rock on pipeline and WTW projects resulting in delays and escalations in project costs • Complicated implementation models i.e. appointments of four contractors on one project e.g. one for excavating, one for preparing of bedding, one for laying pipes, & one for back-filling • Interference by politicians in appointments of incompetent contractors • Delays in the payment of contractors resulting in stoppage of work • ACIP projects implemented by Municipalities are not performing • Interference by politicians in appointments of incompetent contractors • Duplication of payment certificates by WSAs i.e. Sekhukhune DM • DWA Finance (HO) taking too long to give proper direction as to how DWA Construction should be re-imbursed for work done i.e. Moutse BWS (already R27 million incurred but could not be paid)

  19. NTP PROJECTS

  20. A4: NTP LP – Expenditure 2013/14 * Transfer of refurbishment funds took place during October 2013

  21. A4: NTP LP – Expenditure 2012/13

  22. A4: NTP – Expenditure 2012/13

  23. A4: NTP – Expenditure 2012/13

  24. A4: NTP SDM – Expenditure 2012/13

  25. A4: NTP SDM – Expenditure 2012/13

  26. A4: NTP MLM – Expenditure 2012/13

  27. A4: NTP MDM – Expenditure 2012/13

  28. B: Key Challenges • Slow projects implementation progress [All WSA’s] • Delay in submitting proof of payments (Physical progress and financial progress do not match) [All WSA’s]

  29. C: Project to be “Fast Track” RBIG • Moutse BWS: current estimated completion: March 2015 – (total project cost: R626 million) • SinthumuleKutama BWS (Valdezia to Mowkop bulk pipeline) : current estimated completion: June 2015 - (total project cost: R523 million) • Giyani BWS (drought relief): current estimated completion: August 2014 (total project cost: R254 million)

  30. D: Projects to be Launched • Mahlakwena Water Supply (ACIP) will be completed by end of November 2013, but water will not be available pending the finalisation of agreement between Sekhukhune DM and Lebalelo Water User Association. • Middle Letaba Water Supply ACIP)(Muyexe Water Crisis Intervention) will be completed by end of November 2013 pending electrification of boreholes by ESKOM (meeting to be arranged with ESKOM by next week (04-8 Nov 2013)) • Mogalakwena Bulk Water Supply (project 5 - construction of a 10,070km, 1000mm diameter steel pipeline from Piet se Kop Reservoir to Tshamahanzi. To be completed by December 2013

  31. ThanksQuestions Northern Cape

  32. End

More Related