An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lutheran Church of the Good ShepherdBuilding Committee UpdateMay 2014

  2. Coordinated with AT Architecture to develop the Phase 1 construction documents • Contracted with SK Geotechnical firm for a soils analysis of the future building site • Committee toured the new Atonement Lutheran Church and discussed with them how that facility design was developed and constructed • Toured the new addition to Apostle Lutheran Church. Building Committee Activities

  3. Geotechnical Report Bore 6 holes 4 of the holes were drilled in the approximate location of the new building corners 2 were drilled in the approximate location of the new parking lot

  4. Good construction soils and complex foundation construction will not be required • Groundwater was found at an elevation roughly 10 feet below the parking lot • The groundwater will necessitate a continuous foundation drain and permanent sump pumps • The new south parking lot will not be paved for a year to allow for settling Geotechnical Report Continued

  5. Construct the entire Education Building shell • Completely finish the first floor • Finish the majority of the basement • Complete the basement connection from the new addition to the existing building. • Demolish the A frame and the existing education wing to the Fireside room • Construct the new south parking lot (see note in Geotechnical report) Phase 1

  6. The first floor will house the pre school • The first floor will provide temporary office space for the staff and pastors • The finished portion of the basement will be at a lower quality at this time to save money • The rough approximate median construction cost for this first phase is $2,660,600. Phase 1 continued

  7. Additional Option Items will be constructed if funding is available: • Option 1 - Add Narthex - $440,000 • Option 2 - Finish 2nd Floor - $250,000 • Option 3 - Finish 3rd Floor - $120,000 • Option 4 - Finish Basement - $50,000 • Option 5 - Add South Entry - $30,000 • The above cost are budgetary and will be refined as the project proceeds. Inflationary pressures can change material costs in a very short time and have not been accounted for in these estimates. Additional Option Items

  8. Acquisition Process • The building committee recommends that a Design-Build approach be utilized • This will involve developing criteria • Issue a Request for Proposal to potential contractors • Interview Potential Construction Contractors • Award the Contract

  9. Timeline • Currently – continue raising funds through the capital campaign • Our current campaign has collected $566,000 • We have spent $82,863 • The current balance is $496,400 • Once there a $900,000 in the capital fund the building committee will send out the Request for Proposal to the Contractors • Once there is a $1,000,000 in the capital campaign fund we will begin construction. • Kick off a second capital campaign in September 2015

  10. Building Fund Expenses • AT Architecture $28,678 • Bauer Group $15,415 • Hi Tech Construction $ 2,757 • Kairos/Fund Raising $30,031 • Rocky Mountain Doors $ 1,181 • SK Geotechnical $4,800

  11. Mortgage Scenario • Projected amount of initial loan 1.5 million • Today’s rate 6% over 25 years (Thrivent’s current rate) • Projected monthly payments $10,300 • Our current capital appeal monthly income is $25,000 • Goal is to retire this debt and then plan Phase 2

  12. Next Steps • Continue raising funds through the Capital Appeal. (Begin a second capital campaign in September 2015) • Explore Financing Options • ELCA’s Mission Investment Fund • Thrivent • Local options • Refine the design build and the Request for Proposal Information

  13. Next Steps Continues • Communication Person(s) to join the Building Committee • Phase I - Space Use Task Force To Include but not be limited to: • Sunday School Teachers • Pastoral Staff • Office Staff • Music • Youth