260 likes | 333 Views
Location Map. Preliminary Hearing. Give Opportunity for Property Owners to See Plans and Give Comment Awareness Time to Adjust Plans Timeframe Assessments. Infrastructure Replaced. Water Mains & Services to Property Line Sanitary Sewer & Services to Property Line
E N D
Preliminary Hearing • Give Opportunity for Property Owners to See Plans and Give Comment • Awareness • Time to Adjust Plans • Timeframe • Assessments
Infrastructure Replaced • Water Mains & Services to Property Line • Sanitary Sewer & Services to Property Line • Storm Sewer Mains & Catch Basins • Curb & Gutter & Driveway Aprons • Road Surface – Asphalt
Assessments • Preliminary Amounts • Actual Assessment • End of Project • Mailed Notice • Hearing Date • Property Owner must give written notice before hearing of intent to appeal • Following year after construction and over life of financing
Assessment Policy • Water & Sewer Mains – paid for by rates • Laterals to property – assessed • Street surface – 30% of 36 ft. residential/7 ton design (70% is city’s cost) • Storm Sewer – also paid for by rates
Estimated Total Costs • Total Project Cost Estimate: Roadway - $1,413,100 Storm Sewer - $196,100 Sewer - $115,300 Water - $423,900 Total - $2,148,400
Estimated Local (City) Costs • Water main construction - $423,900 City – $296,190 Property Owners – $127,710 (Estimate per service - $2,365) • Sanitary Sewer construction - $115,300 City - $95,200 Property Owners - $20,100 (Estimate per service - $2,010)
Estimated Local Costs (cont.) • Street construction - $1,413,100 City – $909,600 Property Owners – $503,500 (Estimate per front foot - $79.50)
Deferment • Senior Citizens over 65 or Active Military Duty Persons • Must have income less than 60% of median income • Deferment reviewed each year • Deferment due upon death, sale, loss of homestead status, no hardship or failure to renew yearly.
Funding • Bonding • Utility Funds • Assessments