Manassas City Public Schools. Johnson WING Renovation & Breezeway. Location of new Baldwin School. Johnson Wing. Location of future Osbourn HS ballfields , support buildings, and Johnson Wing connecting breezeway/canopy. Project Schedule:. Design Schedule: Aug 2013 – Dec 2013
E N D
Manassas City Public Schools Johnson WING Renovation& Breezeway
Location of new Baldwin School Johnson Wing Location of future Osbourn HS ballfields, support buildings, and Johnson Wing connecting breezeway/canopy
Project Schedule: • Design Schedule: Aug 2013 – Dec 2013 • Bidding period: Jan 2014 • Award for construction: Feb 2014 • Construction: Feb 2014 – Aug 2014 • Occupy new space: Aug 2014 - Sep 2014 • Construction of breezeway: Jun 2016 – Aug 2016 (with construction of Osbourn HS ball fields)