Long Term Power Outage Regional Workshop. OJA Representatives Michael Pohlman Jennifer Lord. Welcome!. Thank you Regional Point of Contact. Project Timeline. February, 2009 Initial planning meetings were held in Clark County. March, 2009
E N D
Long Term Power Outage Regional Workshop OJA Representatives Michael Pohlman Jennifer Lord
Welcome! • Thank you • Regional Point of Contact
Project Timeline • February, 2009 • Initial planning meetings were held in Clark County. • March, 2009 • A draft project timeline was prepared and reviewed. • April, 2009 • A standing planning meeting schedule was prepared and planning team membership was determined. • May, 2009 • A letter to WEMA Board Members was submitted to solicit support for the project as a statewide exercise. • September, 2009 • A Homeland Security Grant was prepared to seek funding for the project. Regional Fiscal agents would be needed.The Workshop agenda was drafted and potential guest speakers were contacted.
Project Timeline • October, 2009 • The Homeland Security Grant Announcement was released and the Workshop Incident Action Plan documents were drafted for the selected functions (fuel supply, community-based residential facilities and special needs independent populations). • November, 2009 • The exercise schedule was developed and exercise planning team formed. Counties were polled for anticipated workshop and exercise participation. • December, 2009 • Dates for Workshops were determined. Workshop documents finalized. • January, 2010 • Registration for Workshops begun and exercise design drafted. October, 2009 The Homeland Security Grant Announcement was released and the Workshop Incident Action Plan documents were drafted for the selected functions (fuel supply, community-based residential facilities and special needs independent populations). November, 2009 The exercise schedule was developed and exercise planning team formed. Counties were polled for anticipated workshop and exercise participation. December, 2009 Dates for Workshops were determined. Workshop documents finalized. January, 2010 Registration for Workshops begun and exercise design drafted.
Mark Garland • Communications Researcher, MSU Center for Telecommunications Systems Management