1 / 10

K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011

SEE upsets in collimator control Mitigation options. K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011. Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team. R2E events.

seoras
Download Presentation

K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SEE upsets in collimator control Mitigation options K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team

  2. R2E events • - 1rst May 2011: SEU in UJ14 collimation control rack -> beam dump • (see presentation of Markus in LMC 4th May) • 5th May 2011: emergency action plan request • May 2011: SEU in UJ14/16 cryogenics • SEU in UJ14/16 biometry ; • SEU in others areas (see RADWG for details) TODAY cryogenics UL16 collimation QPS current leads heaters UJ16 transport reserved volume UJ14/16 racks layout PC PIC BPM Courtesy A. Tursun, Y. Muttoni PC spare Symmetrical layout in UJ14 LMC, 25 May 2011, A. L. Perrot1

  3. Mitigation options • 4 mitigation options can be considered • Option # 0: full relocation + shielding • activities during 7 months for 10 groups • Option # 1: relocate only the 2 collimation racks • Option # 2: relocate all the racks except the Power Converters • Option # 3: shielding • Duration & sequence optimized with Katy, EN/EL & EN/HE LMC, 25 May 2011, A. L. Perrot 2

  4. Option 1- collimation racks relocation Time estimation per side Time estimation for both sides EN/EL 7 days activity EN/STI 10 days activity Total= 15 days Work anticipation in a Technical Stop Phase I: EL (cables + optical fibers) 5 days during 1 TS Phase II: EL (cables connection), EN/STI 12 days emergency or Christmas break Advantage: EL manpower available for other activities during ‘Christmas break’ Partial equipment relocation not an effective R2E approach LMC, 25 May 2011, A. L. Perrot 3

  5. Option 2 – UJ14/16 racks relocation RYCA01 RYCA02 UL16 after relocation RYMCB01 RYMCB02 RYMCB03 RYMCB04 TODAY PC cryogenics (profibus-> moves FIP -> stays) RYLC01 RYLB01 RYMCC01 QYC02 collimation QYC01 RTQX2.R1 exclusion area Courtesy P. Orlandi, JC Guillaume RQX.R1 QPS current leads heaters UJ14/16 racks layout UJ16 UL16 Relocation 6 racks /side (without power converters) 5 groups impacted RYSC01 transport reserved volume PC spare PIC BPM CYCIP01 +DYPG02 DYPG01 Courtesy A. Tursun, Y. Muttoni TYCFL01 LMC, 25 May 2011, A. L. Perrot 4

  6. Option 2 – UJ14/16 racks relocation Fluence decrease by factor 8-30 ‘crash program for EN/EL’ possible manpower issue for the other activities co-activity Study under progress Christmas break 2011-2012: 11 weeks activities in tunnel Conclusion: not possible to relocate the 12 racks during next Christmas break LMC, 25 May 2011, A. L. Perrot 5

  7. Option 3 - Shielding RB16 RB16 UJ16 UJ17 UJ16 L shielding= 28 m After relocation & shielding UJ17 UL16 CourtesyF.Delsaux Courtesy JP Corso Shielding installation in RB16 CourtesyF.Delsaux LMC, 25 May 2011, A. L. Perrot 6

  8. Option 3 - Shielding Fluence decrease by factor 7-10 Time estimation for both sides Parallel activities Empty He liquid in 1 sector Depressurize the triplet He line (discussed with Safety) EN/HE: manpower effort (*) if chicane replaced by a ‘plug’ -> 2 additional weeks ALARA : installation during Christmas break (residual dose rate along the triplets) Conclusion: shielding installation could be scheduled for next Christmas break LMC, 25 May 2011, A. L. Perrot 7

  9. Options comparison Courtesy K. Foraz, M. Brugger & R2E simulation team (*) EN/EL ‘crash program’ (**) depending of the location General remark: co-activity not possible between shielding & relocation (~1000 transports of blocks are foreseen in each UL i.e. lift 4000 up/down) LMC, 25 May 2011, A. L. Perrot 8

  10. Conclusions • R2E proposals: • No independent equipment relocation unless clear impact on LHC operation • Shielding installation during next Christmas break (ALARA) R2E monitors constantly radiation levels, failures & scenarios ‘R2E review’ in November: presentation/discussions of the optimization solutions LMC, 25 May 2011, A. L. Perrot 9

More Related