120 likes | 202 Views
14 th January , 2019. SM18 Shutdown 2019 CE Work. T . Barbé R. Rouzet M . Pezzetti. Shutdown CE tasks. CE tasks from last year Shutdown Communication PLC to/from CTH APAVE remark + CTH labelling In progress Work order Other 24VDC new rack for Linde cabinet for CB
E N D
14thJanuary, 2019 SM18 Shutdown 2019 CE Work T. Barbé R. Rouzet M. Pezzetti
Shutdown CE tasks CE tasks from last year Shutdown • Communication PLC to/from CTH • APAVE remark + CTH labelling In progress Work order Other • 24VDC new rack for Linde cabinet for CB • 24VDC new rack for Linde cabinet for CP • PV915 installation for new liquefier • Replace buffer CV with PV
Communication PLC • BE-ICS communication from SIEMENS to SCHNEIDER is still not mature enough Postponed
APAVE remark + CTH labelling • Status from 2018 shutdown APAVE remark concern mainly labelling (fuse) to finish CTH labelling started but time consuming
Main valve box change for new lique • WO25155913 : mettre des Siparts sur les vannes CV Kammer du 25000 litres (CV921,CV913,CV922, (CV900 optional) More impact on ME side To be confirmed by ME if we proceed • PV915 installation for new liquefier will probably be a CV (CV910 is currently not used and can be used) linked to Infra PLC • PV911 new PV on Infra PLC • HV914 / HV936 changed from HV to PV • CV938 changed to HV Spare link between Infra PLC cabinet and Valve box fieldbox P06 – 10wires 5 signals P27 – 4 wires 2 signals P29 – 8 wires 4 signals Total of 11 signals Total spare in Infra PLC: 34 DI 59 AI 27 DO 30 AO HW : Thanks to new infra cabinet, integration will be easy. Still waiting for exact confirmation from ME team but spare link should be sufficient. Possible to prepare a lot before the shutdown SW : Logic to be defined
New Cryoplant interface • Power supply • 3.3kV and 400V needs already discussed and validated with EN/EL, EN/EL will installed cables up to the new cabinets • 24VDC, 2 standard racks in preparation for new CP and CB (designed by Andrzej and Remy). We will have to pull cables between the new racks and LKT cabinets • TN network, request done and managed by Remy
SH18 buffer -- Status • Following 2017 shutdown, we found out that cable are in bad condition (WO 24573025) • WO22076501 +CRYOTESTF-137, CV have old positioner and have to be upgraded CV function not needed they can be replaced with PV • New buffers will be installed when both cryoplants will be on at the same time (for string 3) • Need for control over buffer even if 6kW CP is down
SH18 buffer -- Proposal • Complete refurbishment of the area • Buffer and Burkhardt needs to be controlled by a system independent of existing CP. 2019 : New rack with independent M580 PLC + RIO 2020 : M580 PLC moved to Infra Cabinet and RIO linked with fiber optic PLC RIO
SH18 buffer – Estim. work • New cabinet • Estimated I/O • 11 Buffer with per buffer :1PT + 1PV + 2HV • 22DI +11DO+11AI • PV185 - PV186 – PV187- PV188 • 4DO + 8DI • Burkhardt • CP1 17DI + 2DO + 6 AI • CP2 16DI + 2DO + 8AI • CP3 15DI + 2DO + 2AI • Total 70DI + 21DO + 27AI • Cost for PLC cards
SH18 buffer – Estim. work • Cabinet design • 3weeks • Cabinet construction • 4weeks 1 FSU • Cabinet installation • 4weeks 2 FSU (can start before the shutdown)