An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 14thJanuary, 2019 SM18 Shutdown 2019 CE Work T. Barbé R. Rouzet M. Pezzetti

  2. Shutdown CE tasks CE tasks from last year Shutdown • Communication PLC to/from CTH • APAVE remark + CTH labelling In progress Work order Other • 24VDC new rack for Linde cabinet for CB • 24VDC new rack for Linde cabinet for CP • PV915 installation for new liquefier • Replace buffer CV with PV

  3. Communication PLC • BE-ICS communication from SIEMENS to SCHNEIDER is still not mature enough  Postponed

  4. APAVE remark + CTH labelling • Status from 2018 shutdown APAVE remark concern mainly labelling (fuse)  to finish CTH labelling started but time consuming

  5. Main valve box change for new lique • WO25155913 : mettre des Siparts sur les vannes CV Kammer du 25000 litres (CV921,CV913,CV922, (CV900 optional) More impact on ME side  To be confirmed by ME if we proceed • PV915 installation for new liquefier will probably be a CV (CV910 is currently not used and can be used) linked to Infra PLC • PV911 new PV on Infra PLC • HV914 / HV936 changed from HV to PV • CV938 changed to HV Spare link between Infra PLC cabinet and Valve box fieldbox P06 – 10wires  5 signals P27 – 4 wires  2 signals P29 – 8 wires  4 signals Total of 11 signals Total spare in Infra PLC: 34 DI 59 AI 27 DO 30 AO HW : Thanks to new infra cabinet, integration will be easy. Still waiting for exact confirmation from ME team but spare link should be sufficient. Possible to prepare a lot before the shutdown SW : Logic to be defined

  6. New Cryoplant interface • Power supply • 3.3kV and 400V needs already discussed and validated with EN/EL, EN/EL will installed cables up to the new cabinets • 24VDC, 2 standard racks in preparation for new CP and CB (designed by Andrzej and Remy). We will have to pull cables between the new racks and LKT cabinets • TN network, request done and managed by Remy

  7. SH18 buffer -- Status • Following 2017 shutdown, we found out that cable are in bad condition (WO 24573025) • WO22076501 +CRYOTESTF-137, CV have old positioner and have to be upgraded  CV function not needed they can be replaced with PV • New buffers will be installed when both cryoplants will be on at the same time (for string 3) • Need for control over buffer even if 6kW CP is down

  8. SH18 buffer -- Proposal • Complete refurbishment of the area • Buffer and Burkhardt needs to be controlled by a system independent of existing CP. 2019 : New rack with independent M580 PLC + RIO 2020 : M580 PLC moved to Infra Cabinet and RIO linked with fiber optic PLC RIO

  9. SH18 buffer – Estim. work • New cabinet • Estimated I/O • 11 Buffer with per buffer :1PT + 1PV + 2HV • 22DI +11DO+11AI • PV185 - PV186 – PV187- PV188 • 4DO + 8DI • Burkhardt • CP1 17DI + 2DO + 6 AI • CP2 16DI + 2DO + 8AI • CP3 15DI + 2DO + 2AI • Total 70DI + 21DO + 27AI • Cost for PLC cards

  10. SH18 buffer – Estim. work • Cabinet design • 3weeks • Cabinet construction • 4weeks 1 FSU • Cabinet installation • 4weeks 2 FSU (can start before the shutdown)