1 / 26

Cons Gattuso AD Shutdown Installation Manager

Cons Gattuso AD Shutdown Installation Manager . DOE Accelerator Safety Workshop Summer Shutdown Planning September 20-22, 2016. Outline. Introduction to Accelerator complex Shutdown planning and execution Planning Timeline: Scope of Work Prioritization Resource Allocation Job Planning

serenity
Download Presentation

Cons Gattuso AD Shutdown Installation Manager

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cons Gattuso AD Shutdown Installation Manager DOE Accelerator Safety Workshop Summer Shutdown Planning September 20-22, 2016

  2. Outline • Introduction to Accelerator complex • Shutdown planning and execution • Planning Timeline: • Scope of Work Prioritization • Resource Allocation • Job Planning • ALARA planning • Pre/post shutdown work • Hazard mitigation C. Gattuso | Summer Shutdown Planning

  3. Fermilab Accelerator Complex Shutdown coordination covers the above along with maintenance and power outages. Second biggest accelerator complex in the world C. Gattuso | Summer Shutdown Planning

  4. Accelerator Division Summer Shutdown Planning • Machine/System Coordinators • Gather work/tasks to be done for their own systems • Prioritize tasks at the machine level • Provide high level management of the work • Project/ Maintenance level C. Gattuso | Summer Shutdown Planning

  5. Shutdown Planning and Execution • Planning time line • Set target dates to keep our planning on track • Work oversight • Resource allocation • Installation Strategy • Task sequencing • Radiation concerns • Beam turn on schedule • Lessons Learned from previous shutdowns • Number and type of people involved • Shutdown priorities • Defined by Laboratory Management • Projects • Accelerator Improvements • Maintience • Duration is set by highest priority task • Typical shutdown last 8-12 weeks C. Gattuso | Summer Shutdown Planning

  6. Accelerator Division Summer Shutdown Planning We take the approach of “Plan your work and work your plan” at all levels C. Gattuso | Summer Shutdown Planning

  7. Shutdown Gantt Chart (Resourced leveled) • Assumptions made… • Work day is 6 hours • Work week is 5 days • External help rated at 80% efficiency factor This allows us to be able to absorb some schedule creep and slippage that may occur during the shutdown. C. Gattuso | Summer Shutdown Planning

  8. Installation- Work Oversight Machine Coordinator level Crew level • 8:00 Daily (Tool Box) Meeting and updates • Crew Leaders • Email messages sent the day before • Outlines up coming work (daily level) • Tool box meeting to review each day’s tasks • Review the Job • Address any resource issues • Address any ESH issues • Division wide meeting • 09:00 Meeting held 3 times per week (M/W/F) • Status updates • Schedule • ES&H • Updates • Changes • Schedule shifts • Revisions • Schedule creep C. Gattuso | Summer Shutdown Planning

  9. Recycler Collimation system. • The conceptual design of the Recycler Collimation System is based on a Main Injector Collimation System design. • Recycler collimation system consist of Primary collimator, plus two Secondary collimators and Masks. LCW Recycler beam line 20 tons Mask Secondary collimator Primary collimator 3 tons MI Dipole C. Gattuso | Summer Shutdown Planning

  10. Collimator example • Manpower • Mechanical Crew sizes (typically 4 techs with varied experience) • Training and experience • Iron Workers are brought in to supplement the crew • Number of people • Equipment limitation • Magnet removal/installation equipment • Specialized Lifting Equipment/Fork lift (riding)/RECO tm (walk behind Forklift)/Transportation dollies • Assembly logistics Issues • Collimator must be designed and broken down to parts/pieces of less than ~3 tons (lift capability of RECO). • Tunnel space • Heavy device that will need to be stacked above head height Design and installation sequence driven • Work sequencing for hazard mitigation • Both task and tunnel traffic levels C. Gattuso | Summer Shutdown Planning

  11. Safety • Task sequencing • Other task in area • Other resources needed Planning/Design Stage of a Single Job (Collimator) Safety • Safety • Machine • Operations • Safety • Stand stability • Component size • Lift points Safety • Safety • Time sensitivity • Other tasks • with in the • area • Safety • HA (Hazard Analysis) • Equipment used • Matched skill sets Safety Safety C. Gattuso | Summer Shutdown Planning

  12. Saving realization using this process • Time • 3 weeks of schedule saving • Cost • ~3K/day or ~$135K in total • Iron workers • Electricians • Pipe fitters • Related safety • Radiation dose • 2.5 mrem/hr x 6 hrs/day X12 people X 15 days = 2700 person-mrem • Injury Risk Reduced • Work smarter • Modularized installation process • Better use of equipment we have C. Gattuso | Summer Shutdown Planning

  13. Shutdown Planning and Execution • Pre shutdown work Planning • Define tasks that can occur Prior to the shutdown that will not impact machine operations but take pressure off critical resources during the shutdown. • Take Advantage of planned and opportunistic access periods • Staging equipment that will be installed • Cable • Devices to be installed • Completed alignment AS-found of tunnel components • Further review jobs in the tunnel • Mitigating possible interference issue • Refining our installation plans C. Gattuso | Summer Shutdown Planning

  14. ALARA PLANNING RR RF Tasked during Week 5-9 Task sequencing to minimize total dose MI/RR Beam stops RR Col. TSP 2 IP Tasked during Week 1-15 Tasked during Week 1-3 Tasked during Week 1-13 Staging area C. Gattuso | Summer Shutdown Planning

  15. Example of Residual Radiation Level near 309 location 5.5 D 2.5 hrs Half lives 44.5 D 312 D *~30 days in ~100 mrem/hr and with Pb shielding ~60 mrem/hr *~40 days in ~80 mrem/hr and with Pb shielding ~45 mrem/hr *~84 days in (End of the shutdown) ~40mrem/hr and with PB shielding ~25 mrem/hr With lead shielding Days from the start of the shutdown C. Gattuso | Summer Shutdown Planning

  16. Example of ALARA (As Low As Reasonably Achievable) Plan in RR RF section C. Gattuso | Summer Shutdown Planning

  17. Hazard Mitigation • Tunnel Rad survey to place in supervised access mode • Switch over to the Shutdown tunnel key system • Tunnel magnet system power lock out configuration • Single lockout point set up • Set up a layered safety mitigation system • Staged work in such a fashion to minimize risk exposure • Electrical disconnection done first (completed by experts) • Power Cable removal (completed by experts) • Water system isolated • Vacuum system removal • Equipment/device removal (if needed) • Work Plan • Reviewed tasks and equipment with the crews doing the work. • Verify we have all the equipment needed and its in good working order • Verify that all of drawing and installation notes are in place • Review the installation sequence with the crews • Make correction if needed C. Gattuso | Summer Shutdown Planning

  18. MI-60 Girder Fabrication • Why a Girder system • Install several components at once instead of one at a time. • Pre-wire powered elements • Quick connect plugs for power elements • Pre-align elements on girder • 6 of the 10 welds are done upstairs • Magnetic shielding was added • Preliminary leak check done upstairs C. Gattuso | Summer Shutdown Planning

  19. Girder Systems Dose and Time Savings Example: Girder with 2 permanent magnets two power trims and BPM • Old installation practices • Individual stands and Magnets install • ~10 hrs • Cabling/termination/field check • ~2 hrs • Alignment welding pass • ~4 hrs • Alignment final pass • ~4 hrs • Welding • ~4 hrs • Shielding • ~4 hrs Total time ~28 hrs ~ dose rate of 10 mrem/hr Total Dose per task = ~280 person-mrem • Girder process • Install girder assembly • ~4 hrs • Cabling/termination/field check • ~.1 hrs • Alignment final pass • ~2 hrs • Welding • ~2 hrs • Shielding • ~2 hrs Total time ~10 hrs ~ dose rate of 10 mrem/hr Total Dose per task = ~100 person-mrem C. Gattuso | Summer Shutdown Planning

  20. RR 30 Installation Guide line Offset Correction C. Gattuso | Summer Shutdown Planning

  21. Lessons learned from the past • Cable pulls • BPM system ~600K ft. of heliax cabling ( ¼ and 3/8 in)(ANU Shutdown 2012) • Re-spooling • Individual cable runs matched to delivered reels. • Original reel lengths range from 1300 ft to 5500 ft • Pull lengths ran from 180 ft to 1500 ft • Tag location for cable destination in high rad areas to aid electricians • Cost of re-spooling vs Additional time for Pulls • With out re-spooling it will take us ~2 week per service building to complete. • ~$8K/day (4-5 person crew) i.e ~$80 K service building • With re-spooling it will take us ~1 week per service building to complete • ~$8K/day (4-5 person crew) i.e ~40 K service building • For 6 service buildings it saved $240 K minus the $50K re-spool cost. • Net savings = $190,000 • Rad dose saving of ~50% • Old method ~5700 person-mrem • New method ~2800 person-mrem 1/2 the spools for a typical building C. Gattuso | Summer Shutdown Planning

  22. MI 30 Tunnel Section MI/RR Shutdown 2012 C. Gattuso | Summer Shutdown Planning

  23. Shutdown 2015 ESH&Q • Shutdown Radiological Exposure • 6859 person-mrem through 14 weeks. 8,000 person-mrem anticipated before shutdown with ALARA plans. • Tunnel background exposure level accounts for ~ 600 person-mrem over the course of the shutdown • Shutdown Radiological Exposure • Tracked doses for 276 shutdown workers • 0-100 mrem 258 workers – 93.6% • 100 – 150 mrem 18 workers – 6.4% • 150 + mrem 0 workers – 0% • Achieved shutdown goal of no individual worker exceeding 150 mrem. • Shutdown related injuries • One First Aid case • Two Recordable case • One case of lost work days • One case of a person placed on limited duty C. Gattuso | Summer Shutdown Planning

  24. Carry over from Shutdown to Shutdown for lessons learned • Effectiveness of Intensity reduction • Cool off periods Vs. Beam Intensity run • Labor Estimates • Resource effectiveness • Types of manpower used • Task sequencing • Pre shutdown planning and preparation • Building flexibility into the schedule • Resource Management • Trades • Technicians C. Gattuso | Summer Shutdown Planning

  25. Risks to Shutdown Planning and Execution • Resources • Aging workforce • Average age of one of the MI Mechanical crews is 62 years old • Loss of expertise • Availability of manpower • Competing for resources across the laboratory • Projects being ready for installation • Additional engineering and technical staff • Tunnel activation levels • As Beam power goes up loss patterns may change • Infrastructure • Tunnel lighting • Etc. C. Gattuso | Summer Shutdown Planning

  26. Thank You C. Gattuso | Summer Shutdown Planning

More Related