Hydroelectric Licensing Regulations. Final Rule July 23, 2003 Federal Energy Regulatory Commission Office of Energy Projects Office of the General Counsel. Rulemaking Process. Sept 2002 – Rulemaking initiated Oct/Nov/Dec – Regional Forums, Drafting Session, Comments February 2003 – NOPR
E N D
Hydroelectric Licensing Regulations Final Rule July 23, 2003 Federal Energy Regulatory Commission Office of Energy Projects Office of the General Counsel
Rulemaking Process • Sept 2002 – Rulemaking initiated • Oct/Nov/Dec – Regional Forums, Drafting Session, Comments • February 2003 – NOPR • Mar/Apr/May – Reg. Workshops, Drafting Session, NOPR Comments • July 2003 - Final Rule
Integrated LicensingProcess Goals • Improves process efficiency, predictability, and timeliness • Balances stakeholder interests • Improves the quality of decision making
Integrated LicensingProcess Benefits • Coordination w/ other processes • Concurrent NEPA scoping and application preparation • Increased public participation • Early Commission staff assistance
Integrated LicensingProcess Benefits • Process plan and schedule • Early study plan development and informal/formal dispute resolution • Enhanced Tribal Consultation
Final Rule Transition Timeline Rule Issued 7/23/2003 Rule Effective 10/23/2003 ILP Default 7/23/2005 • PAD req. for TLP & ALP • Applicant Choice: • TLP • ALP • ILP • New Application Requirements
Post-NOPR Modifications • Improved Pre-Application Document • More time for informal study dispute resolution • Preliminary Licensing Proposal in place of Draft License Application
Post-NOPR Modifications • Water Quality Certification Application moved to REA Notice • Keep existing NEPA Cooperating Agency Policy • Tribal Consultation Meeting
Post-Rule Activities • Training & Outreach • Individual Project & Regional Training • Tribal Outreach • Effectiveness study