Concerned Citizens of Mason County

Concerned Citizens of Mason County. OVERVIEW of ADAGE ORCAA PROCESS Olympic Region Clean Air Agency January 19, 2011. ORCAA. Olympic Regional Clean Air Authority Air Permit Responsible for determining if the stack emissions are within standards. Other Modeled Emissions

shae
Download Presentation

Concerned Citizens of Mason County

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Concerned Citizens of Mason County OVERVIEW of ADAGE ORCAA PROCESS Olympic Region Clean Air Agency January 19, 2011

  2. ORCAA • Olympic Regional Clean Air Authority • Air Permit • Responsible for determining if the stack emissions are within standards

  3. Other Modeled Emissions Arsenic Beryllium Cadmium Chromium Lead Manganese Mercury Nickel Acetaldehyde Acrolein Benzene Formaldehyde Dioxins 8 compounds Furans 8 compounds ADAGE AIR EMISSIONS Facility Wide Annual Emissions PM 107 Tons PM10 73.1 Tons PM2.5 68.1 Tons NOx 240 Tons CO 243 Tons VOC 34 Tons SO2 83.4 Tons H2SO4 4 Tons Fluorides 5 Tons CO2 600,000+Tons

  4. Review of ORCAA Air Permit Activities • April - ADAGE files Air Permit application with ORCAA • Dec 22 – ORCAA issues letter of intent to approve and opens comment Period until Jan 31 • Jan 31 – Public comment meetings at Civic Center at 1 and 6 PM and close of comment period including expert testimony from CCMC air engineer • Feb 15 – Mar 1? Hearing Officer issues decision about Air Permit Recommendation • Apr 2- 30 day deadline for CCMC to appeal ORCAA recommendation to the Pollution Control Hearings Board (PCHB) or Superior Court • Air Permit cannot be granted until SEPA process is completed

  5. Air Permit Issues • Not waiting for the SEPA and possible EIS findings before issuing the report • Amount of emissions • Future impact of Tailoring Rule and the over 600,000 TONS of CO2 • Air Engineer Testimony • Self Monitoring by Duke Energy

  6. Air Permit Comments • Comment on only Air Permit Issues in the ORCAA Staff Recommendation Letterhttp://www.orcaa.org/public-involvement/staff-recommendations/ ORCAA 2940-B Limited Lane NW Olympia, WA 98502 • Comments must be received by 1-31-2011