WBS 1.2 Cryogenics

WBS 1.2 Cryogenics. Jim Kilmer 4/8/2011. Progress in March. Completed documents for the review Wrote a purchase package for the LAr pumps for CD-3a Started 3-D model of cryogenic system in the enclosure. Comments from the review. Fix discrepancies between BOEs and schedule

shepry
Download Presentation

WBS 1.2 Cryogenics

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WBS 1.2 Cryogenics Jim Kilmer 4/8/2011

  2. Progress in March • Completed documents for the review • Wrote a purchase package for the LAr pumps for CD-3a • Started 3-D model of cryogenic system in the enclosure

  3. Comments from the review • Fix discrepancies between BOEs and schedule • Write a purchase package for the cool down heat exchanger, independent review of the specification • Independent review of the ODH analysis • Finish the 3-D model • Get more engineering for the Cryogenics task

  4. Cool down heat exchanger • Couldn’t contact the vendor before review to get a 3a purchasing document done • Finally did get an answer from them • Also contacted other vendors and getting more quotes • Will have a 3a procurement package with multiple quotes before next review

  5. 3-D model

  6. Add additional engineering • PPD has approved a requisition to hire a contract engineer for one year on MicroBooNE • MD has given me another engineer who is just finishing work on DES • Bob Sanders should be available ~ full time by about May 2 • We should have plenty of engineering to get the work for CD-2 done on time