An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ICAO PKD Implementation Financing Requirements May 18, 2004

  2. Status • ICAO PKI Infrastructure Specification achieved – new Technical Report • ICAO Public Key Directory (PKD) required – TAG approval implies action • Detailed estimates and budgets available • Proposal for first phase in hand • Some funds potentially available from ICAO

  3. Elements of the PKD • Architecture – 2 sites, each with backup. • Secure communications with countries • Outsourced site/system IT operations. • ICAO staff for PKD operation & management • PKD certificate update • Due diligence review • Country support and liaison • One-time setup and annual subscription fees

  4. PKD Operations - Assumptions • Year 0 (next 12 months) – implementation • Year 0 - first site installed in Montreal • Year 1 – 13 Visa Waiver nations sign up, plus USA and Canada • Year 1 – 2nd site installed remote from Montreal. • ICAO staffing in Years 0 and 1 • Other VW nations in Years 2 & 3 • No schedule assumptions for non-VW nations

  5. Budget Highlights • Full Implementation costs - $1.8M USD • Includes 2 sites & ICAO staffing • Annual operating costs - ~$800,000 USD • Includes outsourced IT management at 2 sites

  6. Cash Flow Assumptions • Fees based on country size: • Scale 1 countries: <15M citizens • Scale 2 countries: 15M to 25M citizens • Scale 3 countries: 25M to 100M citizens • Scale 4 countries: >100M citizens • Cost of money = 10%

  7. Initial setup fees: Scale 1 - $50,000 Scale 2 - $50,000 Scale 3 - $100,000 Scale 4 - $150,000 Participation fees: Scale 1 - $25,000 Scale 2 - $25,000 Scale 3 - $75,000 Scale 4 - $75,000 Fee Assumptions

  8. Spreadsheet Results • Maximum negative cash flow = $1.6M USD • Some hedge required • Break-even in ops Year 4 (5 years hence) • Small operating margins thereafter • Very economical operation for all countries

  9. Financing Options • Grants? • Unlikely • Country loans • Only a few countries need participate • Commercial loans • Country guarantees? • Commercial financing • “Partnership” arrangements with industry

  10. Conclusions • PKD can be and must be done • Inexpensive for all • ICAO is ready; must proceed NOW. • Immediate decisions necessary; specific country support requested.