PACS Status Report - WE SVR-2 MPE , 1 8 Jan 200 7 O.H. Bauer. FM ILT: WE Configuration. DPU FM SPU FM (partly repaired) DECMEC EQM (not redundant and only blue array) BOLC FM Second set-up used for SPU OBS development. FPU Cold FocalPlaneUnit. BOL/COOL. BOL/BAU. DEC/MEC 2.
E N D
PACS Status Report - WE SVR-2 MPE, 18Jan 2007 O.H. Bauer
FM ILT: WE Configuration • DPU FM • SPU FM (partly repaired) • DECMEC EQM (not redundant and only blue array) • BOLC FM • Second set-up used for SPU OBS development
FPU Cold FocalPlaneUnit BOL/COOL BOL/BAU DEC/MEC 2 DEC/MEC 1 SPU nominal BlueBol BAU MEC I/F-Module Redundant BOL 1 Module BlueGe:GaArray &CRE MPE/ASTEQ/IMEC MEC I/F-Module IAC-Tenerife/TU-Wien DPU nominal DSP Module Redundant RedBol BAU BOL 2 Module BlueBolArray &Read-out CEA DSP Module SPU redundant CEA Cooler Control Warm Interconnecting Harness RedDEC Module RedBolArray &Read-out CEA BlueDEC Module IAC-Tenerife/TU-Wien DPU redundant CEA Base/PSU Redundant RedGe:GaArray &CRE MPE/ASTEQ/IMEC Base/PSU IFSI-ROME CSL-Liege CSL-Liege 0.3K Cooler CEA Grating Assy CSL-Liege Chopper Assy MPIA 2FilterWheels KT 2CalSources KT KT/MPE Instrument Overview and Subsystem Responsibilities Cryo-Harness 13
WE Status I • DPU • Problems in CFM identified (ringing of bus lines) and S/W work-around implemented • FM apparently does not show the same symptoms, but showed some erratic behaviour (MEMCOPY routine caused corrupted data packets) • SPU, DECMEC (but also LFI REBA, ...) • During tests at CRISA read errors from the DSP program memory (PRAM), only with special memory contents, were found. • Error was found on all DSP PCBs systematic design error! • PACS FM SPU partially repaired, can be used for FM ILT. • Complete repair and re-qualification after ILT will take four weeks. • BOLC: OK
WE Status II • DECMEC • During TV test (cold phase, -25°C) DECMEC FM stopped after one hour of operation: two dead transistors found, temperature/design problem Delivery of qualified FM (not EMC: can be done after FPU delivery) later than mid Feb has dramatic impact on ILT schedule and delivery Most of ILT has to be executed with EQM, which is not fully FM-equivalent (lacking redundancy, only blue DEC) Change to red array and swap of EQM against FM need warm-up to 40 K
Schedule • Schedule Summary FM (refurbished CQM for FPU) • ILT at MPE: cool down started 19 Oct 06 • Partial warm-up/cool-down forchange to red Ge:Ga array 16/19 Dec 06 • Warm-up/cool-down for exchange • of chopper, repair of illumination • problem and possible DECMEC • exchange23 Dec 06 – 18 Feb 07 • DECMEC FM delivery to MPE mid Feb 07 ?? • FM WE/FPU delivery to Project late April 07 !? • Schedule for FS FPU • FS FPU ready for possible • delivery to Project end Sep 07