1 / 12

Subsea Power Connections that Work

Subsea Power Connections that Work. 04 – 07 Feb 2013, Vienna, Austria. Contents. Experience History Concerns Design considerations Electrical Thermal Mechanical Conclusions. Experience. 120 years

Download Presentation

Subsea Power Connections that Work

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Subsea Power Connections that Work 04 – 07 Feb 2013, Vienna, Austria

  2. Contents • Experience • History • Concerns • Design considerations • Electrical • Thermal • Mechanical • Conclusions

  3. Experience 120 years Power cables have been around for a long time. Designs have evolved, new materials are being used. Challenges offshore remain. 7,000 km More than 7,000 km of HV (≥ 60 kV) cables are in service (onshore, offshore), many more system-kilometres at 33 kV and below. 80% claims Many offshore wind farms have experienced problems with subsea power cables. Claim amounts related to cables top the list.

  4. Experience – “Other” Subsea Cables • Subsea interconnections ≥ 60 kV • 3,700 km AC, 3,400 km DC (2005) • ~ 50 damages in 1990-2005: • 80% in water depths < 50 m • Many on unprotected cables,e.g. through fishing and anchors • Subsea telecom cables • > 1,000,000 km in service(fibre optic, 2009) • Frequent damages, but networkbuilt with redundancies Data sources: Cigré (2009), Carter et al. (2009)

  5. Experience – Offshore Wind Energy Failure statistics not yet available Incidents in virtually every wind farm Most often during construction Sometimes during operation Strong focus on price , not enough on risk Lack of transfer of knowledge “Industry best practice” yet to be developed Data source: DNV stakeholder consultation

  6. “CableRisk” Joint Industry Project Initiative • 15 Participants • Objective • Develop a guideline for subsea power cables in renewable energy applications which • covers the cable lifecycle • provides technical guidance • improves communication between stakeholders • helps managing the risks • Timeline • Project: Aug 2012 – Jun 2013 • Industry review: Spring 2013 INCH CAPE Project responsible:

  7. Cable Projects – Appreciating Complexity Thermal Electrical Mechanical Quality checks All relevant stakeholders consulted? Started early with the planning and design? Optimised and planned with contingencies?

  8. Electrical 3 x 1 x 240 mm2 Cu 33 (36) kV, 880 m 3 x 1 x 630 mm2 Cu 150 kV, 20,500 m 3 x 1 x 800 mm2 Cu 150 kV, 1,350 m Layout MW, kV Topology selection Choice of mm2 Ampacity estimation Length R, XC Data sheets Cable choice Failure rate Basic power flow Reliability check NPV (€) p.u., Mvar Quality checks Reliability targets set? Failure rates applicable?

  9. Thermal Pel Losses w y s  th Constraints Data Cable route desktop study Site parameters Survey ,  th • Example: 3 x 1 x 240 mm2 Cu, 33 (36) kV • Cable A: 467 A (< 20°C, < 1.0 K m / W) • Cable B: 590 A (< 10°C, < 0.7 K m / W) Proposed corridor y Depth Hazards Burial assessment Electrical losses w Cooling verification Back to electrical study? s Quality checks • Site data available? • Hotspots ok? • J-tubes • Soils with low conductivity • Landfall

  10. Mechanical Radius, tension, friction Fpull Movement Cable properties Site, vessel data Foundation design Back to electrical / thermal study? Construction engineering Trials Method statements Warranty surveyor verification Insurance cover? Quality checks Installation weather dependent? Optimised for smooth installation?

  11. Conclusions • Subsea power cabling • is multi-disciplinary • has frequently been underestimated • Cable risks require assessment over whole life cycle • Industry guidance is being developed

  12. www.dnv.com Joint Industry Project: CableRiskJIP@dnvkema.com

More Related