1 / 6

Tie-Breaker SCED Logic & QSGRs

Tie-Breaker SCED Logic & QSGRs. ERCOT Wholesale Market Committee March 13, 2013. Background. SCED “tie-breaker” logic occasionally adds a small amount of MW to the basepoints of MANY on-line units

sondra
Download Presentation

Tie-Breaker SCED Logic & QSGRs

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tie-Breaker SCED Logic & QSGRs ERCOT Wholesale Market Committee March 13, 2013

  2. Background • SCED “tie-breaker” logic occasionally adds a small amount of MW to the basepoints of MANY on-line units • This effect is transient – it typically adds MWs only very infrequently, and then typically for a short period of time • Normally, quick-start generation resources (QSGRs) are physically off-line, but they are logically on-line since they are available for immediate dispatch by SCED • A QSGR is obligated to follow all basepoints and is required to physically start when it receives a basepoint above zero. • This tie-breaker logic causes unintentional QSGR starts

  3. Problem • The existing tie-breaker logic can start QSGRs and place hundreds of megawatts on-line unintentionally • Most QSGRs have LSLs much higher than the MW added by the tie-breaker logic • After receiving a non-zero basepoint and starting, a QSGR must at least generate at LSL • The tie-breaker logic on QSGRs can frequently cause the QSGRs to be brought on-line at LSL when SCED may be telling each QSGR to go to a basepoint of 1 MW for a few SCED runs. • The tie-breaker logic impacts all units, but impacts QSGRs the most because of the resulting commitment trigger • These unintentional starts also causes the resource owners to incur startup costs (O&M wear/tear and fuel) unnecessarily

  4. SCED Mitigation and Tie Breaker Logic • The tie-breaker logic impacts QSGRs when: • Typically there is at least one active non-competitive constraint • The Step 1 SCED reference price is above a portion of a unit’s mitigated cost curve • SCED sets the all units’ Step 2 mitigated offer curve to not go below the SCED 1 reference price • SCED publishes a basepoint to a each unit that solves the following:

  5. Short-term solution • Normally, we show one QSGR at each site (we have 3 sites with multiple units) to be available for SCED dispatch - the resource status code (RST) is ON. We keep the RST for all other QSGRs at the site set to show an OFF status • This step minimizes the impact of tie-breaker logic on unintentional commitment of QSGRs and over-generation at LSL • We switch another QSGR to ON when there is only a small amount of dispatch room left on any physically on-line QSGRs. • This step ensures that SCED has enough generation available to it to manage local congestion • We switch all of the QSGRs at a site to ON when the LMP is close to reaching a QSGR’s EOC or when LMPs go some amount above the NSRS floor, whichever is lower. • This step ensures that SCED will have the QSGR capacity shown in our COP available for dispatch when needed • This step also results in an increase in the Up Capacity Available to SCED because of real-time RST codes changing from OFF/OFFNS to ON

  6. Long-term solution • ERCOT proposed NPRR 520 last month “to implement the changes necessary to address SCED over-mitigation issues raised by the IMM” • NPRR 520 addresses the QSGR problem in two ways: • “Only those Resources that have a significant contribution in getting the Entity with decision making authority considered for mitigation for a Non-Competitive Constraint will have mitigation applied in SCED” • The formula for mitigating energy offers in SCED is changed to include a small adder to the reference price from SCED Step 1 in order to minimize issues caused by the tie breaking logic

More Related