1 / 3

St. Louis District Gilbert Island RRAT

St. Louis District Gilbert Island RRAT. FY 14 RRAT– Gilbert Island. FY 14 RRAT– Gilbert Island. Chevrons 298.55L & 298.4L along with Dikes 297.9R & 297.7R were completed in the spring of FY11 ($1.5M) So far the third chevron, 298.2L is not needed.

Download Presentation

St. Louis District Gilbert Island RRAT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. St. Louis District Gilbert IslandRRAT

  2. FY 14 RRAT– Gilbert Island

  3. FY 14 RRAT– Gilbert Island • Chevrons 298.55L & 298.4L along with Dikes 297.9R & 297.7R were completed in the spring of FY11 ($1.5M) • So far the third chevron, 298.2L is not needed. • Uppermost location in MVS, by alleviating dredging at this location mobilization costs for the dredge have been significantly reduced • Mussel habitat identified on the LDB • FY14 award to include mussel survey work in FY15

More Related