September 11, 2002. ALEOC MeetingMidland, Texas. 2. Test Well Facilities. The Texas Tech University Test Well Facilities is currently completing the initial procurement stage to complete the well bore portion of the facilities.Donations have been secured for the following items.Two-Phase separat
E N D
1. September 11, 2002 ALEOC Meeting
Midland, Texas 1
2. September 11, 2002 ALEOC Meeting
Midland, Texas 2 Test Well Facilities The Texas Tech University Test Well Facilities is currently completing the initial procurement stage to complete the well bore portion of the facilities.
Donations have been secured for the following items.
Two-Phase separator and Heater Treater from NATCO GROUP.
Lufkin C456D-305-144 Pumping Unit with Pump off Controller.
3. September 11, 2002 ALEOC Meeting
Midland, Texas 3 Donated Equipment Specifications
Lufkin Pumping Unit
C456D-305-144
Pump off Controller
Contact:
Mr. Cecil L. Hunt Jr.Lufkin Industries, Inc.
Oilfield Division
P. O. Box 849
Lufkin, Texas 75902-0849
Phone:(936) 637-5667
Fax: (936) 637-5306
Email: chunt@lufkin.com
4. September 11, 2002 ALEOC Meeting
Midland, Texas 4 Lufkin Pumping Unit PadRed Raider No. 1
5. September 11, 2002 ALEOC Meeting
Midland, Texas 5 Donated Equipment Specifications NATCO GROUP
Two Phase Separator
16 in x 5 ft x 1440 psi.
800 bbls of Fluid per day
Contact Information:
NATCO ODESSA
6609 West 16th Street
Odessa, Texas 79763
Phone: (915) 530-3600
Fax: (915) 530-3636
6. September 11, 2002 ALEOC Meeting
Midland, Texas 6 Donated Equipment Specifications NATCO GROUP
Heater Treater
4 ft x 20 in. x 50 psi
860 bbls of Fluid per day
Contact Information:
NATCO ODESSA
6609 West 16th Street
Odessa, Texas 79763
Phone: (915) 530-3600
Fax: (915) 530-3636
7. September 11, 2002 ALEOC Meeting
Midland, Texas 7 Red Raider No. 1 Equipment (Awaiting Delivery) Stock Tanks (Permian Tank Company, Odessa, Texas)
Three (3) 12ft x 25 ft, API 12F Type B Cone bottom, tanks with ź inch plate and 1 in roll lines.
OCTG Pipe (Tubing)
Five Star Pipe (Odessa, Texas) 4150 ft, 2-7/8 inch, J-55, 6.5 #/ft, R2, SCC
Cont. Casing (Houston, Texas) 1500 ft, 3-1/2 inch, J-55, 9.30 #/ft, R2, SCC
8. September 11, 2002 ALEOC Meeting
Midland, Texas 8 Toshiba Oil Field Motor and Cutler Hammer Panel
9. September 11, 2002 ALEOC Meeting
Midland, Texas 9 Red Raider No. 1 Equipment (Toshiba Motor Name Plate Specs.) Toshiba Oil Well Pump
3-Phase Induction Motor
NAME PLATE SPECIFICATIONS
Model No.: F0506DKF3PDP02
ENCL.: DP
HP: 50
POLES: 6
INC. CLASS: F
NEMA DES.: -
NEMA CODE: G
S.F.: 1.00
TYPE: TIKS
FORM: DBK1
FR#: 365T
DUTY: CONT.
MAX. AMB.: 40 C
VOLTS: 230/460/796 HZ 60
RPM: 1120
AMP: 120/60/34.5
SER. NO.: 001202523
BRG NO.: L.S. 6314C3
O.S. 6313C3
10. September 11, 2002 ALEOC Meeting
Midland, Texas 10 Seating Nipples
11. September 11, 2002 ALEOC Meeting
Midland, Texas 11 Pipe RacksRed Raider No. 1
12. September 11, 2002 ALEOC Meeting
Midland, Texas 12 Test Well Web Page (1)
13. September 11, 2002 ALEOC Meeting
Midland, Texas 13 Test Well Web Page (2)
14. September 11, 2002 ALEOC Meeting
Midland, Texas 14 Test Well Facilities Schedule We are currently waiting on the split hanger for the tubing head.
We hope to have the Lufkin Unit set by Oct. 1, 2002.
We will move tubing to the racks after the pumping unit is set.
The Separation facilities and stock tanks will be ready by the end of Sept. 2002.
We hope to have the puping unit component ready for testing by Dec. 2002.