Dr. GamaniChandrasenaVice ChancellorUva Wellassa University, Sri Lanka Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri Lanka
Construction (Capital) Projects of Uva Wellassa • Phase I • Phase II Phase I • Administration Building Block • Lecture Hall + Lab (Block A) • Lecture Hall + Lab (Block B) • Lecture Hall + Lab (Block C) Total Cost Estimated (Amended TCE) => Rs. 350 Million Actual Expenditure incurred to 30.06.2015 => Rs. 348 Million Future Commitment (Final Bill to be Settled) => Rs 10 Million Physical Process : 100% Financial Progress : 99% • Administration Building Block • Awarding On : 03rd Aug 2005 • Completed On : 16th Oct 2006 25 August 2015
Lecture Hall + Lab (Block A) • Awarding On : 03rd Aug 2005 • Completed On : 01st Nov 2006 • Lecture Hall + Lab (Block B) • Awarding On : 03rd Aug 2005 • Completed On : 11th Oct 2006 • Lecture Hall + Lab (Block C) • Awarding On : 03rd Aug 2005 • Completed On : 11th Oct 2006 25 August 2015
Phase II • Hostel Block No. 1 • Awarding On : 01st Jul 2006 • Completed On : 30th Jul 2007 • Physical Progress : 100% • Financial Progress : 87% • Hostel Block No. 2 • Awarding On : 01st Sep 2006 • Completed On : 26 Jun 2008 • Physical Progress : 100% • Financial Progress : 87% • Hostel Block No. 3 • Awarding On : 01st Aug 2006 • Completed On : 04th Dec 2008 • Physical Progress : 100% • Financial Progress : 87% 25 August 2015
Hostel Block No. 4 • Awarding On : 01st Nov 2006 • Completed On : 25th Jul 2008 • Physical Progress : 100% • Financial Progress : 87% TCE: 457 Million • Dinning & Study Hall • Kitchen for Dinning & Study Hall • Awarding On : 15th May 2006 • Completed On : 30th Jun 2006 • Physical Progress : 100% • Financial Progress : 87% • Water Sump & Pump House • Awarding On : 01st Sep 2006 • Completed On : 16 Jun 2008 • Physical Progress : 100% • Financial Progress : 73% 25 August 2015
Landscaping - Phase - 1 Area • Awarding On : 01stJan 2007 • Completed On : 19th Jan 2008 • Physical Progress : 100% • Financial Progress : 70% • Name Board and Developments • at entrance • Awarding On : 01st Jul 2007 • Completed On : 19th Jan 2008 • Physical Progress : 100% • Financial Progress : 35% • Temporary Sports Court • Awarding On : 15th Jan 2007 • Completed On : 27th Feb 2006 • Physical Progress : 100% • Financial Progress : 70% 25 August 2015
Fiber Network (IT back-born at Phase 1 buildings) • Awarding On : 01st Dec 2007 • Completed On : 31st Dec 2008 • Physical Progress : 100% • Financial Progress : 97% • Vice Chancellor's Bungalow • Awarding On : 08th Sep 2008 • Completed On : 09th Mar 2010 • Physical Progress : 100% • Financial Progress : 98% • Play Ground (For 200m track) • Awarding On : 01st Apr 2007 • Completed On : 13th Sep 2009 • Physical Progress : 100% • Financial Progress: 63% 25 August 2015
Internal Road Network (A,B & D) • Awarding On : 01st Mar 2007 • Completed On : 30th Mar 2009 • Physical Progress : 100% • Financial Progress: 66% • Lecture Hall + Lab (Block E) • Awarding On : 05th Sep 2008 • Completed On : 15th Mar 2011 • Physical Progress : 100% • Financial Progress : 65% • Lecture Hall + Lab (Block F - I) • Awarding On : 01st Jan 2009 • Completed On : 08th Mar 2010 • Physical Progress : 100% • Financial Progress: 65% 25 August 2015
Lecture Hall + Lab (Block F - II) • Awarding On : 27th Apr 2010 • Completed On : 26 Jul 2011 • Physical Progress: 100% • Financial Progress: 65% • Lecture Hall + Lab (Block D) • Awarding On : 27th Apr 2010 • Completed On : 26th Aug 2011 • Physical Progress: 100% • Financial Progress:65% • Storm Water Drainage System • Awarding On : 30th Dec 2009 • Physical Progress: 65% • Financial Progress: 17% Ongoing 25 August 2015
Quarters for Deans/ Registrar/ Bursar & Course Directors • Awarding On : 01st Dec 2011 • Completed On : 15th Feb 2013 • Physical Progress : 100% • Financial Progress : 77% • Staff Quarters (Studio Apartments) • Awarding On : 25th Nov 2012 • Completed On : 05th Mar 2013 • Physical Progress : 100% • Financial Progress : 50% • Roads and Landscaping • at Phase II Area • Awarding On :17th Dec 2009 • Physical Progress : 50% • Financial Progress : 41% Ongoing 25 August 2015
Sports Center & Gymnasium • Awarding On : 30th Dec 2014 • Physical Progress : 25% • Financial Progress : 25% Ongoing • Pavilion • Awarding On :06th Aug 2015 • Physical Progress : 5% • Financial Progress : 5% • (Mobilization Advance) Ongoing • Cafeteria and Toilets • Awarding On : 27th Aug 2012 • Completed On : 26th Aug 2013 • Physical Progress : 100% • Financial Progress: 100% 25 August 2015
Maintenance section • Awarding On : 08th Jan 2014 • Completed On : 08th Oct 2014 • Physical Progress : 100% • Financial Progress: 66% • Senate Building • Awarding On : 20th Mar 2013 • Physical Progress : 95% • Financial Progress: 85% Ongoing • Balance work Roads & Landscaping • Awarding On : 22nd Mar 2014 • Physical Progress: 65% • Financial Progress: 44% Ongoing 25 August 2015
Waste water drainage & • treatment works (Job 01 & Job 02) • Awarding On :14th Oct 2010 / 17th May 2013 • Physical Progress : 85% • Financial Progress: 36% Ongoing • University Guest House • Awarding On: 05th Sep 2011 • Completed On: 20th Oct 2012 • Physical Progress: 100% • Financial Progress: 64% • University Guest House • Awarding On: 05th Nov 2012 • Completed On: 17th Aug 2013 • Physical Progress: 100% • Financial Progress: 96% 25 August 2015