1 / 20

Fault detection and recovery in multi-modal transportation networks with autonomous mobile actors

TRAIL/TNO Project 16. Fault detection and recovery in multi-modal transportation networks with autonomous mobile actors. Jonne Zutt j.zutt@its.tudelft.nl Delft University of Technology Information Technology and Systems Collective Agent Based Systems Group. Supervisors Dr. C. Witteveen

Download Presentation

Fault detection and recovery in multi-modal transportation networks with autonomous mobile actors

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TRAIL/TNO Project 16 Fault detection and recovery in multi-modaltransportation networks with autonomous mobile actors Jonne Zutt j.zutt@its.tudelft.nl Delft University of Technology Information Technology and Systems Collective Agent Based Systems Group Supervisors Dr. C. Witteveen Dr. ir. Z. Papp Dr. ir. A.J.C. van Gemund

  2. Content • Project Characteristics • Problem setting:Transport Planning Problem • Scheduling Example • Preliminary Results • Future plans

  3. Project Characteristics “Fault detection and recovery in multi-modal transportation networks with autonomous mobile actors” • Planning, fault detection and recovery • Multi-agent approach • Multi-layered approach for distributed planning • Operational aspect of multi-modal transportation

  4. Transport Planning Problem – Orders • Transportation orders • Infrastructure resources • Transport resources • Agents O = (f, v, s, Ts, d, Td, l, u, p) f, v freight identifier / volume,s, d source / destination location,Ts, Td source / delivery time-window,l, u loading / unloading costs,p penalty.

  5. TPP – Infrastructure • Transportation orders • Infrastructure resources • Transport resources • Agents

  6. TPP – Infrastructure model • Transportation orders • Infrastructure resources • Transport resources • Agents

  7. TPP – Transport resources • Transportation orders • Infrastructure resources • Transport resources • Agents

  8. TPP – Agent architecture TAC CUS OPR CRA Transportation orders Transport resources Infrastructure resources

  9. Incident Management • What are incidents? • Any event from outside the planning system that cannot be anticipated with certainty. • new orders, changes in orders • road blocks, traffic jams • malfunctional vehicles • What is incident management? • Ensuring the correct operation of a system under the events of incidents • Detection, repair and notification of problems

  10. Distributed operational planning • Job-shop Scheduling with BlockingHatzack & Nebel (ECP 2001) • JS scheduling: find an optimal allocation of a set R of scarce resources to a set of activities (jobs) J over time • Blocking means that a resource is claimed by a job until it claims the next resource • Agent plan: ((IR1, 0-2), (IR2, 5-7), (IR3, 8-9) …)

  11. Algorithm • Schedule(Agent a, Route Rta) ≡ • consider the head of route Rta, • t is the first time at which resource  is not claimed by other agents, • increment t and schedule  at t until the tail of route Rta is (recursively) scheduled successfully.

  12. Algorithm (2) • Process(Agent a, Order o) ≡ • negotiate until agent a is allowed to schedule, • Agent a makes a schedule, • if agent a violates order o’s time-window: negotiate until agent a is allowed to reroute, • after each reroute (of any agent), the above steps are repeated

  13. Deadline Time A B C D E F B G E F B G H C I J H C I J Example E J F I A B C D G H

  14. EX: Determine Scheduling Order (6 – 4) / 4 = 0.5 2 (7 – 4) / 4 = 0.75 5 (6 – 4) / 4 = 0.5 3 (6 – 4) / 4 = 0.5 4 (5 – 4) / 4 = 0.25 1 Deadline Time  (o– Mo) / Mo A B C D E F B G E F B G H C I J H C I J

  15. EX: Compute Schedules A B C D E F B E F B G H C I J H C I J Deadline Deadline Time  Time  2 A B C D 5 E F B G 3 E F B G 4 H C I J 1 H C I J

  16. EX: Compute Schedules Deadline Deadline Time  Time  2 A B C D A B C D 5 E F B G E F B G 3 E F B G E F B G 4 H C I J H C I J 1 H C I J H C I J

  17. Experiments • Used 3 different infrastructures, • 20 transport agents each execute one order, • Randomly chosen source-, destination location and fixed time-window.

  18. Results (averaged over 100 problem instances) Delay  { aA (Ca – Ma) / Ca } / |A| Tardiness aA Ca - a if Ca< a Average % of delay Tardiness Number of alternatives Number of alternatives

  19. Future Plans • Generate realistic problem instances, • Repeat experiments with more different routing and conflict resolution algorithms, • Repeat experiments under influence of incidents.

  20. TRAIL/TNO Project 16 Fault detection and recovery in multi-modaltransportation networks with autonomous mobile actors Jonne Zutt j.zutt@its.tudelft.nl Delft University of Technology Information Technology and Systems Collective Agent Based Systems Group Supervisors Dr. C. Witteveen Dr. ir. Z. Papp Dr. ir. A.J.C. van Gemund