1 / 17

INTRA STATE ABT Necessity Issues Implementation

INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05. Appropriate Commissions to undertake development of power market SERCs to notify GRID CODE by September 2005, if not yet notified

stacy-potts
Download Presentation

INTRA STATE ABT Necessity Issues Implementation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INTRA STATE ABT Necessity Issues Implementation

  2. Some of the features of New National Electricity Policy – Feb.’05 • Appropriate Commissions to undertake development of power market • SERCs to notify GRID CODE by September 2005, if not yet notified • State Commissions to ensure upgradation of SLDCs by June 2006 • SERCs are advised to introduce ABT regime at the State level within one year i.e. by February 2006.

  3. Need for intra-State ABT • Accountability of utilities after reforms • Passing on UI payment • Intra State ABT to identify agencies responsible for overdrawal/underdrawal, overgeneration/ undergeneration, resulting in UI payment to regional pool. • Proper Demand forecast and load management by DISCOMs • To establish a framework for bilateral trading at intra-State level • To achieve overall merit order operation.

  4. Inter-State ABT Non-conventional source of energy e.g., wind energy Intra-State ABT IPPs CPPs • Distribution Control Centre –One for each Discom • ISGS: Inter State Generating Stations • SGS: State Generating Stations • CTU: Central Transmission Utility • STU: State Transmission Utility

  5. Intra state ABT • Pre – requisites • Unbundling of Vertically Integrated State Utilities • Allocations from ISGS/ other state owned generators to various Discoms by State Govt • Control centres in each Discom • RTUs at required locations • Generating stations • Drawal points from STU to DISCOMS on various tie-lines, ICTs • various other critical lines • SCADA information to Discom Control Centres • SEMs at required locations • Processing of SEMs data/Settlement system

  6. Intra-state ABT .what it achieves ? Harness surplus generating capacity available in state with CPPs / IPPs • Operation of grid on economic principles –Merit Order Despatch • Open Access in Intra-state Transmission and Distribution. • Generate signals for efficient grid operation at the intra-state level.

  7. Intra-state ABT –what it achieves ? • Overdrawals at low frequency by Discoms duly priced. • Encourage serving of higher consumer demand • Encourage maximisation of generation during deficit conditions. • Each Discom and state generating station responsible for its actions – a profit centre • Commercial signals available to large consumers capable of regulating drawal

  8. …Intra-state ABT – what it achieves ? • UI mechanism at the intra-state level • UI to be applied on the deviations from the schedules of the DISCOMS/State generators/IPPs/CPPs. • State Utilities to be collectively liable for the States’ liabilities with the regional UI pool account. • Achieves merit order operation for all the entities under ABT • Commercial viability of running Pumped Storage Stations.

  9. Issues needs to be addressed for intra-State ABT • Restructured SEBs • Identification of entities for intra-State ABT • Scheduling Principles & Procedures • Commercial Principle • Metering Philosophy • Treatment of existing Agreements • Organisational Development • Regulatory Issues

  10. Implementation of intra-State ABT The main steps involved to implement intra-State ABT are: • Listing of entities on which ABT/UI mechanism to be applied • Listing of Metering locations and assess the requirement of meters and accessories • Finalize the specifications for meters and accessories • Presentation of the mechanism to all concerned • Finalisation of the tariff for all generating stations in ABT format.

  11. Implementation of intra-State ABT • Finalisation of shares of each distribution zones and other commercial arrangements • Organize installation & commissioning of meters and accessories. • Organising meter reading, data transfer and computation at SLDC • Establishment of the scheduling process along with scheduling software • Presentation/training to all concerned

  12. Implementation Plan • 1st Phase Activities • Finalisation of listing of entities • Listing of Metering locations • Finalisation of technical specifications & quantities of SEMs, DCDs/MTEs • Initiate tendering process for procurement of meters & RTUs

  13. Implementation Plan • 2nd Phase Activities • Finsalisation of Tariff of State Generating Stations as per ABT parameters/norms • Finalisation of Reactive Charge scheme • Finalisation of commercial mechanism for CPPs, Wind farms, Wheeling and banking, Open Access Customers etc. • Determination of Allocations of different Discoms in State Genco/ ISGS/ IPPs.

  14. Implementation Plan • 3rd Phase Activities • Supply and commissioning of meters at different locations • Installation of software for data processing • Installation of software for scheduling / energy accounting • Training • Estimate time for implementation – 12 to 18 months

  15. Status on intra-State ABT • Many SEBs restructured, others in process • State Utilities looking for benefits of intra-State ABT • took lead for intra-State ABT • Punjab took lead in Northern Region • Road-map for Maharashtra is ready • POWERGRID assisting these States by providing consultancy • Other States like MPSEB & Haryana to follow.

  16. INTRA STATE ABT

  17. Thank You

More Related