Resource Asset Registration Form Processing

Resource Asset Registration Form Processing. Art Deller. RARF Processing. Two methods to submit Through Internet MIS as Service Request (Preferred) Through ERCOT Legal ( mpappl@ercot.com , and cc: resourcereg@ercot.com )

Download Presentation

Resource Asset Registration Form Processing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Resource Asset Registration Form Processing Art Deller NATF

  2. RARF Processing • Two methods to submit • Through Internet MIS as Service Request (Preferred) • Through ERCOT Legal (mpappl@ercot.com, and cc: resourcereg@ercot.com) • Submitted by Authorized Representative (or backup Authorized Representative) of the Resource Entity • RARF forms and Guide located on ERCOT.com (http://www.ercot.com/services/rq/re/) • Must be on current version (currently 4.8) as .xls NATF

  3. RARF Processing • ERCOT Processing • Registration receives RARF and performs initial screening • Registration runs programmed business rules to ensure compliance with defined business rules and completeness of data • If passed, Registration communicates next Model Load Date to RE submitting request, based on Section 3.10.1, Timeline for Network Operations Model Changes • Model load date available on website (http://www.ercot.com/gridinfo/transmission/opsys-change-schedule) NATF

  4. RARF Processing • ERCOT Processing (cont) • Registration uploads RARF to data base of record and notifies Network Modeling Group (NMG) • NMG reviews RARF for accuracy and ability to model • NMG may have additional questions NATF

  5. RARF Processing NATF

  6. RARF Processing • Exception Process exists • If the Resource entity needs the change implemented earlier than the next normal model load date, they must request an interim update • Must submit an additional details and justification for interim update (New Form: Request for Interim Network Model Update) • NMG, via Registration, will communicate the earliest available date • Can manage changes of certain parameters through Market Manager, and/or Outage Scheduler NATF

  7. MMS Resource Parameters • Generation Resource Parameters in Market Manager • Normal Ramp Rates • Emergency Ramp Rates • Minimum Online Time • Minimum Offline Time • Maximum Daily Starts • Maximum Weekly Starts • Maximum Weekly Energy • Hot Start Time • Intermediate Start Time • Cold Start Time • Hot to Intermediate • Intermediate to Cold NATF

  8. Questions QUESTIONS? NATF