1 / 8

Where to put Towers A and B in the Grid – technical issues

This document discusses the technical considerations and reasoning behind the placement of Towers A and B in the Grid. It also includes information on cable lengths, installation sequence, and cross-checks with various experts.

starg
Download Presentation

Where to put Towers A and B in the Grid – technical issues

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Where to put Towers A and B in the Grid – technical issues 18-Jan-2005 L. Wai (SLAC/Group K) for LAT I&T

  2. Baseline plan for first two towers radiator +Y • Defined in LAT-MD-676 • TEM/TPS – GASU/PDU cable lengths optimized for baseline sequence • First two towers in baseline sequence are bays 8 & 9 • Connector savers on first TEM/TPS come off to allow insertion of second CAL module • Flight TEM/TPS – GASU/PDU cables and associated cable tray hardware are installed for 2-tower testing +X SIU PDU GASU +Z coming out of page radiator MGSE rotation axis

  3. Baseline plan reasoning • Start on PDU side and work towards SIU side for ease of cable installation • Start in center and work towards edges for ease of tower installation • Install “opposing” pairs including associated cable trays and flight cables to minimize risk in electrical testing

  4. New considerations since baseline planning

  5. Particle physics detector “intuition” • Put the best detectors on the inside; for LAT, this means bays 5, 6, 9, 10, • Put detectors on the outside good enough for background rejection; for LAT, put towers with most bad channels in corners • Don’t use data from outside an analysis defined “fiducial volume” in final analysis

  6. Best option, given current information and status of flight hardware and EGSE: Grid bays 0,4

  7. Proposed installation sequence • TKR-A / FM104 into bay 0 • TKR-B / FM105 into bay 4 • Keep connector savers on and use EGSE TEM/TPS-GASU/PDU cables for 2-tower test • Return to start of baseline installation sequence with subsequent towers

  8. Cross-checks • Martin Nordby (integration issues) • “no show stoppers” • Gary Godfrey (Van De Graaff issues) • “no show stoppers” • Eric Gawehn (MGSE issues) • “no show stoppers” • Bill Atwood (physics issues) • “no show stoppers”

More Related