ELENA Project Installation follow-up Erwan Harrouch EN-MEF
Worksite follow-up • Mechanical support installation • Next : BTV support and LNE50 supports – Planned on Friday Erwan Harrouch EN-MEF
Worksite follow-up • Source re-installation • Relocation of the gaz pipe not sufficient to install the back cover. • Relocation of the complete gaz panel needed for the end of the year. 2 weeks without gaz for the experiments. • Date to be defined Erwan Harrouch EN-MEF
Worksite follow-up • CV works : • Pipes on the shielding have been re-routed • The cooling pipes inside AD has been modified to remove the valve • The water will be back around 16h00 Erwan Harrouch EN-MEF
Worksite follow-up • Cabling activities on standby until next week • Work foreseen during the YETS for cabling activities : • Pulling of the kickers cable : Done • Cable tray installation next to LNI : Done • Cable tray installation from the power room to ELENA : Start in January • Request for 200 additional control cables will be pulled in February (At the same time of the DC cable campaign) – Last call to send your “demande d’ installation de câble” Erwan Harrouch EN-MEF
Worksite follow-up • LV installation • Installation on-going Erwan Harrouch EN-MEF
Worksite follow-up Beginning of IT Worksite (2weeks) • Pulling of cables (~200) in between the ground level of the racks and the new platform • Few cables to be pulled around ELENA • Relocation of their equipment on Tuesday morning – False floor should stay closed at the ground level of the racks (Between the two first rows) Erwan Harrouch EN-MEF
Worksite follow-up • LNI Installation – Preparation works : • Modification of the cooling pipes on the shielding (F. Moro) • Delivery of the steel blocks for the wall (F. Bais) • Removal of the cable on the wall (P. Burdelski) • Relocation of the purge valve (F. Moro) (If confirmed) • General cleaning of the area (E. Harrouch) • Dismantling of the barriers (A. Bouvard) Erwan Harrouch EN-MEF
Worksite follow-up • LNI Shielding openning • Ouverture du murVendredi - Lundi (Stockageen zone Gbar) • Stockageen zone Gbar • Béton : 4888x7 1688x2 24168x4 • Acier: 1682x5 882x6 1684x2 Erwan Harrouch EN-MEF
Worksite follow-up • Préparation par TE-VSC • Pompe à relocaliser • Pompe ionique à sortir • Chambre à vide + support à retirer Erwan Harrouch EN-MEF
Worksite follow-up • Travaux survey • Network consolidation willstart on Monday. • Ground marking (TE-ABT needed to relocate the kicker cables) Erwan Harrouch EN-MEF
Plan de calepinage LNI Erwan Harrouch EN-MEF
Power room modifications Start on the 3rd of December Erwan Harrouch EN-MEF
Summary of the work planned next week • Powering of the new platform (R. Necca) • Mechanical support installation (A. Kolehmainen) • Preparation for LNI installation (E. Harrouch) • Dismantling of the barriers (Today) • Opening of the shielding and storage of the shielding blocks : Friday-Monday (Transport) • Relocation of the pumps and vacuum chamber Monday (A. Sinturel) • Consolidation of the survey network + Ground Marking : Tuesday – Thursday (T. Dobers) • General cleaning of the area (E. Harrouch) • Cleaning of Gbar area (E. Harrouch) • IT installation Erwan Harrouch EN-MEF