1 / 14

ELENA Project

ELENA Project. Installation follow-up. W orksite follow-up. Mechanical support installation Next : BTV support and LNE50 supports – Planned on Friday. W orksite follow-up. Source re-installation Relocation of the gaz pipe not sufficient to install the back cover.

stephanyj
Download Presentation

ELENA Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ELENA Project Installation follow-up Erwan Harrouch EN-MEF

  2. Worksite follow-up • Mechanical support installation • Next : BTV support and LNE50 supports – Planned on Friday Erwan Harrouch EN-MEF

  3. Worksite follow-up • Source re-installation • Relocation of the gaz pipe not sufficient to install the back cover. • Relocation of the complete gaz panel needed for the end of the year. 2 weeks without gaz for the experiments. • Date to be defined Erwan Harrouch EN-MEF

  4. Worksite follow-up • CV works : • Pipes on the shielding have been re-routed • The cooling pipes inside AD has been modified to remove the valve • The water will be back around 16h00 Erwan Harrouch EN-MEF

  5. Worksite follow-up • Cabling activities on standby until next week • Work foreseen during the YETS for cabling activities : • Pulling of the kickers cable : Done • Cable tray installation next to LNI : Done • Cable tray installation from the power room to ELENA : Start in January • Request for 200 additional control cables will be pulled in February (At the same time of the DC cable campaign) – Last call to send your “demande d’ installation de câble” Erwan Harrouch EN-MEF

  6. Worksite follow-up • LV installation • Installation on-going Erwan Harrouch EN-MEF

  7. Worksite follow-up Beginning of IT Worksite (2weeks) • Pulling of cables (~200) in between the ground level of the racks and the new platform • Few cables to be pulled around ELENA • Relocation of their equipment on Tuesday morning – False floor should stay closed at the ground level of the racks (Between the two first rows) Erwan Harrouch EN-MEF

  8. Worksite follow-up • LNI Installation – Preparation works : • Modification of the cooling pipes on the shielding (F. Moro) • Delivery of the steel blocks for the wall (F. Bais) • Removal of the cable on the wall (P. Burdelski) • Relocation of the purge valve (F. Moro) (If confirmed) • General cleaning of the area (E. Harrouch) • Dismantling of the barriers (A. Bouvard) Erwan Harrouch EN-MEF

  9. Worksite follow-up • LNI Shielding openning • Ouverture du murVendredi - Lundi (Stockageen zone Gbar) • Stockageen zone Gbar • Béton : 4888x7  1688x2 24168x4 • Acier: 1682x5 882x6 1684x2 Erwan Harrouch EN-MEF

  10. Worksite follow-up • Préparation par TE-VSC • Pompe à relocaliser • Pompe ionique à sortir • Chambre à vide + support à retirer Erwan Harrouch EN-MEF

  11. Worksite follow-up • Travaux survey • Network consolidation willstart on Monday. • Ground marking (TE-ABT needed to relocate the kicker cables) Erwan Harrouch EN-MEF

  12. Plan de calepinage LNI Erwan Harrouch EN-MEF

  13. Power room modifications Start on the 3rd of December Erwan Harrouch EN-MEF

  14. Summary of the work planned next week • Powering of the new platform (R. Necca) • Mechanical support installation (A. Kolehmainen) • Preparation for LNI installation (E. Harrouch) • Dismantling of the barriers (Today) • Opening of the shielding and storage of the shielding blocks : Friday-Monday (Transport) • Relocation of the pumps and vacuum chamber Monday (A. Sinturel) • Consolidation of the survey network + Ground Marking : Tuesday – Thursday (T. Dobers) • General cleaning of the area (E. Harrouch) • Cleaning of Gbar area (E. Harrouch) • IT installation Erwan Harrouch EN-MEF

More Related