1 / 10

The Corporation of the Town of Amherstburg Public Works Department

The Corporation of the Town of Amherstburg Public Works Department. 2013. CAPITAL BUDGET Presented to: The Heavy Construction Association March 20, 2013. ROADS DEPARTMENT. Texas Road Reconstruction – 2 Year Program $ 6,000,000

Download Presentation

The Corporation of the Town of Amherstburg Public Works Department

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Corporation of the Town of Amherstburg Public Works Department 2013 CAPITAL BUDGET Presented to: The Heavy Construction Association March 20, 2013

  2. ROADS DEPARTMENT • Texas Road Reconstruction – 2 Year Program $ 6,000,000 • Sandwich Street Surface Asphalt Rehabilitation $ 615,000 • 6th Conc. North Resurfacing – Phase 2 of 2 $ 387,500 • 2013 Tar & Chip Program $ 200,000 • County Wide Active Trail System Contribution $ 110,000 • Roads Needs Study Update $ 75,000 • Sandwich Street Alignment of Lanes & Line Painting $ 40,000 • Traffic Signal Control Cabinet Replacement Program $ 25,000 • Tree Inventory Update $ 20,000 $ 7,472,500

  3. ROADS DEPARTMENT - BRIDGES • Bi-Annual Bridge Inspections – Engineering $ 20,000 • Bridge over Sucker Creek at 8th Conc. - Structural Investigation$ 4,120 $ 24,120

  4. ROADS DEPARTMENT – MUNICIPAL DRAINS • North Townline Drain Culvert Replacements $ 180,000 • Dufour Drain Improvements $ 150,000 • Leo Beaudoin Drain Culvert Replacements $ 85,000 • Major Drain & Extension Culvert Replacements $ 36,000 • 8th Concession Road Drain Culvert Replacements $ 30,000 • Collison Drain – New Access Culvert $ 16,900 • George Anderson Drain Culvert Replacement $ 16,230 • Hamel Drain – New Access Culvert $ 14,960 $ 529,090

  5. SANITARY SEWER COLLECTION SYSTEMS • King Street Sanitary Sewer Renewal – Phase 2 From Gore to Richmond $ 350,000 $ 350,000

  6. SANITARY TREATMENT SYSTEMS • Amherstburg Wastewater Treatment Plant • Connection of Edgewater Lagoon System to Plant $ 1,600,000 • Boblo Wastewater Treatment Plant • Standby Generator – Portable Unit $ 50,000 • Big Creek Wastewater Treatment Plant • Sewage Pump Replacement – Pump 1 of 2$ 10,000 $1,660,000

  7. WATER DISTRIBUTION SYSTEM • Riviera Place/Drive Watermain Upgrade $ 225,000 • 6th Concession North Watermain Upgrade $ 220,000 • Hamilton/Wilkinson Court Watermain Upgrade $ 190,000 • Automatic Radio Meter Reading Program $ 97,500 • Redevelopment of Old Water Tower Site at Alma & Venetian $ 30,000 $ 762,500

  8. AMHERSTBURG WATER TREATMENT PLANT • Construction of New Clarifier – 2-year project (2013 funds) $ 262,000 • SCADA System Implementation $ 100,000 $ 362,000

  9. MISCELLANEOUS EQUIPMENT • 8-Ton Dump Truck w/ Salter, Plow & Wing $ 225,000 • 1-Ton Dump Truck w/ Salter & Plow $ 75,000 • General Maintenance Pickup Truck $ 40,000 • Sewer & Water Locates Pickup Truck $ 40,000 • Weather Stations (2 per year) $ 3,500 $ 383,500

  10. 2013 CAPITAL PROJECTS • Roads Division $ 8,025,710 • Wastewater Division $ 2,010,000 • Water Division $ 1,124,500 • Miscellaneous Equipment $ 343,500 Total 2013 Capital $ 11,503,710

More Related