Right-of-Way Cost Estimating Ohio DOT Perspective

Right-of-Way Cost Estimating Ohio DOT Perspective. R/W & Utilities Subcommittee Conference Florida 2007. Project Development Process. All projects must go through a PDP Process to: ● E ncourage communication among all disciplines ● I ncrease plan quality

suchi
Download Presentation

Right-of-Way Cost Estimating Ohio DOT Perspective

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Right-of-Way Cost Estimating Ohio DOT Perspective R/W & Utilities SubcommitteeConference Florida 2007

  2. Project Development Process All projects must go through a PDP Process to: ● Encourage communication among all disciplines ● Increase plan quality ● Foster better management of the agency’s resources ● Document reasoning behind project-related decisions • Documentation includes Right-of-Way cost estimating which is: • Required at the initiation of a project • Updated throughout PDP process, and • Becomes part of the decision making process

  3. Project Types Projects are divided into 3 types

  4. STEPS 1-10 OF THE OF THE PDP PROCESS On Major Projects (Steps 1- 6) • No real plans at this point; many assumptions must be made. • Market Survey and Tax Roll data are used to estimate costs. • Conversations with Realtors, Auctioneers • Pulling base comparables from local MLS • Talk to County Auditor to find comparables they use for various property types • Pull Tax Roll data on random sampling of properties within project area On Major Projects (Steps 7-10) • Once preferred alignment selected, overlay alignment over tax maps and aerials. Determine: • the take • the impact to the residue • relocation issues • valuation formats • complexity of the project • time necessary for the acquisition, and • capacity of in house staff versus using consultants • Gather verified market data for more accurate costs • Data books having verified sales that are reflective of the property types being impacted • People along the project site physically inspecting the take area and the residue and determining the impact of the take on the residue • Start assessing complexities of acquisition-appraisal-relocation processes on preferred alignment • Estimate of damages to residue becoming more apparent • Serious R/W project management starts, and R/W Costs become market driven at this point

  5. General Formula Estimate value today (Compensation paid)(at Step 1) + Relocation Costs(Est. Payment to owner)(at Step 5) + Consultant Labor Costs (at Step 6) Subtotal A + Adj. for Time(Current to R/W Authorization date)(at Step 1) Subtotal B + Adj. for Administrative Settlements (at Step 1) + Adj. for Appropriations (at Step 1) +Adj. for Incidental Expenses(at Step 1) TOTALCOST TOTAL COST ROUNDED

  6. Information onRelocation Costs Relocation Costs(Est. Payment to Owner): ● Residential Owner $ 40,000 ● Residential Tenant $ 11,750 ● Commercial/Farm $ 25,000 ● Personal Property $ 1,000

  7. Information onLabor Costs Consultant Labor Costs: Titles . . . . . . . . . . . . . . . $ 400/pcl Appraisal Simple . . . . . . . $ 750/pcl Detailed . . . . . . $ 4,000/pcl Appraisal Review Simple. . . . . . . . $ 500/pcl Detailed . . . . . . $ 2,000/pcl Negotiation . . . . . . . . . . $ 1,100/pcl Relocation PP Move . . . . . . $ 1,500/displacee Residential Move $ 5,200/displacee Commercial Move$ 5,600/displacee Closings . . . . . . . . . . . . . $ 400/ownership Project Management . . . $ 550/pcl Asbestos Testing . . . . . . $ (determined by project)

  8. Information onAdjustments Adjustment for Time: ● Based on market support or average % of change in CPI over last 5 yrs. Adjustment for Administrative Settlement: ● Assume 15% of parcels settle by Adm. Settlement at average of 20% over offer ●[Subtotal B x 0.15] x 1.20 Adjustment for Appropriation ●Assume 10% of parcels will be appropriated ● Appropriated parcels will settle at amount 50% over offer ● Formula is [Subtotal B x 0.10] x 1.50 Adjustment for Incidental Expenses ● Assume ODOT will have some incidental expense ● 90% of parcels will settle and close ● Amount is estimated to be 2.5% of settlement amount ● Formula is [Subtotal B x 0.90] x 0.025

  9. STEP 1 OF THE PDP PROCESS • Working with stakeholders to understand problems and needs • No plans • Defining the Study Area • Developing an initial cost estimate _________________________________ This is what you have……….. A 500 square mile study area

  10. STEP 1 OF THE PDP PROCESSDefining the Study Area - 500 Sq. Mile Study Area

  11. Developing an Initial Cost Estimate Given the study area, I’m assuming that the highway will be: ● a single corridor (located somewhere in the study area): ● a 4 lane divided facility ● 300 feet wide ● the length of the study area _________________________________ Visualizing the assumptions……..a defined area

  12. STEP 1 OF THE PDP PROCESSGreen Line is Defined Area

  13. Determining“Value Today”for the Formula Working with a corridor that is 300 ft. wide x 36 miles long: 1. Determine Land Usage Within this Corridor: • By using a combination of aerial photographs and County Profiles, one can assume: ●70%agricultural●24%residential ●5%commercial●1%industrial 2. Determine values appropriate for land usages within corridor: • Ignore structures within the corridor • Focus only on the land • Ask local Realtors and Auctioneers what land is going for (now too difficult to use tax roll data) 3. Break the 36 mile long corridor into land-use segments; verify per-acre price for each segment: • Agricultural Land $3,500/acre • Residential Land $5,000/acre • Commercial Land $7.00/SF or $304,920/A • Industrial Land $2.50/SF or $108,800/A

  14. Determining“Value Today”for the Formula (cont’d) Using 5,280 LF = 1 mile/43,560 SF = 1 Acre: 1. Calculate the total acreage within corridor. • Determine how many linealfeet are in the 36 mile corridor: 36/Miles x 5,280/LF = 190,080/LF • Determine how many squarefeet are in the corridor: 300/ft. wide x 190,080/ft. long = 57,024,000 SF • Determinehow many acres are in the corridor: 57,024,000 SF ÷ 43,560 = 1,309 Acres in the corridor 2. Calculate the number of acres in each land use segment using the land-use ratios. • Calculate the value of the acres in each land use segment. • Calculate the value of all the land in the corridor as of today. Goes into the formula

  15. Determining Adjustment for Timefor the Formula • Adjust current value forward in time to anticipated Sale Date or R/W Authorization Date • This information provided by District Office • Assume 4 years from now • Time is based on market evidence or CPI and tempered with reason • Reflects history and not necessarily indicative of the future • Assume 2.5% per year increase over thenext 4 years • Using an HP-12C calculator, the time adjustment is: 4N 2.5i 1CHS PV Solve for FV = 1.1038 $26,164,710 x 1.1038 = $28,880,607 Goes into the formula

  16. Developing the Cost EstimateDetermining Other Adjustments for the Formula Adjustment for Administrative Settlements [ $28,880,607 x 0.15] x 1.20 = $5,198,509 Adjustmentfor Appropriations [$28,880,607 x 0.10] x 1.50 = $4,332,091 Adjustmentfor Incidentals [$28,880,607 x 0.90] x 0.025 = $649,813

  17. STEP 1Entering Other Adjustments into the Formula Estimate value today (Slide 16) $26,164,710 Relocation Cost (at Step 5) -0- Consultant Labor Cost (at Step 6)-0- Subtotal A$26,164,710 Adj. for Time (Slide 20) x 1.1038 Subtotal B $28,880,607 Adj. for Administrative Settlements (Slide 22) + 5,198,509 Adj. for Appropriations (Slide 22) + 4,332,091 Adj. for Incidentals (Slide 22) + 649,813 Total Estimated Cost$39,061,020 Rounded to: $39,060,000

  18. STEP 7 - An Overview • 3. Create a Sales Data Book • ● All Sales in Sales Data Book to be • of vacant land • ● Utilize local Realtors, appraisers, • staff or consultants • ● Verify market data to reflect • property types in the corridor • ● Use ODOT standard data sheet 1. Preferred alignment identified 2. Approximate centerline known ●Topographical ground survey features collected ● Utilities and their depths shown ● Railroad acquisitions identified ● Preliminary Plan and Profile sheets shown ● Preliminary construction limits shown ● Cross section being developed ● Individual auditor parcels now known 3. Create a Sales Data Book ● All Sales in Sales Data Book to be of vacant land ● Utilize local Realtors, appraisers, staff or consultants ● Verify market data to reflect property types in the corridor ● Use ODOT standard data sheet 4. Update Costs Estimate for: ● Improved properties ● Damages to residue properties ● Relocation Costs ● Consultant Labor costs for R/W Acquisition

  19. STEP 9 - An Overview Overview ● Stage 1 review completed; comments incorporated into the Stage 2 design ● Preliminary R/W Plans available ● Summarize environmental commitments; prepare environmental plan notes ● Stage 2 Detailed design is created at the end of this step Address Serious Project Management Decisions • Time needed for relocation process • Use staff or consultants for relocation • Time needed for acquisition parcels • Use staff or consultants Determine the complexity of the appraisal process • Engage the appraisal reviewer • Create parcel impact notes • Define the valuation issues • Determine the scope of appraisal needed • Determine the type of appraisal needed • Use staff or consultants

  20. STEP 9 - An Overview Other Determinations • Consultant utilization • Money needed to pay the consultant • Process to encumber money, and • Contracting process to engage consultants Update Cost Estimate ● Preliminary R/W Plans basis for cost estimate • Workplan used to estimate costs ● Pre-Acquisition Surveys initiated for Relocation parcels • Skilled relocation people estimating relocation cost ● Tax roll data no longer used for improvements • Skilled eminent domain people estimating value to improvements taken and damages (if any) to residue ● Update labor cost Example of a Step 9 Cost Estimate ● Focus will be on 1 Parcel ● Based on Preliminary Plans ● Use: Summary Sheet (Slide 37) Property Map Sheet Detail Sheet

  21. Parcel 283 WL Before – 5.371 Net Acres Take – 1.783 Acres Remainder – 3.588 Acres

  22. House located along existing road at front of property At grade crossing at Intersection of US 24 and Whetstone Road New 4 lane median Divided road, limited access Located to the rear of the property

  23. Small horse barn 103 ft. from R/W 1,570 LF of 4 Strand barb wire Fence on wood poles taken LA R/W CL of Project

  24. From the Cross Section and the Data Book Using Information from the Cross Sections ● Grade change is minimal – about 4 feet ● EOP is about 100 feet from the rear property line Using Information from the Data Book Zoning for Parcel 123: AG Residential ● Defined as Agricultural Residential ● Min site size is 1.5 acres ● Setbacks are: 50 feet from CL of any road 30 feet from the rear property line 15 feet side property line ● Min. frontage of 200 feet Land value ● For 5 to 10 acre Residential Use Properties ● Ranges from $3,000 to $5,000 per acre

  25. STEP 9 - Determining Estimate ValueToday From Data Book Range is $3,000 to $5,000/A Estimate $4,000/Acre Take Area is 1.783 Acres Land Value Estimate: ●$4,500/A x 1.783 A = $8,023 Improvements Taken: Fence taken – 1570 LF Cost New is $7.00/LF Fence taken is older – Est. 50% depreciated ● $7.00 x 50% = $3.50 Estimate of Fence: ● 1,570 LF x $3.50/LF =$5,495 Damages: No fence along R/W to keep livestock out of roadway Need CTC to create a fence Cost to Cure ● 214 feet x $7.00/LF =$1,498 Put It Together Land Value Estimate: $ 8,023 Estimate of Fence: $ 5,495 Cost to Cure: $ 1,498 Est. Value Today: $15,016

  26. STEP 9 - Determine Consultant Labor Costs Consultant Labor Cost: ● Amounts from Slide 9 _______________________________________ Titles $ 400/parcel Appraisal – Simple $ 750/pcl Appraisal Review – Simple $ 500/pcl Negotiation $1,100/pcl Closings $ 400/ownership Project Management $ 550/pcl Total$3,700/Parcel 123

  27. STEP 9 - Determining Adjustment for Time Adjustment for Time: ● Time is to based on market evidence or CPI and is also to be tempered with reason. ● Reflects history and not necessarily indicative of the future ● Assume 2.5% per year increase ● Assume from current date until R/W clear date of 2.5 years Calculate It Using an HP-12C calculator, the time adjustment is: 2.5N 2.5i 1CHS PV Solve for FV = 1.0638 $18,716 x 1.0638 = $19,910

  28. STEP 9 - Determining Other Adjustments Adjustmentfor Settlements [ $19,910 x 0.15] x 1.20 = $3,584 AdjustmentforAppropriations [$19,910 x 0.10] x 1.50 = $2,986 AdjustmentforIncidentals [$19,910 x 0.90] x 0.025 = $ 448

  29. STEP 9 - Updating the Formula Estimate value today: (slide 58)$15,016 + Relocation Cost: -0- + Consultant Labor Cost$ 3,700 Subtotal A$18,716 +Adj. for Timex 1.0638 Subtotal B $19,910 +Adj. for Adm. Settlements (slide 53)$ 3,584 + Adj. for Appropriations (slide 53)$ 2,986 +Adj. for Incidental Expenses (slide 53) $ 448 Total Cost$26,928

  30. Questions? • Douglas S. Maitland • Ohio DOT • (614) 466-6802 • dmaitland@dot.state.oh.us