Machine Checkout 2012 J. Wenninger, R. Gianchino, M. Albert
Schedule Expected end of powering tests • The machine checkout period covers W10 and part of W11. LBOC - Machine Checkout
Tunnel activities planning Pt2 LBOC - Machine Checkout
Tunnel activities Pt8 LBOC - Machine Checkout
Who? • Machine checkout coordination by R. Giachino and M. Albert – starts W10. • Back up J. Wenninger. • Starting in W10 we will organize 17:00 meetings in the CCC glassbox to coordinate the activities (in addition to 8:30). • Experience shows that the evening are the most efficient periods. • Time for meetings weekend of W10 to be defined. LBOC - Machine Checkout
What? • Main aims of W10: • Run the machine (PCs, collimators, if possible RF & ADT) through the full cycle: injection, ramp, squeeze, ramp down, pre-cycle. • Close the BIS loop and arm the LBDS. Dry-test the LBDS. • Pulse the MKIs in Pt2 and Pt8. • LHC beams (at least some pilots…) to the downstream TEDs. • Weekend of W10 (Sat 10thand Sun 11th) is likely to be the most efficient period. • Please no accesses !!! • For the experiments: • We will set the beam mode to STABLE BEAMS during this period !! We will give some pre-warning on page1. LBOC - Machine Checkout