BioWire Progress Report Week Six “Halfway There”

BioWire Progress Report Week Six “Halfway There”. Orr Ashenberg, Patrick Bradley, Connie Cheng, Kang-Xing Jin, Danny Popper, Sasha Rush. Last Week. [Almost] Finished building Lux parts Did experiments with Lux senders Got cleanroom certification. Building the Circuits. Lux

suki
Download Presentation

BioWire Progress Report Week Six “Halfway There”

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BioWire Progress ReportWeek Six“Halfway There” Orr Ashenberg, Patrick Bradley, Connie Cheng, Kang-Xing Jin, Danny Popper, Sasha Rush

  2. Last Week • [Almost] Finished building Lux parts • Did experiments with Lux senders • Got cleanroom certification

  3. Building the Circuits • Lux • All parts finished (except receiver test construct). • Started moving plasmids in order to cotransform. • Las • Still building parts. • Switched constitutive promoters, P(Bla)-->P(Cat) because the old part just wasn’t working. • Moved within two cycles of finishing.

  4. Experiments

  5. Sender Construct (LVA+): aTc -> AHL Receiver Construction Intermediate: J06006 J06001 Receiver Output Component (Weiss): AHL -> YFP, cI repressible Sender Construct (LVA-): aTc -> AHL J06002 J06005 Sender Reporter (eCFP), Ptet Test Receiver Output+Propagation Component: AHL-> {YFP, AHL}, cI repressible, LVA+ J06003 Receiver Test Construct: AHL -> YFP J06007 Receiver Output+Propagation Component: AHL-> {YFP, AHL}, cI repressible, LVA- J06000 Receiver Repressor Component: AHL -> cI J06008 J06004 Lux System Constructs

  6. Lux System Constructs: Status Lig./Trans. 7/15, miniprep today Done Construct Status Notes Sender Construct (LVA+): aTc -> AHL Completed J06001: Ptet+luxI(LVA+) Done (R0040+B003x)+(C0161+B0015) Sender Construct (LVA-): aTc -> AHL J06002.x: Ptet+luxI(LVA-) Completed Sender Reporter (eCFP), Ptet Test J06003: Ptet+ ECFP Receiver Test Construct: AHL -> YFP Building I13272 missing. (R0063+I0462) +(R0062+E0432) J06000: LuxPL + luxR + luxPR + YFP Receiver Repressor Component: AHL -> cI Done F2621 initially missing. ([(R0063+I0462) + R0062] + [B003x + (C0051+B0015)]) J06004.x (vary RBS)

  7. Lux System Constructs: Status Construct Status Notes NO! Receiver Output Construction Intermediate: (R0065+B0034) + E0032 J06006 Done (R0065+B0034)+(E0032 + B0015) Receiver Output Component (Weiss): AHL -> YFP, cI repressible J06005 Receiver Output+Propagation Component: AHL-> {YFP, AHL}, cI repressible, LVA+ Done (((R0065+B0034) + (E0032 + B003x))+(C0061 +B0015)) x=1,2,4 J06007.x (((R0065+B0034)+ (E0032 + B003x))+(C0161 +B0015)) x=1,2,4 Receiver Output+Propagation Component: AHL-> {YFP, AHL}, cI repressible, LVA- Done J06008.x

  8. Sender Construct (LVA+): aTc -> AHL Receiver Construction Intermediate: Receiver Output Component (Weiss): AHL -> YFP, cI repressible Sender Construct (LVA-): aTc -> AHL Sender Reporter (eCFP), Ptet Test Receiver Output+Propagation Component: AHL-> {YFP, AHL}, cI repressible, LVA+ Receiver Test Construct: AHL -> YFP Receiver Output+Propagation Component: AHL-> {YFP, AHL}, cI repressible, LVA- Receiver Repressor Component: AHL -> cI Las System Constructs

  9. Las System Constructs: Status Lig./Trans. 7/15, miniprep today Done Construct Status Notes Sender Construct (LVA+): aTc -> AHL Building (R0040+B0034) + (C0078+B0015) J06101: Ptet+lasI(LVA+) Building (R0040+B0034) + (C0178+B0015) Sender Construct (LVA-): aTc -> AHL J06102.x: Ptet+lasI(LVA-) Completed Sender Reporter (eCFP), Ptet Test (I14033+ (B0034+C0079+B0015 + R0079)) = J06400 (I14033+ (B0034+C0079+B0015 + R0079))+E0432= J06100 J06103=J06003: Ptet+ ECFP Receiver Test Construct: AHL -> YFP Building J06100: PBla + lasR + PLasR + YFP Receiver Repressor Component: AHL -> cI Building J06400 + ( B003x+C0051+ B0015) x=4,1,2 J06104.x (vary RBS)

  10. Las System Constructs: Status Construct Status Notes NO! Receiver Output Construction Intermediate: ((I14016 + B0034)+ E0032) J06106 Building (I14016 + B0034)+ (E0032 + B0015) Receiver Output Component (Weiss): AHL -> YFP, cI repressible J06105 Receiver Output+Propagation Component: AHL-> {YFP, AHL}, cI repressible, LVA+ Building x=1,2,4 (I14016+B0034+E0032+B003x) + (C0078 + B0015) J06107.x x=1,2,4 (I14016+B0034+E0032+B003x)+(C0178 + B0015) Receiver Output+Propagation Component: AHL-> {YFP, AHL}, cI repressible, LVA- Building J06108.x

  11. Photolithography • Master • Completed general cleanroom training. • Will get tool-specific training as soon as Kit’s lab gets their SU-8 2. • Ordered (will order?) SU-8 2075. (Balance of low viscosity and good thickness.) • Talked with Microchem researcher about SU-8 types and protocols.

  12. Photolithography • Stamps • Poured PDMS negative molds out of 33 rpm vinyl records in Kit’s lab. • Continued to experiment with pouring stamps from 96- and 384-well plates, using 3% and 5% high gel strength agarose. • Stamped cells using last week’s stamps.

  13. Stamp Picture

  14. This Week • Building parts • Test constructs for Lux, finish Las parts. • Experiments • Photolithography • Go into cleanroom to make a master.

  15. Updated Schedule • Week 1 (6/6): Project Choice and Design • Week 2 (6/13): Got parts and set up tests • Week 3 (6/20): Began building test constructs, finished sender • Week 4 (6/27): Finish receiver, receiver w/repressor; CAD a mask • Week 5 (7/4): Continued building parts, received mask • Week 6 (7/11): Finished Lux, Tested senders, made PDMS molds • Week 7 (7/18): More experiments, finish Las, make first master/PDMS/stamp • Week 8 (7/25): Experiments • Week 9 (8/1): “ • Week 10 (8/8): “ • Week 11 (8/15): “ • Week 12 (8/22): “

More Related