LEIR Status

LEIR Status. C. Carli and M. Chanel on behalf of the LEIR and I-LHC team. General Comments on the Autumn 2006 LEIR Run What has (not) been achieved: Early LHC ion Beam Matching LEIR -> PS In view of the Nominal Beam Low level RF Schottky Diagnostics at high energy Conclusions Lessons

sumana
Download Presentation

LEIR Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LEIR Status C. Carli and M. Chanel on behalf of the LEIR and I-LHC team • General Comments on the Autumn 2006 LEIR Run • What has (not) been achieved: • Early LHC ion Beam • Matching LEIR -> PS • In view of the Nominal Beam • Low level RF • Schottky Diagnostics at high energy • Conclusions • Lessons • Detailed “To do list” (for completeness) LEIR Status

  2. General Comments on the Autumn 2006 LEIR Run • Vacuum leak(s) before and at the beginning: • Leak on a high voltage feed through (ion pump) detected on August 28th, • Preparation to exchange the electron cooler gun (known problem in this sector), • Bake-out between weeks 37 and 38, • Incident (heating of the cooler collector to >400 deg.) on September 19th, • Vacuum leak on collector – differential pumping (no varnish precaution) -> vacuum o.k., but sparks at the outside, • All PCs available on September 25th (should start with beam), • “Definite” fix (saving the run) with UHV varnish on October 4th by the SPS vacuum team (several leaks detected), • Thanks for all the efforts (workshop, AT/VAC teams, e-cooler team) • Magnetic cycle generation: • Test started at beginning of September, • Difficulties to make new lattice data available -> restart with old “LSA-supercycles” (system still in development !), • Efforts from the LSA team were crucial for us (thanks !). LEIR Status

  3. General Comments on the Autumn 2006 LEIR Run • Circulating beam again on September 26th (but no electron cooling !!). • Low level RF (new generation fully digital, by M.E. Angoletta & Co) • re-commissioning (during “normal” start-up, had been considered an issue), • continuous development during run. • Electron cooling: • Available on October 5th (after fix of the collector leak) only, • Cooling observed immediately. • LEIR beam circulated for the first time in PS on Thursday, October 12th: • almost on time – a miracle !! (planning: LEIR beam available on October 9th). • Until the end of the run (November 20th): • operational machine providing ion beam (h=1 AND later h=2) to the PS, • various machine studies in parallel. • Very limited support from OP LEIR Status

  4. What has (not) been achieved • Early beam: • Obtained (after sorting out technical problems – vacuum, cycle generation …) relatively easily, without too much readjustments, • LEIR is reproducible (like e.g. the PSB) apart injection line in PS tunnel, • One Linac 3 shot (> 22 mA) just sufficient. OASIS acquisition on October 9th LEIR Status

  5. What has (not) been achieved • Matching LEIR -> PS (and transverse emittances): • difficult due to the state of the instruments, • dedicated PS MD on Oct. 18th: “large” dispersion mismatch, • dedicated PS MD on Oct. 25th: almost perfect in horizontal, but strong vertical mismatch !! Vertical Profiles in PS ring (October 18th) Horizontal Profile on ETL.MSF10 (November 17th) LEIR Status

  6. What has (not) been achieved • In view of the nominal beam (schedule: “first exploratory studies”): • Nominal intensity accumulated, • Losses (not understood) at beginning of ramp, emittances NOT measured !! • Further studies (availability of measurements) required !! • Best we could obtain with the available resources. 80% of nom. intensity accelerated on Oct. 13th Nom. intensity at end of accumulation on Oct. 13th LEIR Status

  7. What has (not) been achieved • Low Level RF system: • “Pilot system” for a new generation of fully digital systems, • After re-commissioning, h=1 and h=2 operational beams provided for PS • “In the shadow”, continuous development of the system, • System very well advanced (close to completion), • Still to do: completion (diagnostics …) and transfer to operations. PU and transformer traces of a correctly synchronized h=2 beam LEIR Status

  8. What has (not) been achieved • Schottky diagnostics at high energy: • Special cycle: debunched beam on “long ejection plateau”, • Clear Schottky spectra with present (no cryogenics) system in all 3 planes. Vertical Schottky spectrum at high energy (average over ~20 shots) (courtesy J. Tan) Special cycle for Schottky measurements at high energy LEIR Status

  9. ConclusionsLessons • LEIR operational status • reasonably reproducible (say like the PSB), • apart technical problems (vacuum ..), reasonably smooth start-up, • “early” beam for the PS provided without particular problems, • vacuum upgrades successful: studies on nominal beam not limited by life-time (small margin? – intensity saturated at less than twice the nominal one), • electron cooler works well (gun/collector spare situation is a concern). • Needs for consolidation/completion (emittance and other measurements, hardware, RF low level …) • Still a long way to have the nominal LEIR beam available: • we did the best we could with the resources and time available, • (probably) not exhaustive list of issues: • improve accumulation rate (injection, Linac 3 current …), • better understanding of transverse damper, • understand losses at beginning of ramp (acceptances/emittances in all three planes, tune spreads ? …) LEIR Status

  10. Conclusions(detailed “to do list” for completeness) Detailed and (may-be still) not exhaustive “to do list”: LEIR Status

  11. Conclusions(detailed “to do list” just for completeness) LEIR Status

  12. LEIR Status