This application outlines the Centralia High School modernization project, including the project team members, scope, schedule, budget, and why it is suited for GC/CM. The project aims to upgrade the legacy high school, improve safety and security, update HVAC and electrical systems, and add state-of-the-art educational spaces.
E N D
Application for Project Approval Centralia High School Modernization
Agenda Agenda • Introduction of Project Team • Why this Project is Suited for GC/CM • Scope • Schedule • Budget and Funding • Questions
Project Team Project Team Project Team
Project Management Expertise Project Leadership Expertise Project Leadership Phil Iverson, Maintenance & Operations • 20 year industry veteran • Extensive experience with complex projects • Alternative Delivery experience Kasey Wyatt, Program Manager • 23 year industry veteran • Extensive GC/CM experience • Over $1 billion in K12 project Experience Lee Fenton, Principal In Charge • 30 Years industry veteran • Extensive K12 design experience • Extensive GC/CM experience
Project Management Expertise Project Leadership Expertise Project Leadership Jane Louie, Sr. Project Manager • 35 Year Industry Experience • GC/CM Trained Bob Lindstrom, Architect Project Manager • 28 year Industry Veteran • K12 Design Expertise • GC/CM Experience Cynthia Balzarini, Project Engineer • 10 Years industry experience • GC/CM experience
Exceeds Statute Requirements Why Project is Suited for GC/CM Centralia High School Modernization Project • Complex phasing and scheduling • Occupied • Involvement of GC/CM critical
Scope Centralia High School Modernization
Scope Centralia High School Modernization Modernization of 149,000 SF legacy High School • State of the art educational spaces • Upgraded safety and security • Site circulation • CCTV • Access controls • Expand and update HVAC & electrical systems • Energy efficient systems • STEM addition • OSPI STEM grant for 10,000 SF of classroom space • All classrooms under one roof (remove 8 portables)
Schedule Schedule • GC/CM Process July-September 2017 • 1stAdvertisement for GC/CM RFQ July 31, 2017 • 2nd Advertisement for GC/CM RFQ August 7, 2017 • GC/CM Presubmittal Meeting August 10, 2017 • Statement of Qualifications Due August 18, 2017 • Short-list Most Qualified GC/CM’s August 24, 2017 • Interview GC/CM’s September 7, 2017 • Open GC/CM Fee Proposals September 11, 2017 • Programming and Ed Specs September 2017 - January 2018 • Schematic Design January 2018 - April 2018 • Interim Housing Construction June 2018 • Construction Documents August 2018 - February 2019 • Permitting August 2018 - December 2018 • Construction November 2018 - December 2020 • Substantial Completion December 2020 • Final Completion/Closeout January - March 2021
Centralia High School Modernization Questions? Questions? Modernization Centralia High School