WBS 1.03 Readout Systems Scope, Cost and Schedule

WBS 1.03 Readout Systems Scope, Cost and Schedule. Gary Varner University of Hawaii. Talk Outline. WBS Element Scope Performance Requirements Cost Estimate Schedule Risk Summary. WBS 1.03 Scope (1). Readout electronics for the iTOP (WBS 1.02), and KLM (WBS 1.04) detector

sydneyk
Download Presentation

WBS 1.03 Readout Systems Scope, Cost and Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WBS 1.03 Readout SystemsScope, Cost and Schedule Gary Varner University of Hawaii

  2. Gary Varner, Belle II Directors Review (Pre CD-2/3) Talk Outline • WBS Element Scope • Performance Requirements • Cost Estimate • Schedule • Risk • Summary

  3. WBS 1.03 Scope (1) • Readout electronics for the iTOP (WBS 1.02), and KLM (WBS 1.04) detector • Design, prototype and evaluation of ASICs and readout boards within Belle-II DAQ environment • Procurement of all components • Assembly, integration and test of sub-detector readout modules • Delivery to sub-detector assembly sites 16-17 January 2013 Gary Varner, Belle II Directors Review (Pre CD-2/3) 3

  4. WBS 1.03 Scope (2) • Firmware for real-time ASIC operation and data flow control and monitoring • FPGA/DSP microcoding for waveform data reduction • Documentation and support of ASICs and readout modules • Low-level software modeling of trigger (tsim) and event buffer overflow prevention logic 16-17 January 2013 Gary Varner, Belle II Directors Review (Pre CD-2/3) 4

  5. Performance Requirements • Operate within the Belle II Trigger and Data Acquisition specifications • Meet the detailed timing and signal processing specifications for the iTOP and KLM sub-detectors • Fabricate using commodity components or processes with high yield and reliability assembly houses • Verify component and integrated module radiation tolerance for the background environment expected 16-17 January 2013 Gary Varner, Belle II Directors Review (Pre CD-2/3) 5

  6. CD-2/3 Cost Estimate – WBS 1.03 16-17 January 2013 Gary Varner, Belle II Directors Review (Pre CD-2/3) 6

  7. Cost Basis of Estimate • Reasonable Cost Range • Make up of cost estimate • 54% of total cost is subcontract of ASIC and circuit board fabrication and assembly • Competitive (commodity) quotes received for all components and assemblies • Engineering labor associated with prototype testing and final acceptance testing • Maturity of the estimate • Majority of remaining cost (67%) is commodity components or processes • Remaining estimate based on engineering estimate for development of calibration system, testing, and interface on mechanical system and actual cost from prototype articles. 16-17 January 2013 Gary Varner, Belle II Directors Review (Pre CD-2/3) 7

  8. Schedule – iTOP Readout • Key drivers/constraints • CD-3 April 2014 to support production readout procurement plan • Pre-tested readout assembled with completed modules for extended cosmic-ray verification prior to Belle II detector installation CR B B CR CR B Beam & Cosmic Tests Preproduction Readout CD-3 Production Readout Module Assembly Install & Commission Periods shown are calendar years 16-17 January 2013 Gary Varner, Belle II Directors Review (Pre CD-2/3) 8

  9. Schedule – KLM Readout • Key drivers/constraints • CD-3 April 2014 to support Scintillator production readout procurement plan • Pre-tested readout assembled with completed modules for extended cosmic-ray verification prior to Belle II detector installation CR w/ COPPER CR Cosmic Ray Tests Preproduction Readout CD-3 Production Readout Module+ Pre-amp Assembly Install & Commission Periods shown are calendar years 16-17 January 2013 Gary Varner, Belle II Directors Review (Pre CD-2/3) 9

  10. Identified Project Risks • One high risk remains • Gary Varner and team in Hawaii are overcommitted and cannot complete all assigned scope on schedule. • Mitigation has been to transfer electronics development and testing scope to other institutions (IU, PNNL, WSU, VT, USC) 16-17 January 2013 Gary Varner, Belle II Directors Review (Pre CD-2/3) 10

  11. Technical Risk Assesment • Performance of switched capacitor array waveform sampling has been well established in various experiments (ANITA, MUEGAMMA) • ASICs fabricated in high-volume, commodity IC vendor lines and are low risk • Module fabrication and QA/QC procedures are industry standard processes and low risk • Concurrent ASIC development cycles increase risk of delays due to design multi-tasking • Mitigate by having more stringent submission reviews with additional external experts • Further reduce stress on design engineering resources by increasing pool of qualified test and evaluation engineering talent 16-17 January 2013 Gary Varner, Belle II Directors Review (Pre CD-2/3) 11

  12. Conclusion • Scope of WBS well understood • Evidence – Performance achieved in beam and bench tests • Final opto-electro-mechanical configuration • Integration with existing Belle II DAQ infrastructure • Costs are known and fit within funding profile • Evidence – Costs defined by bid/vendor quote/similar work • Fits funding profile • Ready for CD-2 and (conditional) CD-3 pending success of recently submitted ASICs 16-17 January 2013 Gary Varner, Belle II Directors Review (Pre CD-2/3) 12