170 likes | 179 Views
Western Regulation Usage and Pilot Program Results. Regulation Usage. Real Time Load/Resource Balancing Frequency Response Net Interchange Deviations Maintain Uniform Ramp rates for Generation Dispatch and Net Interchange Schedule Changes Inadvertent Payback
E N D
Regulation Usage • Real Time Load/Resource Balancing • Frequency Response • Net Interchange Deviations • Maintain Uniform Ramp rates for Generation Dispatch and Net Interchange Schedule Changes • Inadvertent Payback • COI Mitigation (initial response) • BA Supplemental Regulation • Time Error Correction
Regulation Users • SNR Operations • SNR Merchant • SNR LSE’s • Host BA (SMUD now BANC) • WECC Interconnected Utilities
Regulation Refresher • Generating Units are set up to Receive Signals From an EMS AGC placed on Regulation. • WASN Provides 27 MW of Regulation for LSE Control Performance and another 33 MW’s to manage SBA Control Performance Requirements which equates to 60 MW’s of Regulation in the Up and Down Direction. • Inadvertent payback is limited to 10 MW (+) or (-). • Transmission loss forecast errors vary, but can be anywhere from 10 MW to as much as 50 MW. This Variance is Normally Driven by Market Conditions
Regulation Reduction Pilot Test Conclusions The Pilot Test Provided Enough Data to Support the Reduction of Regulating Margins During Certain Timeframes and Western’s Ability to Maintain Reliable Operation of the Western SBA The Test Also Indicated that the Requirements for Regulation are not Flat and Vary With System Conditions
Regulation Reduction Pilot Test Conclusions • The Pilot Test Results and Supplemental Studies by Operations Indicate that There are Additional Hours Where Regulation May be Reduced and Still Maintain Reliable Operation of the Western SBA • Western Will Coordinate with the USBR to Examine Those Hours and Times When this May be Possible
Future Regulation Pilot Test • Propose Another Pilot Test Beginning on or about Oct. 1, 2011 • Test to Include a Reduction in Up and Down Regulation • Test to Run for Approximately 180 Days, Concluding on or about March 31, 2012 • Western Will use 60 MW of Up and Down Regulation as the Base Requirement • Test Will Use Varying Levels of Reduced Up and Down Regulation.
Regulation Usage Studies • Operations Examined SBA Regulation Usage for the 2010 Calendar Year Including the Pilot Test Period • All 8760 Hours Were Sampled Each Hour Was Polled Twice Producing Over 16,000 Snapshots Each Snapshot has a Minimum of 10 Data Points • Operations Also Examined SBA Performance on an Hourly basis for 2010 Producing 8760 Data Points
Regulation Usage Studies Data • SBA NIA • SBA NIS • CVP Gen Scheduled • CVP Gen Actual • CVP Gen Set Point • SBA Load • Hourly Load Change • Hourly Tie Change • Hourly Gen Change • LSE Hourly Deviation • SBA Losses
Preliminary Study Results • Regulation Requirements are Reduced during the Late Fall, Winter and Early Spring • Regulation Requirements Increase during the Warmer Months
Preliminary Study Results • More than 40 MW of Down Regulation was Used in 254 Hours • More than 40 MW of Up Regulation was Used in 300 Hours • The SBA used 60 MW of Down Regulation in 53 Hours • The SBA used 60 MW of Up Regulation in 35 Hours
Peak Day Study ResultsAugust 25, 2010 • SBA Load 1501 MW @ 16:45 • SBA Load 1495 MW @ 17:15 • SBA Peak Load 1520 MW @ Approx. 17:00 • SBA NIA 140 MW (Net Exporter) • SBA NIS 130 MW (Net Exporter) • CVP Gen Scheduled 1169 MW • CVP Gen Actual 1199 MW • LSE Deviation -1 MW (Coming to the SBA)
Peak Day Study ResultsAugust 25, 2010 • LSE Total Deviation for the Day -125 MWH (Delivered to the SBA) • LSE Average Deviation for the Day -5.20 MWH (Delivered to the SBA) • LSE Hourly Peak Deviation for the day -16 MWH (Delivered to the SBA)
Peak Day Study ResultsAugust 25, 2010 • SBA Daily Scheduling Delta 385 MWH (Delivered from the SBA) • SBA Hourly Average Scheduling Delta 16 MWH (Delivered From the SBA) • SBA Peak Hourly Scheduling Delta 39 MWH (Delivered From the SBA)
Monthly Study ResultsAugust 2010 • LSE Maximum Daily Deviation 205 MWH (Delivered From the SBA) • LSE Maximum Daily Deviation -144 MWH (Delivered to the SBA) • LSE Maximum Hourly Deviation 33 MWH (Delivered from the SBA) • LSE Maximum Hourly Deviation -23 MWH (Delivered to the SBA) • LSEs out of Bandwidth 1 hour on 8/21 33 MWH
Preliminary Study Conclusions • Initial Data Suggests that that Loss Forecast Error and Net Interchange Deviations (Exports) Require More Detailed Analysis • Regulation Usage Patterns are Seasonal • LSE Deviation (Regulation Usage) is Relatively Neutral, Both + and – • There is opportunity to reduce the Amount of Regulation Necessary to Maintain Reliability
Next Steps • Analyze the Large Volume of Data in More Detail • Incorporate the Lessons Learned From the Regulation Pilot Test into SNR Daily Operations and the Next Proposed Pilot Test • GOAL: Reliably Reduce SBA Regulation Requirements in Both the Up and Down Direction