An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Re-setup of injection protection after ALICE polarity flip ABT, OP LBOC Meeting, 30-Aug-2011

  2. Orbit in IP2 ALICE spectrometer compensation bump + external bump: For sign flip in compensation bump also external bump is sign-flipped change of closed orbit INJP TDI INJP TDI LHC DR, p.535

  3. Re-establish LHC orbit... • In case orbit is not changed at the injection point • TI 2 trajectory can be kept • otherwise will need to • steer the TI 2 trajectory • (maybe) re-setup the TI 2 collimators

  4. Injection protection set-up I • Resteer the line [possibly] • Set up TCDIs to new TI 2 trajectory, and validate [possibly] – 12h • Centering • Check phase space coverage with oscillation bumps in TI 2 of +/- deg [0,30,60,90,120,150] deg System tolerance Setting + tolerance Nominal setting 15-Sept-2010

  5. Injection protection set-up II • TDI/TCLI centering, TDI tilt adjustment – 4h • Full beam scraping with TDI jaws separately; for -1, 0, +1 mrad jaw tilt • Centering of TCLI • TDI protection validation – 4h • Grazing the TDI jaw with different angles, I&D with pilots 20-April-11 • Total time estimate: • About 1 shift if present TI 2 TCDI setup remains valid • About 2.5 shifts if new TCDI set-up and revalidation necessary