1 / 19

East Midlands Modular Project

East Midlands Modular Project. Final Peer Review for Constructing Excellence James Rix Construction Team Manager – South PfP Developments Ltd. The Project Team. Why this route?. 4 Sites in the Midlands Tender Prices NBH owned the sites Using NBH standard house types

tangia
Download Presentation

East Midlands Modular Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. East Midlands Modular Project Final Peer Review for Constructing Excellence James Rix Construction Team Manager – South PfP Developments Ltd

  2. The Project Team

  3. Why this route? • 4 Sites in the Midlands • Tender Prices • NBH owned the sites • Using NBH standard house types • Needed to progress quickly • Pilot scheme needed

  4. PROPOSED BENEFITS Construction Time • On-site period – 50% No increase in period for design development • Utilities connections on critical path

  5. PROPOSED BENEFITS Predictability • Significantly Increased + 50% • Reduction in trade interfaces • Factory culture

  6. PROPOSED BENEFITS Defects - Aims • Significantly reduced – 50% • Quality built in, not inspected out • Increased Automation • Minimal Tolerances

  7. PROPOSED BENEFITS Productivity • Significantly increased • Less reliance on weather • Increased Automation • Deskilling of Process

  8. PROPOSED BENEFITS Turnover and Profits • Opportunity to double output using the same level of resource • Opportunity to increase profit due to limitation of risk

  9. BENEFITS Capital Cost • Need not be more expensive • Varies from Region to Region • Dependent upon Volume • Superstructure more expensive + 30% • Savings in: Substructure - 25% Preliminaries - 50% Design Fees - 50% Overheads - 30%

  10. Programme

  11. Fact Sheet • 4 separate sites • Total Contract Sum £905,000 • Cost per m2 £947 • Cost per dwelling £56,500 • Construction period 34 weeks • Form of contract JCT ’98 WCD

  12. Costs Fact Sheet

  13. How the Finances Stacked Up

  14. East Midlands Total Man Hours

  15. Key Performance Indicator's • Time – 55% saving • Cost – Accurate predictability • Quality – Defects 5% higher at handover • Man hours – 36% fewer / £100k

  16. East Midlands Modular Project – Lessons Learned - Prototype

  17. East Midlands Modular Project – Lessons Learned • Time of year influential / weather protection • Early involvement of Regulatory Bodies/ Funders • Coordination of Public Utilities • Access and logistics requirements fully appraised • Completion within factory • Valuations/Communications

  18. Lesson’s Learned • All design development must be 100% complete before the units go into production in the factory.

  19. BENEFITS Defects • Quality built in, not inspected out • Increased Automation • Minimal Tolerances

More Related