HCAL Commissioning Overview. What has been done Cabling HV-LED mechanics Signal cable -> CAMAC connection Detailed study of PMT stability LED spectra Suspicious PM+CW ~10 min relaxation Double peak for LED Access problem Complete signal cabling layout
E N D
HCAL Commissioning Overview • What has been done • Cabling • HV-LED mechanics • Signal cable -> CAMAC connection • Detailed study of PMT stability • LED spectra • Suspicious PM+CW • ~10 min relaxation • Double peak for LED • Access problem • Complete signal cabling layout • Narrow slit between muon filter and HCAL • Interference with muon chambers installation • Future 15.02.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)
HCAL Commissioning Signal cabling Connectors grouping (one mistake found) 15.02.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)
HCAL Commissioning Cabling Protected inside the electronics platform Top connectors fed through 15.02.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)
HCAL Commissioning Cabling • Cable interface to CAMAC • made 5 (40 channel) • needed 12 (+7 connectors) • due to module is spread • over 12 cable bundles 15.02.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino) C-side A-side
HCAL Commissioning Mechanics for HV-LED boxes HV-LED housing mechanics done 8 HCAL + 32 ECAL + few spare Waiting for motherboards and SPECS slaves 15.02.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)
HCAL Commissioning HV-LED HV-LED control board prototype SPECS slave LED8 1 3 5 7 . . . . . 9 0 2 4 6 8 CW power supply LED1 15.02.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)
HCAL Commissioning HV-LED spread over 10 DAC At least 6 hours per connector 15.02.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)
HCAL Commissioning Stability test Long term study of PM/LED performance with the HV-LED control board (SPECS) 8 9 10 11 • Typical trace-plot monitoring stability of LED pulse over several hours • pulse rate ~7.7 Hz • light yield ~7000 ph.e. • gain ~1.5E5 12 13 14 15 pinD2(on) pinD1(off) +1% -1% 15.02.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)
HCAL Commissioning Stability test (2) 1 0 2 3 Non-typical behavior of ch#2 2 6 5 7 4 15.02.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)
HCAL Commissioning LED signal study 8 9 10 11 LED pulse spectra WHAT IS IT??? Two peaks even @ 20s 9 12 13 15 14 15.02.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)
HCAL Commissioning Suspicious PM+CW location mod4 15.02.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)
HCAL Commissioning Access problem How to reach there (in the slit of 40cm) No chance to access PM-CW during muon chambers installation ??? HCAL Muon chamber installation schedule 18.01.06 Rustem DZHELYADIN (CERN&IHEP, Protvino)
HCAL Commissioning Future Preparing to the general commissioning of the LHCb detector the following has to be done • Measurement of Gain-HV for each PMT “in-situ” • Measurement of Delay-HV on LED-pulse (+7 mini-connectors needed) • Measurement of PMT linearity at different HV • Radioactive source commissioning and first run • Long-term stability monitoring for whole sub-detector Problemsstill • To complete the cabling of HCAL. • To solve the access problem (priority before June?) • PinD amplifiers to be screened up (dismantle 104 LED-PinD and install) • Exhaustive check of all PM-CW at C-side before June! 15.02.2006Rustem DZHELYADIN (CERN&IHEP, Protvino)