FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy Presentation to the Facility Advisory Committee June 16, 2008
Outline • Commission FEE Instruments • Offset mirror commissioning • SASE optimization • AMO experiment alignment • User Operations at ~4 GeV
Related Presentations • Paul Emma, Commissioning Results and Plans • H.D. Nuhn, LTU and Undulator Commissioning Plans • Richard Bionta, FEE Diagnostics and Commissioning • John Bozek, AMO Instrument
LCLS Installation and Commissioning Time-Line First Light in FEE First Light in FEH PPS Cert. LTU/Dump LTU/Und/Dump Install CD-4 (7/31/2010) X-Rays in NEH FEE/NEH Install FEH Hutch BO FEH Install PEP-II run ends Und. Seg. Install now J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A A M 2008 2009 2010 Down PPS LTU/Und Comm. Linac/BC2 Commissioning Re-commission Inj/BC2 to SL2 NEH Operations/ Commissioning FEE Comm. June 16, 2008
Readiness Reviews • FEE/NEH Beam Readiness Reviews to be held in March-April 2009 time frame • AMO Experiment Readiness Review in June-July 2009 • X-Ray Tunnel/FEH Beam Readiness Reviews to be held in November-December 2009 time frame
FEE Commissioning - Initial Conditions • Start with single undulator • 13.6 GeV electrons • 0.2 nanocoulombs • 10 Hz
FEE Instrument Commissioning5/15 to 6/25 • Conduct FEE Beam readiness review in Mar.-Apr., 2009 • Open Dump stoppers, RP initial survey (1-2 d) • Insert Direct Imager, check upstream apertures (1-2 d) • Commission adjustable slits (1-2 d) • Insert all undulators, 13.6 GeV electrons, RP survey (2-3 d) • Insert gas attenuator apertures, check alignment (1-2 d) • Commission gas attenuator/solid attenuators (1-2 d) • Center reticule on beam, project through C1 (1-2 d) • Decide if OMS realignment is necessary (+/- 1mm range) (0-5 d)
FEE Instrument Commissioning (cont.) • Commission gas detectors (2-4 d) • apertures inserted • add gas • power magnet • compare APD & PMT response to attenuation • Commission K-monochromator (4-6 d) • Transmit beam through 4 bounces (~8.172 eV) • Checkout quadrant photodiode (keep intensity low) • Measure x-ray energy, undulator bandwidth • Measure photon flux (part of CD4 goals) (1 d)
Offset Mirrors6/26 to 7/16 • Tune linac for appropriate energy • Begin with soft x-ray offset mirror system (SOMS) • Insert M1S, use P1 to set angle, translation (2-4 d) • Insert M2S, use P2S to set angle, translation (1-2 d) • Insert M3S2, use P3S2 to set angle, translation (1-2 d) • Retract M3S2 and insert M3S1, use P3S1 to set angle, translation (1-2 d) • Retract M1S and apply same procedure to HOMS (3-5 d) • Priority is SOMS for hutch 2 - delivers beam to AMO experiment
Offset Mirrors (cont.) • Open hutch stoppers to AMO experiment • RP surveys - insure full intensity through C4S2 • Begin AMO experiment alignment
SASE Optimization7/17 to 8/13 • Change linac to 4.52 GeV (nominal 908 eV), check beam center with K-mono (keep intensity low, 1-2 d) • Switch to direct imager, look for FEL (should be able to see signals ≥100 nJ) • If unable to find FEL, measure undulator K values • Change linac back to 13.56 GeV, 10 Hz • Use K-mono to measure spectrum (3-5 d) • Optimize SASE (vary bunch compression, emittance, RF, BBA, etc.) • Above 50 J, imager saturates, need gas attenuator
SASE Optimization (cont.) • If FEL reaches ~0.1-1.0 mJ, commission calorimeter (3-5 d) • Need to limit linac to 10 Hz • Once calorimeter is commissioned, cross-calibrate the gas detectors and the direct imager (2-3 d) • Measure position stability • Electron energy stability already < 0.1% (at end of linac) • During off-hours, deliver beam to AMO experiment
AMO Experiment • HF Physics chamber will be in place by May 1, 2009 • Laser will be ready at the same time • Commissioning of laser transport to AMO exp. begins • Diagnostics chamber to be in place June, 2009 • KB optics delivered in May or June, 2009 • Begin aligning KB optics, HF physics chamber, and diagnostics chamber in mid-July
Summary • Very tight schedule between first beam to FEE and User Run - driven by FY08 budget limitations. • Very tight schedule between AMO experiment installation and User Run - driven by FY08 budget limitations. • We think the goal of achieving lasing at 1.5 nm by Aug.-Sep., 2009 is reasonable • Experiments in Fall, 2009 are not part of CD 4 goals