1 / 14

ESKOM RURAL ELECTRIFICATION EXPERIENCES - LESSONS LEARNT -

ESKOM RURAL ELECTRIFICATION EXPERIENCES - LESSONS LEARNT -. Presentation to UPDEA Workshop in Durban I. Sokopo. CONTENTS. Strategic Approach Commitment From Government Social Interventions Technical Interventions Process Institutional and Funding Arrangements Public Private Partnerships

telyn
Download Presentation

ESKOM RURAL ELECTRIFICATION EXPERIENCES - LESSONS LEARNT -

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ESKOM RURAL ELECTRIFICATION EXPERIENCES - LESSONS LEARNT - Presentation to UPDEA Workshop in Durban I. Sokopo

  2. CONTENTS • Strategic Approach • Commitment From Government • Social Interventions • Technical Interventions • Process • Institutional and Funding Arrangements • Public Private Partnerships • Achievements to date • Electrification Success: Cumulative • Cost Per Connection • Way Forward • Lessons Learnt • Conclusion

  3. COMMITMENT BY GOVERNMENT • 1990-1993 Eskom performed 380 000 connections • 1994 - Target set by Government for 1,75m by year 2000. • 2001 to date - 3,3 million households electrified • Connection every 30 seconds, pole every 10 seconds, 200m cable every minute. • 1000 projects - 200 simultaneously each year.

  4. SOCIAL INTERVENTIONS • Critical to ensure success of any program • Existing structures not necessarily recognised by communities. • Electrification Committees set up • Transfer of skills crucial

  5. TECHNICAL INTERVENTIONS • Tackled in four areas. • Realistic load requirements • 3kVA - 0,4kVA • Type of supply • single or three phase • Utilisation of equipment • Poles, transformers, indicators used • Revenue management and metering • Prepayment

  6. PROCESS • Change from reactive to proactive target driven approach • Process had to be put in place • Lead time of 18 months • Centrally controlled. • Rolling plan reviewed every three months • very dynamic environment.

  7. INSTITUTIONAL AND FUNDING ARRANGEMENTS • UP TO 2000 • Funded by Eskom, flexibility, ability to meet targets, up front planning • 2000 TO PRESENT • Funded By Government • Stringent processes to follow • No certainty on future cash availability • Situation is improving • Numbers have dropped [Energy White Paper] • FUTURE – CONFIDENT OF LIAISON WITH GOVERNMENT TO ENSURE DELIVERY

  8. PUBLIC PRIVATE PARTNERSHIPS • USED FOR NON – GRID PV SYSTEMS • EXPENSIVE TO CUSTOMER • R100 connection fee compared to R0 • R60 per month compared to usage • R9/kWh compared to R0.5/kWh • ELECTRIFICATION NOT PROFITABLE EVEN WITH LIMITED SUBSIDIES

  9. ACHIEVEMENT TO DATE • By end 1999 Eskom electrified 1,750,750 households - bulk in rural areas. • 12% in 1994 to 46% at end 1999. • Achieved cost per connection reduction by over 50% in real terms. • Approximately 6000 PV systems • 8 500 schools and clinics

  10. ELECTRIFICATION SUCCESS CUMULATIVE CONNECTIONS

  11. WAY FORWARD

  12. LESSONS LEARNT • Need Vision From Government • Need Supply Chain • Up front planning • Pre – engineering • Funding for 132 kV networks • Need Technology, Standards, Process • Public Private Partnerships have limited success due to profit requirement

  13. CONCLUSION • Need to always learn from mistakes • Need to have strict control from a Central office with a clearly defined target and process • Sound Stakeholder management throughout the process

More Related