Pradhan Mantri Gram Sadak Yojana Review Meeting (Himachal Pradesh, Haryana, Jammu & Kashmir, Punjab and Uttarakhand) at IAHE, Noida On 29th & 30th October, 2015
Compliance Parameters of Last Review Meeting held at Delhi(27.2.2015)
Action Taken by the States All participating States during their last RRM has assured for the following:- • Reconciliation of Habitation data and uploaded on OMMAS by 31st March 2015 – All participating States. • Completion of remaining 34 road works sanctioned upto 2005-06 by end June, 2015 – Himachal Pradesh. • Settle 1 pending final bill (sanctioned 2006-07) by 10th March, 2015 (Haryana). • Jammu & Kashmir and Uttarakhand would settle all pending final bills by 31st March, 2015. • Update all details of New Technologies used on the new formats on OMMAS- All participating States. • Haryana, Jammu & Kashmir and Uttarakhand submit actual figures of road length and no. of Trees planted under Tree Plantation. • States to submit plan for pending ATRs addressed during Dec. 14 and Feb. 15 to NRRDA – All participating States.
Haryana Compliance Parameters of Last Review Meeting(27 Feb. 2015)
Himachal Pradesh Compliance Parameters of Last Review Meeting(27 Feb. 2015)
Jammu & Kashmir Compliance Parameters of Last Review Meeting(27 Feb. 2015)
Punjab Compliance Parameters of Last Review Meeting(27 Feb. 2015)
Uttarakhand Compliance Parameters of Last Review Meeting(27 Feb. 2015)
HaryanaTrends of Physical Completion of Roads in km 495 road works i/c Bridges completed out of 520 (97% length completed )
Haryana Physical Progress as per OMMAS
HaryanaTrends of Financial Progress(Release / Expenditure in Rs. Crore) 2012-13 & 2013-14 : No funds released.
Himachal PradeshTrends of Physical Completion of Roads in km 1,887 road works i/c Bridges completed out of 2388 (81% length completed)
Himachal Pradesh Physical Progress as per OMMAS- Normal 182 in-complete road works till 2010-11 is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
Himachal Pradesh Physical Progress as per OMMAS- RRP-I RRP-II 111 in-complete road works till 2010-11 is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
Himachal PradeshTrends of Financial Progress(Release / Expenditure in Rs. Crore) 2012-13 & 2013-14 : No funds released.
Jammu & KashmirTrends of Physical Completion of Roads in km 1,226 road works i/c Bridges completed out of 1,984 (63% length completed)
Jammu & Kashmir Physical Progress as per OMMAS 361 in-complete road works till 2010-11 is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
Jammu & KashmirTrends of Financial Progress(Release / Expenditure in Rs. Crore)
PunjabTrends of Physical Completion of Roads in km 939 road works i/c Bridges completed out of 1,044 (96% length completed)
Punjab Physical Progress as per OMMAS- Normal
Punjab Physical Progress as per OMMAS- RRP-II
PunjabTrends of Financial Progress(Release / Expenditure in Rs. Crore)
Uttarakhand Physical Progress as per OMMAS- Normal 105 in-complete road works till 2010-11 is a cause of concern, State should focus on expediting the process of completion of these in-complete road works as well as their financial closure
Uttarakhand Physical Progress as per OMMAS- RRP-II
UttarakhandTrends of Financial Progress(Release / Expenditure in Rs. Crore) 2013-14 : No funds released.
1.Details of R&D being presented in the next slides are as per records of NRRDA. However, these details have not been updated by the States on OMMAS. The length and cost of new technology portion is to be updated by the State, which has not been done in most of the cases or incorrect information updated.2. Photographs, performance reports etc. are also to be uploaded for such works. In most of the cases photographs and performance reports are not being uploaded by the States. Details of Road works Sanctioned as New Technology (R&D) Projects under PMGSY
Haryana (Rs. In Crore)
Himachal Pradesh (Rs. In Crore)
Jammu & Kashmir (Rs. In Crore)
Punjab Maintenance - Financial
Uttarakhand Maintenance - Financial
Unconnected Habitations Data Haryana
Unconnected Habitations Data Himachal Pradesh
Unconnected Habitations Data Jammu & Kashmir
Punjab Unconnected Habitations Data All eligible habitations sanctioned. To be corrected to 441 How to 250+ habitations are eligible in Punjab
Uttarakhand Unconnected Habitations Data
Eligible Habitations, Habitations Cleared and Connected (Since commencement – September, 2015) Based on MPRs
Eligible Habitations, Habitations Cleared and Connected (Since commencement – September, 2015) Based on MPRs
Updating of Data on OMMAS • States are requested to update their data on OMMAS particularly relating to habitations, DRRP, Core Network, Year wise sanctioned proposals, R&D, Maintenance, R&P Module etc latest by 31st December, 2015. • All physical reports will be dispensed with and all reports will be taken from OMMAS directly. • States will have to update their progress latest by 10th of next month on which all these reports will be taken from OMMAS.
Details of Awarded Works • In many cases data of awarded works entered by the PIUs does not appear to be realistic as it is more than 100% of the GoI sanctioned cost. • Also in some cases the data entered is in Rupees, where as it should have been in Rs. In lakhs. This has been corrected from backend by NRRDA, however, the States need to verify and confirm that the data appearing on OMMAS is correct latest by 15th November, 2015. • In many cases the data of award has not been updated on OMMAS. A check is being applied on OMMAS, so that details of award will have to be entered within 10 days from date of award
Officers trained under various Training Programmes during 2015-16(Upto September, 2015)
Quality Mechanism Haryana Himachal Pradesh Jammu & Kashmir Punjab Uttarakhand
1st tier Inspections accounted from Apr.,2015 to Oct.,2015. • Based on NQM inspection • Haryana has 0% deficiency in quality management as per NQM observations
1st tier Status of Field Lab • Consideration period starting from FY which involves at least one On going Works.
2ND tier Sqm inspection summary * No. of SQMs who have uploaded Inspections in OMMAS during FY 2015-16.