An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. B.O.S.S.SPS ring and transfer lines Serge Massot for BE-OP-SPS European Organisation for Nuclear ResearchCERN CH-1211Genève 23Switzerland CERN BE-OP-SPS

  2. Highlights • SPS layout • Beam instrumentation : • Injection Line TT10 • SPS Ring • All LSS • Transfer lines • TT20 to North Area • TT40 and TT60 • TT41 • TT66 • Ti2 and Ti8 • Summary CERN BE-OP-SPS

  3. SPS layout CERN BE-OP-SPS

  4. Injection line TT10 • BPCL: • 14 devices • Beamsteering/ Injection oscillation correction • Critical for machine operation • BCT: • TT10.BCTFI.102834 and TT2.BCTFI.212 (in CPS side but used by SPS-OP) • Beam structure / Bunch distribution / Gap •  Critical for machine operation • SEM (OUTIN) • 9 BSP - 3 BSG - 1 BSTK • Energymatching / Emittancecheck / Beam position •  Critical for machine performance • BTV: • 3(+1 in TT2) • Beam position / Beamshape / Transverse blow up •  Critical for machine set-up • No BLM CERN BE-OP-SPS

  5. SPS Ring • BPM: • 104 BPH • 93 BPV • Beamsteering • Critical for machine operation • BLM: • 216 devices (36 per arc) • Losses check / Machine protection •  Critical for machine operation • BCT: • BCTFS.60903 • Synchronisation for extraction kickers •  Critical for machine operation • BTV: • BTV.21003 and BTV.61003 • Beam position / Used in case of difficultstart up •  Critical for machine set-up • BBSR: • BBSR.21001 and BBSR.61001 • No device (Empty tank); To bereplaced by a vacuum chamber CERN BE-OP-SPS

  6. BBSR21001 and BTV21003: SPS Ring BBSR.21001 BBSR.21001 + BTV21001 • Also the case for BBSR61001 and BTV61003 CERN BE-OP-SPS

  7. LSS1 • BPM: • 2 BPD - 2 BPCN - 1 BPVC • Beamsteering • Injection oscillation correction • Critical for machine operation • BLM: • 12 devices • Losses check •  Critical for machine operation • BCT: • BCTFS.11640 • Synchronisation for injection kickers •  Critical for machine operation • BTV: • 4 devices (2 of which have a screen on a stepper motor) • Injection setting up •  Critical for machine set-up SPS Ring BSGV.11793 in front of TIDH (Dump) damaged. Replacement ongoing. BPSH.12174, BPSV.12179 (Schottky, RF Group) BCTDC.11601 (obsolete, to be removed) CERN BE-OP-SPS

  8. LSS2 • BPM: • 2 BPCR • 3 BPCN • 1 BPVC • Damper and feedback • Tune measurement BBQ • Critical for machine performance • BLM: • 15 devices • Losses check • Machine protection • North extraction surveillance (ZS, MSE, MST) •  Critical for machine operation • Stepper motor: • 13 BBS and 2 BSG • Extraction setting up to North Area •  Critical for machine set-up SPS Ring CERN BE-OP-SPS

  9. LSS3 • BPM: • 1 BPNB • 2 BPCN • 1 BPCR • 1 BPVT • Beamsteering •  Critical for machine operation • Chromaticitymeasurement (BPCR) •  Critical for machine performance • BCT: • BCTDC.31832 • Page-1 highintensity • Economy mode •  Critical for machine operation • BCTFR.31450 • Bunch distribution  Beamquality check •  Critical for machine performance SPS Ring CERN BE-OP-SPS

  10. LSS4 • BPM: • 3 BPCE - 1 BPCL – 1 BPL - 1 BPLT - 1 BPMBV • Beamsteering • Extraction setting up to TT40 • Critical for machine operation • BLM: • 7 devices • Losses check • Machine protection • Critical for machine operation • BCT: • BCTDC.41435 • Page-1 lowintensity • Economy mode • BCTFS.41438 • Synchronisation for extraction kickers •  Critical for machine operation SPS Ring CERN BE-OP-SPS

  11. BWS: • 2 Rotational (1 only V plane) and theirfilters (Stepper motor) • Emittancemeasurement • Aperture measurement • Cross check wirescan in LSS5 •  Critical for machine performance (especially for LHC beam) • BTV: • 2 BTVE (Screen on a stepper motor) • 1 BTV • Extraction setting up •  Critical for machine set-up LSS4 (SPS Ring) CERN BE-OP-SPS

  12. LSS5 • BPM: • 2 BPMBH – 4 BPMBV • Beamsteering • Monitoring for experiments • Critical for machine operation • BLM: • 4 devices: • Losses check for experiment (UA9) • Critical for machine operation • BCT: • BCTDC108.51895 and BCTDC108.51897 • Measurement of highintensity for primary ion beam interlock •  Critical for personalprotection • BWS: • 1 Rotational / 2 Linear and theirfilters (Stepper motor) • Emittancemeasurement • Aperture measurement • Cross check wirescan in LSS4 •  Critical for machine performance (especially for LHC beam) SPS Ring CERN BE-OP-SPS

  13. BTV + BMO (Stepper motor): • 1 device • Screenmatching (Injection energymatching) •  Critical for machine performance • BBLR: • 4 devices • Beambeam long range •  Development instrument • BIPM: • 1 BIPMH – 1 BIPMV • Profile by residualgas ionisation •  Development instrument • BRS: • 2 devices • Synchrotron light •  Development instrument LSS5 (SPS Ring) CERN BE-OP-SPS

  14. LSS6 • BPM: • 3 BPCE – 2 BPCN • Beamsteering • Extraction to TT60 • Critical for machine operation • BLM: • 13 devices • Losses check • Machine protection • Critical for machine operation • BTV: • 4 BTVE (Screen on a stepper motor) • Extraction setting up •  Critical for machine set-up SPS Ring CERN BE-OP-SPS

  15. Transfer lines • TT20 to North Area • BLM: • 20 devices • Transfer losses / losses atsplitting / Machine protection • Critical for machine operation • SEM (OUTIN): • 19 BSP – 11 BSG – 6 BSI • Beamsteering / Intensitymeasurement • Critical for machine operation • Stepper motor: • 34 BBS (Mini scanner) – 2 BSI – 6 BSM – 2 BSG – 2 BTV screens • Setting up to North Area •  Critical for machine set-up • BTV: • 10 devices • Setting up to North Area •  Critical for machine set-up CERN BE-OP-SPS

  16. TT40 and TT60 • BPM: • 4 BPKG in TT40 – 5 BPCK in TT60 • Beamsteering • Critical for machine operation • BLM: • 6 devices in TT40 – 8 devices in TT60 • Losses check • Machine protection • Critical for machine operation • BCT: • 1 BCTFI in each line • Beampresence • Injection Quality Check •  Critical for machine operation • BTV: • 3 devices in each line • Beamtransfer setting up • Screenmatching •  Critical for machine set-up Transfer lines TT41: CNGS over. Configuration to be discussed for AWAKE CERN BE-OP-SPS

  17. TT66 • BPM: • 6 devices – 1 BPKG • Beamsteering • Critical for machine operation • BLM: • 12 devices • Losses check • Machine protection • Critical for machine operation • BCT: • 1 BCTFI • Beampresence • Beamquality check •  Critical for machine operation Transfer lines CERN BE-OP-SPS

  18. Ti2 and Ti8 • BPMI: • 53 devices in Ti2 - 47 devices in Ti8 • Beamsteering • Critical for machine operation • BLMI: • 39 devices in Ti2 - 32 devices in Ti8 • Losses check • Machine protection • Critical for machine operation • BCT: • 1 BCTFI in each line • Beampresence • Injection Quality Check •  Critical for machine operation • BTVI: • 9 devices in each line • Beamtransfer setting up • Screenmatching •  Critical for machine set-up Transfer lines CERN BE-OP-SPS

  19. Summary • Critical for machine operation: • Almost all BPMs • All BLMs • Almost all BCTs • All SEMs (OUTIN) in TT20  Beamsteeringeveryday • Critical for machine performance: • BPMs for tune and chromaticitymeasurement • BCTFR.31450 • All SEM (OUTIN) in TT10 • Wirescanners • BTVs for screenmatching • Critical for machine set-up: • BTVs for extraction setting up • Mini scanners • Development instrument: • BBLR • BIPM • BRS • To beremoved: • BCTDC.11601 • BBSR.21001 and BBSR.61001 (Tank) CERN BE-OP-SPS

  20. Acknowledgment • I wouldlike to thank L. Jensen and K. Cornelis for theiruseful guidance CERN BE-OP-SPS

  21. Thankyouverymuch for your attention CERN BE-OP-SPS