1 / 28

Status Update: Using NMMS for Building SSWG Cases

Status Update: Using NMMS for Building SSWG Cases. Wes Woitt CenterPoint Energy 2010 SSWG Chair. Current Process. TSP Data PSSE IDEV. TSP Data PSSE RAW format. Yes. Posted to ERCOT Website. No. ERCOT Using PSSE. Compile Data and Solve. Output PSSE Cases. Case need tuning?.

thao
Download Presentation

Status Update: Using NMMS for Building SSWG Cases

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status Update: Using NMMS for Building SSWG Cases Wes Woitt CenterPoint Energy 2010 SSWG Chair

  2. Current Process TSP Data PSSE IDEV TSP Data PSSE RAW format Yes Posted to ERCOT Website No ERCOT Using PSSE Compile Data and Solve Output PSSE Cases Case need tuning? Ready for use in planning studies ERCOT Determines Dispatch Using UPLAN • TSP Data • Some have internal databases to compile data • Others take previous case and add projects or corrections as necessary • Incumbent upon each TSP to coordinate and track what is contained in data sent to ERCOT

  3. NMMS Process MOD TSP Data PMCR TSP Data PSSE RAW format Yes No Posted to ERCOT Website ERCOT Using PSSE Compile Data and Solve Output PSSE Cases Case need tuning? Ready for use in planning studies PSSE ERCOT Determines Dispatch Using UPLAN Topology from NMMS Topology Processor RAW file to MOD TSPs Provide Loads and Device Control Profiles RAW file to MOD TSPs Provide Future Projects PMCR

  4. Topology Processor Functionality • Topology Processor (TP) • Converts Operations formatto Planning format (RAW) files • MOD produces (.PRJ Project) • Converts “Bus/breaker” to “Bus/branch” model • Case Builder (CB) • Builds time-based models 4

  5. What’s been done so far? • IMM work • ERCOT prepopulated much of the planning related data in 2009 • TSPs cleaned up over 1000 incorrect Connectivity Node Groups (CNGs) • Moved incorrect Connectivity Nodes into the correct CNGs • Worked with ERCOT to correct CNGs and nodes where TSPs did not have ownership • TSPs cleaned up planning related data (Area #s, Zone #s, ckt IDs, etc.) • Submitted SCR 759 • Worked with ERCOT to modify TP • MOD training in July • Currently testing new build process using Topology Processor (TP) and MOD • Identified issues with TP/IMM

  6. IMM/TP output PSSE v30TSP Combined Issues List #50 • TP is already dated • SSWG moved to PSSE v31 in May 2009 • New data types and parameters • PSSE generally puts out a new version annually • For TP to be able to include new data types or new parameters, IMM will need to be changed not just TP

  7. No Distribution Cap Banks in TP CaseTSP Combined Issues List #38 • TSPs model distribution cap banks at transmission buses in PSSE • Allows cap banks to be switched during planning studies • IMM does not model equipment below transmission voltage • Hundreds of these cap banks in ERCOT system • Cannot solve through MOD Device Control Profile

  8. Distribution Cap banks Fall Planning Case Topology Processor Case

  9. Zero Impedance Lines Created by TP Have 9999 MVA RatingsTSP Combined Issues List #35 • TSPs model about 250 zero impedance lines which have real ratings in SSWG cases • See examples

  10. Zero Impedance Line Ratings Planning Case TP Case

  11. Zero Impedance Line Ratings Zero impedance branch 46110 – 46111 – 95 Rate A = 360 MVA Rate B = 440 MVA Rate C = 440 MVA North Belt 138 kV Non-zero impedance branch 46111 – 46002 – 95 Rate A = 455 MVA Rate B = 478 MVA Rate C = 580 MVA

  12. Associating Loads and Cap Banks with the Correct CNGTSP Combined Issues List #33 and #34 • It was somewhat of an art to assign nodes to CNGs to create model that we wanted to see • See example

  13. Bus 40002 Ckt. 01 A D To Bus 70000 Figure 1: Modeling of Cap Banks and Load Taps in IMMScenario 1 Bus 50000 B E G C F Bus 60000 Ckt. 02 Bus 40001 To Bus 80000 Bus 40000 • LEGEND • Node Switch AC Line Segment Series Compensator Breaker • With the current method of modeling, the cap bank and distribution load are associated with Bus 40000. To match the topology of our cases, the cap bank and distribution load should be associated with Buses 40001 & 40002, respectively. With the cap bank and load modeled as part of multi-section lines off of the main bus (40000), we are able to switch the lines, de-energize the cap bank, and “roll” the load to another load bus. This is impossible with the current method, because when the lines are de-energized, the cap bank and load remain on the main bus (40000). • See Figure 2 for the resulting PSSE diagram when the above (current) method of modeling is run through the Topology Processor. • See Figure 3 for the desired PSSE topology of the above substation.

  14. Figure 2: Resulting PSSE Topology Using Scenario 1 Modeling Method

  15. Bus 40002 Ckt. 01 A D To Bus 70000 Figure 4: Modeling of Cap Banks and Load Taps in IMMScenario 2 Bus 50000 B E G C F Bus 60000 Ckt. 02 Bus 40001 To Bus 80000 Bus 40000 • LEGEND • Node Switch AC Line Segment Series Compensator Breaker • With the current method of modeling, the cap bank and distribution load are associated with Bus 40000. To match the topology of our cases, the cap bank and distribution load should be associated with Buses 40001 & 40002, respectively. With the cap bank and load modeled as part of multi-section lines off of the main bus (40000), we are able to switch the lines, de-energize the cap bank, and “roll” the load to another load bus. This is impossible with the current method, because when the lines are de-energized, the cap bank and load remain on the main bus (40000). • See Figure 2 for the resulting PSSE diagram when the above (current) method of modeling is run through the Topology Processor. • See Figure 3 for the desired PSSE topology of the above substation.

  16. Figure 5: Resulting PSSE Topology Using Scenario 2 Modeling Method

  17. Figure 3: Desired PSSE Topology

  18. Autotransformer Modeling IssuesTSP Combined Issues List #41, #42, #48, and #52 • #48 and #52: • CNP reported that the TP was incorrectly calculating off-nominal 3-winding transformer impedances. • Subsequent discussion with ERCOT/Siemens leads us to believe that we are inputting incorrect Ohmic impedances into IMM – Still testing • Siemens has used this method in other regions and had the same arguments • No documentation about what we are expected to provide in IMM or what calculation TP is using • #41 • CNP Operations standardizes all autos – SCADA does adjustment automatically • PSSE does not have that same intelligence; therefore, IMM auto models must be adjusted to reflect real equipment characteristics • Some parameters can be changed in Device Control Profile, but not all • Not talking about ratings and impedances differences • #42 • Allow a phase shift to be applied to transformers and output in the case. Useful when creating cases for fault duty studies to have this already in case. • This has nothing to do with phase-shifting transformers

  19. Autotransformer Ops Model vs. Planning Model • The device control profile is not robust enough to handle the majority of differences between the Topology Processor output case and the Transmission Planning case. Instead, at least 50 3-winding transformers in CenterPoint Energy’s area will require PRJ files to alter the Topology Processor output case to a typical Transmission Planning case. • Differences Resolved with PRJ • Moving the LTC from the low winding to the high winding. • Number of taps • Specifying a different voltage control bus • The tap range of the LTC Rmax, Rmin • Differences Resolved with Device Control Profile • Winding voltage for off-nominal NLTC settings. • The auto-adjust code for LTC windings • Voltage control bus regulation values Vmax, Vmin

  20. FACTS Device ModelingTSP Combined Issues List #32 • PSSE allows modeling FACTS devices (STATCOMs, SVCs, TSCs, etc.) in a number of different ways • Generator • Switched shunt • FACTS Device • TP only outputs a FACTS device as a generator model • Important to model correctly for dynamic studies

  21. FACTS Devices Planning Case – CNP’s FACTS Device TP Case model –CNP’s FACTS Device

  22. FACTS Devices Planning Case – AEN’s FACTS Device TP case – AEN’s FACTS Device, currently on wrong bus

  23. PSSE IDs for Branches • PSSE allows any two character CKT ID for any branch • IMM has validation rules that series devices PSSE CKT IDs have to be Sx • TP automatically creates PSSE CKT ID of BC or BO for any branch that represents and breaker or switch • Would prefer to leave PSSE CKT ID open and left to the discretion of TSPs Line IDs with BO/BC ID

  24. RARF Data TSP Combined Issues List #30 • TSPs have seen lots of basic problems with RARF data • MBASE • Zsorce • Other RARF data problems • Reactive data does not correspond with biennial tests • RARFs submitted with erroneous PSSE bus numbers • ERCOT Network Modeling creates NOMCRs • Creates problems with TP output as SSWG recently discovered • Need process to allow TSP review • Even more issues with wind resource RARFs • NPRRs currently being drafted or in process

  25. Equipment Associated with SPS/RAPs Modeled in IMM TSP Combined Issues List #49 • SPS/RAP models are not real equipment • TSPs see additional data in TP output

  26. Remaining Issues TSP Combined Issues List #26, #27, #28, #29 • #26: Each of the items identified above can be fixed in SSWG base cases through ‘Standard’ PMCRs • Taken as a whole, this represents an enormous amount of corrections to make to the case • SCR being drafted to propose changes to many of these • #27: Changes described in #26 are not implemented by next spring • #28: SCR 759 is never implemented • Multi-section line creation is not functional • #29: Case building process is still very unclear • Due to these uncertainties • Just begun finding issues with MOD

  27. Remaining Issues TSP Combined Issues List #40, #48, #51, #52 • #40: Specific modeling added for contingency analysis, dynamic analysis, short circuit analysis, etc., that is lost by creating cases from IMM data • This punishes TSPs who have made a concerted effort to align their base cases to serve the needs of planning, protection, and stability studies without having to maintain separate cases. • #48: Topology Processor issues • Software is still being changed • Radial line reduction still not working properly • #51: Not all TSPs have PSSE which is creating problems with their ability to create PRJ files • Potential resolution is being discussed, but it is a workaround • #52: Lack of documentation about TP

More Related