630 likes | 813 Views
United Arab Emirates University College of Engineering Chemical Engineering Department Training and Graduation Project Units Graduation Project II. Estimation and Capturing CO 2 from Emirates Cement Factories.
E N D
United Arab Emirates University College of Engineering Chemical Engineering Department Training and Graduation Project Units Graduation Project II Estimation and Capturing CO2 from Emirates Cement Factories Project Code CHF2-4 Presenting to :Dr. Ali Al Naqbi , Dr. NayefGhasem Prof. MamdouhGhannam Department Advisor: Dr. Samir Abu-Eishah
Agenda • Acknowledgement. • Introduction. • Summary of Achievements in GPI. • Selection and discussion of final process. • Detailed equipment design. • Design Alternatives. • Details of Cost Analysis & Discussion. • Relevant Codes of Ethics and Moral Frameworks.
Agenda • Codes of Ethics. • Environmental Impact of the Process. • HAZOP (Hazard and Operability). • General loop of the process. • P&ID diagram for the process. • Problem faces and solutions. • Conclusion.
Acknowledgement • We would like to express deepest thanks and appreciation to Dr. Samir Abu-Eishah, the supervisor of the graduation project for his leadership and supervision, also would like to express our sincere appreciation to the college coordinator, Dr. Hend Al-Qamzi, for her guidance during our presentations. • We would like to thank chemical engineering professors and special thanks go to the Training and Graduation Projects Unit.
Introduction • Problem statement: • Cement industry is responsible for about 5% of the global emission of the CO2 to atmosphere. • The purpose of this project is to estimate and capture CO2 from the stacks of the Emirates Cement Factories in Al Ain. • Project and design objective: • Find the best techno-economical solution to capture CO2 from the Emirate Cement Factories.
Introduction • Outcomes and Deliverables: • The system was a physical absorption process using Selexol as a solvent to capture CO2. • The equipment were designed based on the process operating conditions. • The system control loop was identified for safety and HAZOP consideration. • HAZOP study of equipments was determined for different situations. • Cost analysis was made based on CAPCOST estimations and annual operating cost .
Summary of Achievements in GPI • The linkage system was selected to connect flue gases from Emirate Cement Factories to our process. • The flue gas was cooled and the water accompanning the flue gas was separated. • The flue gas was then compressed and cooled before entering the absorber. Figure 1: Linkage system in GPI drawn by khulood Al jaberi
Summary of achievement in GPI • Selected process in GPI: • The process selected in GPI was chemical solvent absorption using (MEA), which is the most suitable method for capturing CO2 from other gases for low CO2 concentrations. • The flue gases from ECF enter a packed absorption column. The counter current flow was used with the chemical solvent for more efficient absorption of CO2 by chemical reaction. • For energy integration ,Rich solvent from the absorber exchanges its heat with the lean solvent from the stripper through a heat exchanger. • CO2 is separated from the rich solvent in a stripper using a reboiler. • The lean solvent is recycled back to the absorber and CO2 was sent to storage
Flow sheet Figure2 :Chemical absorption with MEA solvent drawn by Elham Abdullah
Summary of achievement in GPI • Material balance: • Two sources of CO2: • Combustion of Natural gas: CO2= 15.65 (ton/hr) • Calcinations of carbonates, for example, calcium carbonate: • Amount of CO2 produced from calcinations: • From limestone 9.65 (ton/hr) • From marl stone 4.72 (ton/hr)
Summary of achievement in GPI Rotary Kiln Figure3:Material balance around the rotary kiln drawn by khulood Al jaberi
Summary of achievement in GPI • Energy balance: • Energy balance was around the E-100 which cooled the flue gases and water from 150oC to 40oC. • E-100 divided into three zones: Figure4: three phases in heat exchanger drawn by EimanSaleh
Summary of achievement in GPI • Water: • Gas:
Selection and discussion of final process • The linkage system was modified by replacing the separator by heat exchanger with boot which collects the condensed water. • Multi stage compressor with three inter cooling was added. Figure5 : Multi stage compressor flow sheet drawn by khuloodSaeed
Selection and discussion of final process • Physical absorption process was selected for this project . • The Final design consists of six coolers, one multi stage compressor, one heat exchanger, one pump, one absorber, one flash separator and one vessel. Figure 6: Process flow sheet drawn by ElhamAbdullah and EimanSaleh
Selection and discussion of final process • Process optimization: • Temperature • Pressure
Selection and discussion of final process • Liquid flow to gas flow ratio (L/G) • Number of Trays
Detailed equipment design • Pump P-100 (power required) • Compressor K-100 (power required) • Heat exchanger E-105 ( Overall heat transfer, Area) • Flash drum V-100 (diameter , height) • Absorber T-100 (diameter , height)
Pump P-100 design • The required information for calculating pump power is as follows: • Based on rules of thumb the applicable equation is:
Pump P-100 design • Centrifugal multistage pumps are usually used for the volumetric flow rate of 0.076 - 41.6 m3/min. • since the system volumetric flow rate 40.48 within the range the required efficiency is 0.75. • Required power:
Compressor K-100 design • Input for compressor power calculation: • Large centrifugal compressors are at the range of 2.83 – 47.2 m3/s. • since the system flow rate is within this range then the efficiency is 0.75.
Compressor K-100 design • Required power:
Heat exchanger E-105 design • The split ring floating head exchanger was chosen because for efficiency and ease of cleaning. Figure7: split ring floating heat exchanger Reference: http://omranenergy.com/index.php?option=com_content&view=article&id=35&Itemid=27
Heat exchanger E-105design • Step 1: Specification definitions
Heat exchanger E-105design • Step 2: Overall heat transfer coefficient and heat transfer area
Heat exchanger E-105design • Assuming overall heat transfer coefficient after different trails the U assumed to be 1600W/m2.oC, then • The procedure outlined in (book) was followed for the estimation for the final heat transfer area for the heat exchanger as shown below:
Absorber T-100 design: For absorber design two things must be found the diameter and the height of the tower. For diameter: = diameter of the tower (m) = volumetric flow rate of gases (m3/s) = velocity of gases (m/s)
Absorber T-100 design: • The velocity ( ) was calculated using: : Vapor density (kg/m3) : Liquid density (kg/m3) : Constant obtained from k was found from figure (8) and using FLV and tray spacing From heuristics for tower calculation the tray spacing is 0.5 (m)
Absorber T-100 design: Figure8: k for sieve plate (Coulson and Richardson, Chemical Engineering Design book , volume 6)
Absorber T-100 design: = 0.07 • Height calculation:
Design Alternatives • There are three alternatives for the system: • CO2 absorption process. • Regeneration of the solvent. • CO2 final product to storage.
Design Alternatives Process alternative: • Chemical Absorption. • Used for low CO2 concentration. • Two absorption columns, or more, in series are needed. • Fresh solvent for each column is needed. • Physical absorption: • Can be used for high concentration
Design Alternatives Regeneration of the solvent: • Flash drum instead of stripper. • No packing or trays. • No reflux. CO2final product to storage: • For high pressure or liquefied CO2. • Add compressor and cooler/condenser. • Store CO2.
Details of Cost Analysis &Discussion • The cost estimation is divided into capital cost and manufacturing cost. • Capital cost estimation is related directly to the operating condition and the equipment size. • Manufacturing costs depends on the fixed capital investment, cost of operating labor, cost of raw materials, cost of utilities and cost of waste treatment.
Details of Cost Analysis and Discussion • Cooling water utility:
Details of Cost Analysis and Discussion • Compressor power requirement:
Details of Cost Analysis and Discussion • Selexol cost: • Selexol cost is equal to 1.32 $/lb, • total amount required = 5,494,000 lb/year.
Details of Cost Analysis and Discussion • Labor cost:
Details of Cost Analysis and Discussion Profit Calculation