1 / 18

Preliminary Studies of the Electric Power Distribution for CLIC

CLIC Meeting May 2009. Preliminary Studies of the Electric Power Distribution for CLIC. Cezary JACH (EN/EL). CLIC Meeting May 2009. Technical Studies for the Electric Power Distribution for CLIC. Power balance Layout Variants of the power distribution system Next steps.

Download Presentation

Preliminary Studies of the Electric Power Distribution for CLIC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CLIC Meeting May 2009 Preliminary Studies of the Electric Power Distribution for CLIC Cezary JACH (EN/EL)

  2. CLIC Meeting May 2009 Technical Studies for the Electric Power Distribution for CLIC • Power balance • Layout • Variants of the power distribution system • Next steps

  3. 3 TeV Power Requirements

  4. Power Requirements • Total consumption of active power = 415 MW • Assuming an average power factor of 0.85, the apparent power will be approximately 500 MVA • 80% (400 MVA) of the load located near central complex (CERN Prevessin, new substation) • 20% (100 MVA) of the load located outside central complex (remote substations)

  5. Drive Beam Generation Complex drive beam accelerator 2.37 GeV, 1.0 GHz drive beam accelerator 2.37 GeV, 1.0 GHz 1 km 1 km 48 km CLIC overall layout 3 TeV Main Beam Generation Complex e- injector 2.4 GeV e+ injector, 2.4 GeV Layout (1)

  6. Layout (2) M S R S R S R S R S R S R S R S R S R S R S 4.9 km 4.9 km 8.7 km 48 km MS = Master Substation RS = Remote Substation

  7. Variant 1 – 400/18 kV Main Substation, 18 kV Remote Substations, 18 kV Distribution – 18 kV Utility Voltage 400 kV RTE European Network 400 kV station Bois Tollot CLIC 400 kV 6x 400/18 kV, 100 MVA CERN, existing installations 18 kV loop New installations for CLIC

  8. Variant 1a – 400/66/18 kV Main Substation, 66/18 kV Remote Substations, 66 kV distribution, 18 kV Utility Voltage 400 kV RTE European Network 400 kV station Bois Tollot CLIC 400 kV 5x400/18 kV, 100 MVA 2x400/66 kV, 100 MVA 10x66/18 kV, 20 MVA CERN, existing installations 66 kV loop New installations for CLIC

  9. Variant 2 – 400/66/18 kV Main Substation, 66/18 kV Remote Substations, 66 kV Distribution, 18 kV Utility Voltage 400 kV RTE European Network 400 kV station Bois Tollot CLIC 400 kV 6x400/66 kV, 100 MVA 5x66/18 kV, 100 MVA 10x66/18 kV, 20 MVA 66 kV CERN, existing installations 66 kV loop New installations for CLIC

  10. Variant 2a – 400/66/18 kV Main Substation, 66/18 kV Remote Substations, 18 kV Distribution, 18 kV Utility Voltage 400 kV RTE European Network 400 kV station Bois Tollot CLIC 400 kV 6x400/66 kV, 100 MVA 5x66/18 kV, 100 MVA 2x66/18 kV, 100 MVA 66 kV CERN, existing installations 66 kV New installations for CLIC 18 kV loops

  11. Variant 3 – 400/36 kV Main Substation, 36 kV Remote Substations, 36 kV Distribution, 36 kV Utility Voltage 400 kV RTE European Network 400 kV station Bois Tollot CLIC 400 kV 6x400/36 kV, 100 MVA CERN, existing installations 36 kV loop New installations for CLIC

  12. Summary (Substations)

  13. CLIC 400 kV / 36 kV Main Substation 400 kV Grid, Scc = 13 000 MVA 100 MVA 400 kV/36 kV Remote loads Remote loads Local loads Local loads

  14. CLIC 36 kV Remote Substation(Shaft Area) Machine Network Service Network 36 kV Busbar 400 V x V 400 V x V Surface Underground (Alcove) 400 V (Alcove) 400 V Tunnel

  15. CLIC 36 kV Double Loop (End Section) Machine Network Service Network

  16. Major Cost Drivers • Power requirements • Connection to 400 kV Grid via new transmission line? • Centrally located main substation (distribution voltages, number of transformers, switchgear, protection, monitoring, etc.) • Remote substations (transformers, switchgear and 400 V panel-boards) • Cables in the tunnel (?) using loop configuration • Transformers (?), panel-boards in tunnel • Emergency generators, cabling, transformers, etc. associated with safety system

  17. What’s Next? • Preliminary design (chronologically) • Loads (voltage, apparent power, power factor, harmonics, locations, etc.) • Network topology (choice of variants, machine and service networks, redundancy, safety networks, underground facilities, etc.) • Main substation preliminary design • Remote substations preliminary design • System simulations • Cost estimate

  18. What’s Next? • June 2010 • Preliminary Design Report • Cost Estimate • Available Resources - discussion

More Related