An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Emergency Engine Emissions Standards Kathi Harris, HOLT CAT Emissions Business Manager - June 13, 2012

  2. The information presented is an interpretation of federal, state or local regulations and should not be used as legal guidance. HOLT Power Systems assumes no liability for errors or omissions.

  3. Today’s Agenda Is this an Actual Emergency? Emissions Standards Now What?

  4. Emergency?

  5. EPA Emergency Engine Regs – Current vs. Proposed

  6. Proposed Demand Response Changes Up to 100 hours per year for non-emergency activities Hours include Demand Response, Maint. & Testing, Peak Shaving Hours Can Get Paid – Peak Shaving up to 50 hrs/year • TCEQ requires PBR 106.512 or Case-By-Case Permit Fed Regs Aligned (NESHAP & NSPS)

  7. Demand Response When: Regional Transmission Authority or equivalent balancing authority declares Energy Emergency Alert Level 2 (EEA Level 2) Voltage sag of 5% or more below standard voltage or frequency. Peak Shaving When: Done as part of program with local distribution system operators. Power can only be used at facility or towards the local system. Expires April 16, 2017 Proposed Changes - Details, Details

  8. Texas Requirements • Permits By Rule (PBR) • 106.511 (Portable & Emergency Engines & Turbines) • 106.263 (Maintenance, Startup & Shutdown) • 106.512 (Stationary Engines & Turbines; Peak Shaving) • Case-by-case (Peak Shaving) • PBR 106.511 = 876 hours emergency use • Paperwork • 106.511 – review, keep copies, records of compliance, no fee or registration. • 106.263 – same as above if MSS project less than 180 days. http://www.tceq.texas.gov/permitting/air/nav/numerical_index.html

  9. DFW Minor Source NOx Rule All federal and state regulations plus: • No Maintenance & Testing 6 am – noon, with few exceptions • Old Diesels Relocated into DFW must meet at least emergency engine emissions standards • Natural Gas-fired = 0.5 g/bhp-hr NOx, 0.6 for landfill gas

  10. Federal Requirements

  11. New Regulations - NESHAP 40 CFR 63, Subpart ZZZZ Compliance Dates: • CI: 5/3/2013 • SI: 10/19/2013 Requirements: • Maintenance specified • Minimize idle and startup – 30 minutes • Record-keeping - 5 yrs.

  12. New Regulations Maintenance Change oil, filter every 500 hrs. or annually. • Option to use oil analysis program to extend. Inspect air cleaner every 1,000 hrs. or annually. Inspect hoses, belts every 500 hrs. or annually, replace as needed. Records: • malfunctions & reducing emissions during, performance tests, maintenance, monitoring results, hours ops., emergency notifications, demand response, peak shaving, non-emergency uses.

  13. Close, but no cigar! EPA taking public comments until July 23, 2012 http://www.epa.gov/ttn/atw/rice/ricepg.html Webinars – 6/20, 6/25, 6/28

  14. Contacts Your HOLT CAT Salesperson HOLT CAT IRVING • 972-721-2000 TCEQ Air Permits Division • 512-239-1250