Risk-Based Hurricane Recovery of Highway Signs, Signals and Lights

Risk-Based Hurricane Recovery of Highway Signs, Signals and Lights. presented to Virginia Department of Emergency Management by the Center for Risk Management of Engineering Systems October 6, 2000. Project Team. Virginia Department of Transportation Travis Bridewell Lynwood Butner

Download Presentation

Risk-Based Hurricane Recovery of Highway Signs, Signals and Lights

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Risk-Based Hurricane Recovery of Highway Signs, Signals and Lights presented to Virginia Department of Emergency Management by the Center for Risk Management of Engineering Systems October 6, 2000

  2. Project Team Virginia Department of Transportation Travis Bridewell Lynwood Butner Mac Clarke Perry Cogburn Jon DuFresne Stephany Hanshaw Steve Mondul Gerald Venable Virginia Transportation Research Council Wayne Ferguson

  3. Project Team (cont.) Students Ryan Finseth Clare Patterson TJ Zitkevitz Linn Koo Richie Moutoux Advisors Professor James H. Lambert Professor Yacov Y. Haimes

  4. Overview of Presentation • Introduction • Overview of Project and Goals • Retrofitting and Upgrading Options • Spares and Reserves Options • Priority Setting • Recommendations

  5. Motivation • Why a Recovery Plan is Needed • Restore mobility and save lives • Solicit aid from FEMA and FHWA • Estimate $30-60 billion if categ.4 hit Hampton Rds, Richmond, and NoVa (Source: 97 Post Hurricane Recovery Workshop, Insurance Institute) • Current Plan • Allows inventory only for routine damage • Absent rationale for recovery priorities

  6. Saffir-Simpson Hurricane Categories

  7. Hurricane Andrew Impacts Dade County, FL • Replaced 2,000 signal heads at 400 intersections • Replaced signs • 7 Overhead structure signs • 45 Multipost ground mounted signs • 169 Single post ground mounted signs • 5 Span-wire attached signs • Compared with ‘Groundhog Storms’ (1998) • 40 Signal heads • No damage to signs reported • Storage of these items is associated with scheduled maintenance or upgrades to the system Source: Fr. Adofo Fassrainer, FDOT-D6 OPERATIONS

  8. Hurricane Floyd • Hurricane Floyd hit Suffolk District in mid-September, causing significant flood damage • 56 deaths made Floyd the deadliest US hurricane since Agnes in 1972 • Roads did not receive much wind damage, but flooding closed many roads in Virginia

  9. Hurricane Floyd Damage

  10. Suffolk District • Interstates 64, 264, 464, 564, and 664 • US Routes 13, 17, 58, 60, 258, 460 • State Routes 44, 164, and 168

  11. Project Objective The goal of the effort is to aid the Virginia Department of Transportation (VDOT) in planning and management for the hurricane recovery of highway signs, lights, and signals through assessment of the risks, costs, and benefits of alternatives.

  12. Project Structure

  13. Equipment Upgrade

  14. Wind Speed Assumptions • Not all equipment experience maximum sustained wind speed • Most equipment experience less than maximum sustained wind speed • Few equipment experience wind speeds greater than max sustained wind speed

  15. Distributions of Damage

  16. Three Upgrade Levels

  17. Upgrading Costs* *communicated with Vince Roney, Suffolk District

  18. Upgrading Trade-off Analysis

  19. Upgrading Cost Trade-off

  20. Spares and Reserves Options

  21. Spares and Reserves • Motivation • Currently VDOT and others prepare for low level damage • New spares and reserves leads to faster, cheaper post-hurricane recovery • Objective • Assess the costs and benefits of inventory options

  22. Spares Options • Options in terms of % of damageable equipment currently installed on roadways

  23. Spares Cost Analysis • Pre Hurricane Costs • Cost to increase current level • Annualized cost under low demand • Yearly storage cost • Post Hurricane Costs • Affected by hurricane severity • Costs under moderate and high demand

  24. I (low damage, mod demand) $ Option 1 II (moderate damage, mod demand) $ Option 2 III (extensive damage, mod demand) $ IV (extreme damage, high demand) $ Option 3 V (catastrophic damage, high demand) $ Post Hurricane Costs

  25. Spares Cost Assumptions • Signs will be produced in-house unless under extreme demand (Paul Balderson) • Sign shops provide signs at cost • All other equipment will be purchased from contractors • Shops not equipped to produce cantilevers, signals, and lights • Cost of purchasing equipment increases by 2-3 times under heightened demand

  26. Obtained Inventory Data

  27. Option 3 Option 2 Option 1 Status Quo Investment in Spares vs. Post Hurricane Cost (Ground Signs)

  28. Time to Recovery under Spares Options • Reduction of Time to Recovery • Spares and reserves • Reduction in manufacture and delivery time • Immediate replacement of equipment • Data used in calculation • Manufacture and delivery time • Installation time

  29. Investment in Spares vs. Time to Recovery (Ground Signs) Option3 Option2 Option1 Status Quo

  30. Priority Setting

  31. Features of Priority Setting • Importance of roads and intersections based on critical facilities and condition of road network • Restoring or replacing damaged equipment • Critical facilities are those necessary for a community’s well-being

  32. Classification of Critical Facilities

  33. Critical Facilities

  34. Geographic Information Systems • Build on an existing GIS database of VDOT roads • Network model in Arcview to create prioritization tool • Using Arcview’s Network Analyst for optimization

  35. Electronic Road Map • Two sources for electronic road maps • VDOT’s “Network Level Basemap” • Used to establish road system from which network model will be created • Census maps obtained from UVA Library • Used for geocoding addresses

  36. Suffolk District Eastern Shore Williamsburg Hampton Roads Emporia Example of Arcview Map

  37. Facility Data • Working with the Hampton Roads Planning District Commission to get data on locations of critical facilities • HRPDC’s databases are much more complete and accurate than any data collection we can do • Data acquisition and formatting is ongoing

  38. Norfolk Facility Data

  39. Phases of Preparedness …. …. ….

  40. From Map to Network Model • The Arcview maps need translation to a mathematical model • Data consists of intersections, road segments, and various classes of critical facilities • Mathematical model is in terms of nodes, arcs, and levels of supply and demand

  41. Optimization of Recovery

  42. Recommendations Consider three remedies: 1) Upgrading equipment 2) Increasing spares and reserves 3) Priority setting of roads for recovery

  43. Sample of Recommendations • Upgrading overhead (two pole span) signs on critical routes (10% of installed base = 35 signs ) • Assume pay 3.3% of total cost annually • Replacement cost per sign = $75,000 * Over 30 years

  44. Sample of Recommendations (cont.) • Spares for ground signs in Suffolk District • Assume pay 5% of total cost annually (12,000 installed) * Over 20 years

  45. Recommendations (cont.) • Notice the problem: Hurricanes can cause region-wide damage to traffic equipment • Consider short (days or weeks), medium (months), and long-term (years) aspects of recovery • Short-- Hospitals, Medium-- Schools, Long-- All • Evaluate different upgrading or spares policies by assessing the cost before a hurricane strikes and the damage, cost, and recovery time after a hurricane

  46. Recommendations (cont.) • Adapt spares and reserves to hurricane-center and other seasonal forecasts • Perform impact analysis using the various storm categories • Adopt the models for estimating the costs and effectiveness of upgrading and spares policies • Consider upgrading only routes critical to a community’s well-being in a hurricane

  47. Recommendations (cont.) • Consider critical facilities throughout the road network in setting priorities for recovery • Consider the following facilities as critical: emergency, education, government, military, operations, commerce, communications, and transportation. • Maintain a web site for support of recovery of signs, signals, and lights.