1 / 7

2015 BOND PROJECTS

2015 BOND PROJECTS. WEST ADA SCHOOL DISTRICT BOARD OF TRUSTEES UPDATE JUNE 28, 2016. VICTORY MIDDLE SCHOOL. Estimated cost - $30 million CM – Beniton Architect – LCA Completion – August 22, 2016

titus
Download Presentation

2015 BOND PROJECTS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2015 BOND PROJECTS WEST ADA SCHOOL DISTRICT BOARD OF TRUSTEES UPDATE JUNE 28, 2016

  2. VICTORY MIDDLE SCHOOL Estimated cost - $30 million CM – Beniton Architect – LCA Completion – August 22, 2016 Status – Punch list of classroom wings this week, expect to begin moving in furniture next week Projected cost – $27,327,836 Prelim Architect Fees - $713,343 (Plant) Adjusted 2015 Bond cost - $26,614,493 Remaining contingency - $728,131

  3. HILLSDALE ELEMENTARY Estimated cost - $10 million CM – Russell Architect – Hummel Completion – August 22, 2016 Status – Substantial completion July 30, begin moving furniture into building the first week in August Projected cost – $14,705,379 Remaining contingency - $145,395

  4. MERIDIAN HIGH SCHOOL Estimated cost - $24 million CM – CM Company Architect – Hummel Estimated completion – October 2017 Status – Punch list of Phase 3B this week, Phase 5 completed March 2017, Phase 4 demo has begun, Phase 6 demo begins March 2017 Projected cost - $20,637,382 Remaining contingency - $1,269,339

  5. STAR MIDDLE SCHOOL Estimated cost - $30 million CM – ESI Architect – LCA Estimated completion – November 2017 Projected cost – $29,908,218 Remaining contingency - $1,000,000

  6. FUTURE HIGH SCHOOL SITE ACQUISITION $2,000,000 West of Ten Mile Road between Chinden and I-84 50-55 acres minimum

  7. 2015 BOND SUMMARY • 2015 Bond - $96,000,000 • Projected cost of all projects - $93,879,002 • Interest earned to date on 2015 bond - $435,000 • Unencumbered contingency - $3,142,865 • Unencumbered bond revenue - $5,698,863 • 96,000,000 – 93,879,002 = 2,120,998 + 435,000 + 3,142,865 = $5,698,863

More Related