PSSRA Work Package Overview. “The Mighty War Ship” USS JOHN C. STENNIS (CVN 74) FY13 DPIA. What’s the Message?. NW Contractors supporting the war-fighter and Naval SY. Opportunity - good sized work package for prime contractor, sub-contractor and vendor partners.
E N D
PSSRA Work Package Overview “The Mighty War Ship” USS JOHN C. STENNIS (CVN 74) FY13 DPIA
What’s the Message? • NW Contractors supporting the war-fighter and Naval SY. • Opportunity - good sized work package for prime contractor, sub-contractor and vendor partners. • Contractor Work Force engaged. • Opportunity for another Private Sector “Win”!
Terminology • MSMO- Multi-Ship Multi-Option = Vigor Shipyard • HM&E Repairs and Modernization (Shipalts) • IDIQ – Indefinite Delivery Indefinite Quantity = International Marine and Industrial Applicators, LLC (IMIA) • Preservation of Underwater Body, Freeboard, Catwalks, Tanks • Project Manager = Assistant Project Superintendent • SBS – Ship Building Specialist = Zone Manager • Contracting Officers Technical Representative • ACO – Administrative Contracting Officer • Warrant Holder
Overview • Estimated Total Man-days (MD’s) 61K • MSMO Repair 29K • IDIQ Preservation 32K • MSMO = Code 412 and Vigor Shipyards Inc. • HM&E Repairs & SCD/Alterations • IDIQ = Code 412 and IMIA • Hull, Tank, Vent Plenum Preservation • 4A1 Upkeep will start 2 June 2014 – landing area non-skid preservation, Boat Davit & B&A Crane weight tests
MSMO Major Repair Items • 2 Firemain Piping Repairs • 2 Weather Deck Drain Pipe Repairs • 2 Catapult Hydraulic Piping Repairs (NR 1 & 3) • 2 CAT Wing Void Piping Repairs • Replace FWD CHT Tank Diffuser Nozzle • Replace CHT System Cross Connect Valve • Modify Trash Compactor Cover • Replace Bridge Windows 08 Level • Replace Vent Inlet Screen 01-203-2 • Replace Fire Zone Boundary Door 03-148-6 • Weight Test 4 Ea Bi-Rail Bridge Cranes • Replace 2 Metal Joiner Doors • Replace Corroded Vent Heater • Lagging at Various Locations • Replace 148 SW Hoses in Weapons Magazines • AC #10 Motor/Pump Transition Replacement • Stern Dock Rubber Removals – Preservation • Replace all Fire Pump Recirc Piping • 12 Watertight Door Replacements • 6 AESS Trunk Repairs • 4 Fan Coil Unit Replacements • 13 Ventilation Ducting Repairs • 2 Catapult Drain Piping Repairs • JBD 3 Inaccessible Void Repairs • 4 CHT Piping Repairs • Replace Laminate in Wardrooms/CPO Mess • 15 Head Rehab • Hydro-blast 5 CHT Zones • Weight Test CIWS Safety Nets • Replace Fantail Portable Life-rails • Deck repair in Forward Galley • SPS-48 Radar Heat Exchanger Cleaning • Chill Water Piping Insulation • 48 Radar Heat Exchangers Cleaning • Stern Dock Bumper Repairs
MSMO Major Modernization Work NAVSEA - None screened TYCOM - • SCD 4502 ACE HP ACCUMULATOR GATE VALVE MOD • SCD 4757 REMOVAL OF FORWARD BOAT BOOMS • SCD 5687 UPGRADE GALLEY VENT CONTROL CABINET 2-169-0-Q • SCD 5857 AFFF SPRINKLING FOR ENCLOSED AIRCRAFT FUELING STATION (S/A 9391D) • SCD 5875 CAT LO SERVICE TANK MODS • SCD 6363 STEERING GEAR HYDRAULIC FILTER MOD • SCD 6486.1 SAFETY IMPROVEMENTS TO TRUNK SAFETY NETS (5 Weapons Spaces) • SCD 6486.2 SAFETY IMPROVEMENTS TO TRUNK SAFETY NETS (1&4 Shaft Alley Trunks) • SCD 7030 WEATHER OPENING DISPOSABLE FILTERS • SCD 7131 UPGRADE GALLEY VENT CONTROL CABINET 03-160-3-Q • SCD 9073 MEDICAL STERILIZER • S/A 9442 CAG/DCAG OFFICE EQOL – • Replace Galley Ovens in Aft Crews Galley (EQOL Alteration)