1 / 13

FEH Layout, Status

FEH Layout, Status. John Arthur – LCLS Expt’l Facilities Div June 3, 2009. LCLS new construction. Undulator Hall. Near Experimental Hall. Front End Enclosure. Far Experimental Hall. First LCLS FEL light at 1.5 Å. Gain vs undulator length at 1.5 Å. FEL gain length = 3.3 m.

tokala
Download Presentation

FEH Layout, Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FEH Layout, Status John Arthur – LCLS Expt’l Facilities Div June 3, 2009

  2. LCLS new construction Undulator Hall Near Experimental Hall Front End Enclosure Far Experimental Hall

  3. First LCLS FEL light at 1.5 Å

  4. Gain vs undulator length at 1.5 Å FEL gain length = 3.3 m FEL saturation indicated Pulse energy ~ 1 mJ

  5. The LCLS X-ray Beamline 3 Hutches X-ray transport tunnel Far Experimental Hall 3 Hutches Near Experimental Hall Front End Enclosure

  6. FEE Solid Attenuators Gas Attenuator Calorimeter Beam Direction Slit Gas Detectors K-Mono 5 mm collimator Direct Imager (Scintillator) FEL Offset Mirror Systems

  7. LCLS Offset Mirror Systems 800-2000 eV to Hutch 1 HOMS: Hard x-ray Offset Mirror System SOMS: Soft x-ray Offset Mirror System insertable 800-2000 eV to Hutch 2 Shadow Wall Wall 2 insertable 2000-25000 eV to Hutch 3-6

  8. Far Experimental Hall

  9. FEH Hutch Layout HPS control Roll-up door (interlocked) Online-offline status lights HPS door (one per hutch) PPS door (Tunnel entrance) Accelerator status lights (two places) PPS control (keybank, etc) exit

  10. FEH Hutch Layout Detail HPS control Roll-up door (interlocked) Online-offline status lights HPS door (one per hutch) Accelerator status lights (two places) 9 m 20 m

  11. FEH Hutch construction plan • Bids were well below estimates • Contract about to be signed • Steel frame procurement already under way • Construction finished Dec 2009 • CXI installation could start early 2010 • Basic services installed Feb 2010 • Network, PPS

  12. Open issues with hutches • PPS design needs to be finalized • Utilization of mezzanine • Cooling water system upgrade These issues will be easier to resolve when instrument designs are final

  13. Summary • LCLS works • FEH hutches will be ready in early 2010 • Operations support including User support is in place • Support staff being hired

More Related