An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TTC & BST Layout StatusMay 2007 • Overview and vocabulary • Common TTC fibres • Common BST fibres • TTC & BST fibres in the experiments • Conclusion & schedules LEADE, 07/05/2007

  2. OVERVIEW AB/RF Tx and Rx modules TTC Receiver Crates Optical fibres LEADE, 07/05/2007

  3. VOCABULARY 12 or 24 single mode fibres ribbon MINI-TUBES TUBE LEADE, 07/05/2007

  4. Overview and vocabulary • Common TTC fibres • Common BST fibres • TTC & BST fibres in the experiments • Cost Estimation • Schedules LEADE, 07/05/2007

  5. TTC fibres layout AB/RF Tx and Rx modules TTC Receiver Crates Optical fibres LEADE, 07/05/2007

  6. TTC fibres [SR4 to CMS] SR4 (2475) US45 3.5 km US45 UJ56 USC55 UJ56 LEADE, 07/05/2007

  7. TTC fibres [SR4 to CCR] SR4 (2475) 10 km CCC Prevessin CCR (874) CCC Telecom To SR2 (ALICE) To SR1 (ATLAS) To SR8 (LHCb) LEADE, 07/05/2007

  8. TTC fibres [CCR to SR1-2-8] CCC - Telecom 6 km, ready end of May 4 km 5 km SR8 - LHCb SR1 - ATLAS SR2 - ALICE LEADE, 07/05/2007

  9. Optical Power Budget 0.5 dB/km BST 1 dB SR4 RF SR4 LCR Tx=+0-1dBm Rx sensitivity -30dBm Rx min authorized power = -25dBm => Optical Power Budget: 25dB 0.2km CMS 3dB 2dB + 3dB +5dB = 10dB 3.5km Tx UJ56 US45 Tunnel SR4 SR4 RF SR4 SP ALICE SR1,2,4 10km 2.5dB + 6dB +4dB= 12.5dB 0.2km 5km 6dB 0.2km ATLAS 4km Tx Rx 2dB + 6dB +4dB= 12dB 6km 0.2km CCC Telecom LHCb CCR MONITORING CCR Signal regeneration 3dB + 6dB +4dB= 13dB LEADE, 07/05/2007

  10. Overview and vocabulary • Common TTC fibres • Common BST fibres • TTC & BST fibres in the experiments • Conclusion & schedules LEADE, 07/05/2007

  11. BST fibres layout BST Master / transmitters TTC Receiver Crates Optical fibres LEADE, 07/05/2007

  12. BST fibres [CCR to SR 1-2-5-8] CCC Prevessin CCR (874) CCC Telecom 4 km 5 km 10 km 6 km SR1 - ATLAS SR5 - CMS SR8 - LHCb SR2 - ALICE LEADE, 07/05/2007

  13. Overview and vocabulary • Common TTC fibres • Common BST fibres • TTC & BST fibres in the experiments • Conclusion & schedules LEADE, 07/05/2007

  14. TTC & BST inside the experiments • Fibre installation and patching directly done between experiments and TS/EL (Nicolas Zaganidis in charge of the TTC/BST fibre installation campaign) • For ALICE and LHCb, the 9 fibres are included in their fibres installation scheme • For ATLAS and CMS, the installation has been requested by PH/ESS in the framework of the TTC/BST installation • To be paid by each experiment LEADE, 07/05/2007

  15. Overview and vocabulary • Common TTC fibres • Common BST fibres • TTC & BST fibres in the experiments • Conclusion & schedules LEADE, 07/05/2007

  16. CONCLUSION & SCHEDULE • Schedules: • The general infrastructure can be ready for mid-July (-> SR) • except LHCb (civil engineering required) • The special installations in the experiments may take some more time. Everything should be ready for end of September. • Cost: • An estimation will be sent to the experiments during the week Fibres to be blown June 07 Patches to be installed Sept 07 LEADE, 07/05/2007

  17. TTC & BST fibres [synoptics] LEADE, 07/05/2007

  18. TTC & BST fibres [synoptics] LEADE, 07/05/2007