1 / 11

Continuous Gas-Lift Optimization: Offshore Gulf of Mexico

Continuous Gas-Lift Optimization: Offshore Gulf of Mexico. April 13, 2005. Introduction. Background Technical Description Field Criteria Method Costs Qualifications Conclusion. Background. SS 208—50 miles off coast of LA 90% of wells on continuous gas-lift

trinh
Download Presentation

Continuous Gas-Lift Optimization: Offshore Gulf of Mexico

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Continuous Gas-Lift Optimization: Offshore Gulf of Mexico April 13, 2005

  2. Introduction • Background • Technical Description • Field Criteria • Method • Costs • Qualifications • Conclusion

  3. Background • SS 208—50 miles off coast of LA • 90% of wells on continuous gas-lift • Limited injection gas fluctuates • Inefficient process to optimize gas-lift

  4. Technical Description • Constant Gas-Lift Injection Rate • Real Time Wellhead Surveillance • Optimization Well Tests • Data to Desktop

  5. Field Criteria • Proper gas-lift equipment • Inadequate data gathering from wells • Need to decrease operating costs

  6. Method • New hardware on: • Wellhead • Gas-Lift Header • Test Separator • Computer hardware and software

  7. Costs • Total Cost = $860,000

  8. Qualifications • Internship with UNOCAL at SS 208 • Production Engineering course on gas-lift

  9. Conclusion • Similar field success • Next step • Questions

More Related